REMOVING CONC (MISC)
|
SY
|
9.000
|
$80.000
|
$120.000
|
$500.000
|
$1,746.100
|
|
|
REMOVING CONC (PILE ENCASEMENT)
|
CY
|
14.600
|
$350.000
|
$800.000
|
$1,000.000
|
$1,034.600
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
105.000
|
$45.000
|
$60.000
|
$100.000
|
$520.000
|
|
|
CL C CONC (PILE ENCASEMENT)
|
CY
|
9.600
|
$750.000
|
$4,200.000
|
$5,000.000
|
$6,000.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
38.000
|
$700.000
|
$3,200.000
|
$1,500.000
|
$5,000.000
|
|
|
CL C CONC (MISC)
|
CY
|
0.900
|
$1,582.000
|
$30,000.000
|
$10,000.000
|
$20,000.000
|
|
|
CL C CONC(PILE ENCASEMENT)(UNDERWATER)
|
LF
|
52.000
|
$1,050.000
|
$1,200.000
|
$3,000.000
|
$5,000.000
|
|
|
CONC STR REPAIR (EPOXY MORTAR)
|
SF
|
10.000
|
$570.000
|
$300.000
|
$500.000
|
$750.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
98.000
|
$200.000
|
$280.000
|
$500.000
|
$150.000
|
|
|
CONC STR REPAIR (STANDARD)
|
SF
|
60.000
|
$200.000
|
$260.000
|
$500.000
|
$150.000
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL3)
|
LF
|
495.000
|
$30.000
|
$70.000
|
$100.000
|
$45.000
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL7)
|
LF
|
1,661.000
|
$65.000
|
$65.000
|
$100.000
|
$41.500
|
|
|
HEADER TYPE EXPANSION JOINT
|
LF
|
255.000
|
$150.000
|
$500.000
|
$100.000
|
$77.500
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$119,062.000
|
$175,000.000
|
$200,000.000
|
$240,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$3,500.000
|
$6,000.000
|
$8,500.000
|
$67,000.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
2,250.000
|
$30.000
|
$120.000
|
$95.000
|
$72.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
2,250.000
|
$6.000
|
$15.000
|
$20.000
|
$7.300
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
2,250.000
|
$8.000
|
$15.000
|
$30.000
|
$10.300
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
5.000
|
$2,500.000
|
$5,000.000
|
$6,500.000
|
$3,196.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
5.000
|
$1,000.000
|
$5,000.000
|
$2,500.000
|
$2,130.400
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
5.000
|
$28,000.000
|
$7,000.000
|
$30,000.000
|
$40,000.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
3,390.000
|
$1.000
|
$3.000
|
$2.000
|
$1.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
6,030.000
|
$0.540
|
$3.000
|
$3.000
|
$1.250
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
48.000
|
$13.500
|
$200.000
|
$20.000
|
$4.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
2,195.000
|
$0.540
|
$2.000
|
$2.000
|
$1.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
6,400.000
|
$0.540
|
$4.000
|
$3.000
|
$1.250
|
|
|
WK ZN PAV MRK REMOV (REFL) TY I-C
|
LF
|
2,250.000
|
$0.750
|
$4.000
|
$2.000
|
$4.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
LF
|
4,690.000
|
$0.750
|
$4.000
|
$2.000
|
$4.000
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY W
|
LF
|
2,100.000
|
$4.290
|
$5.000
|
$2.000
|
$2.000
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
|
LF
|
345.000
|
$0.800
|
$5.000
|
$2.000
|
$2.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
3,772.000
|
$0.200
|
$3.000
|
$2.000
|
$0.200
|
|
|
PAVEMENT SEALER 6"
|
LF
|
1,840.000
|
$0.300
|
$3.000
|
$3.000
|
$0.300
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
|
LF
|
140.000
|
$0.850
|
$20.000
|
$2.000
|
$0.600
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
2,680.000
|
$1.000
|
$10.000
|
$2.000
|
$0.600
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
|
LF
|
1,800.000
|
$1.100
|
$5.000
|
$3.000
|
$0.700
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
480.000
|
$1.600
|
$20.000
|
$2.000
|
$0.600
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
1,880.000
|
$0.750
|
$10.000
|
$2.000
|
$0.600
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
15,794.000
|
$0.300
|
$2.000
|
$2.000
|
$0.250
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
1,800.000
|
$0.450
|
$5.000
|
$3.000
|
$0.450
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
40.000
|
$3.300
|
$20.000
|
$20.000
|
$1.500
|
|
|
TEMP TRAF SIGNALS
|
EA
|
2.000
|
$25,000.000
|
$6,000.000
|
$6,500.000
|
$50,000.000
|
|
|
CONCRETE RAIL REPAIR (IN-KIND)
|
LF
|
16.000
|
$510.000
|
$700.000
|
$500.000
|
$584.600
|
|
|
CNC CRACK REPAIR (DISCRETE)(INJECT)
|
LF
|
612.000
|
$80.000
|
$55.000
|
$100.000
|
$20.200
|
|
|
BRIDGE JOINT REPAIR (ARMOR)
|
LF
|
36.000
|
$612.000
|
$500.000
|
$1,000.000
|
$559.600
|
|
|
BRIDGE JOINT REPLACEMENT (ARMOR)
|
LF
|
240.000
|
$670.000
|
$500.000
|
$1,250.000
|
$466.200
|
|
|
THERMOPLASTIC PIPE (PP) (24")
|
LF
|
94.000
|
$75.000
|
$80.000
|
$500.000
|
$115.900
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
10.000
|
$15,000.000
|
$4,000.000
|
$150.000
|
$20,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
100.000
|
$250.000
|
$200.000
|
$250.000
|
$32.400
|
|
Totals: |
$1,214,676.900
|
$1,727,474.000
|
$2,040,452.000
|
$2,489,762.660
|