Bid Cobra

JASPER US0096 (6488-31-001)

Items: 31

County: JASPER
Length: 0.0100 MILES
Highway: US0096
District: BEAUMONT
Control Number: 6488-31-001
DBE Goal: 0.0%
Project: BPM - A00217091
Guaranty: $46,000.00
Time: 39 WORKING DAYS
Engineer's Estimate: $2,126,165.06
Date: 08/05/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8264001
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00217091
Project Description: MISC. BRIDGE REPAIRS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 2 files available
Bidders (8)
E
Engineer's Estimate
$2,126,165.06
$1,880,325.00
Over/Under Est: -11.56% -$245,840.06
$1,888,415.00
Over/Under Est: -11.18% -$237,750.06
Amt Left: 0.43% $8,090.00
Over/Under Est: 11.63% $247,305.94
Amt Left: 26.23% $493,146.00
Delta: -25.69% -$485,056.00
Over/Under Est: 16.23% $345,112.34
Amt Left: 31.43% $590,952.40
Delta: -4.12% -$97,806.40
Over/Under Est: 22.51% $478,617.74
Amt Left: 38.53% $724,457.80
Delta: -5.40% -$133,505.40
Over/Under Est: 31.39% $667,348.19
Amt Left: 48.57% $913,188.25
Delta: -7.25% -$188,730.45
Over/Under Est: 56.23% $1,195,479.94
Amt Left: 76.65% $1,441,320.00
Delta: -18.91% -$528,131.75
Over/Under Est: 69.17% $1,470,579.94
Amt Left: 91.28% $1,716,420.00
Delta: -8.28% -$275,100.00

Bid Items & Bid Tabulations

31 Total 0 of 31
JASPER  |  US0096  |  BEAUMONT  |  6488-31-001  |  08/05/2026 1:00 PM CDT  |  $2,126,165.06  |  BPM - A00217091  |  BRIDGE PREVENT MAINT  |  39 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PATHFIELD INVESTMENTS LLC
ISI CONTRACTING, INC.
GARRET SHIELDS INFRASTRUCTURE
SCR CIVIL CONSTRUCTION, LLC
RAGLE CONSTRUCTION, INC.
STRUCTURAL INTEGRITY GROUP LLC
BLACKSMITH VENTURES LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
REMOV CONC (RIPRAP)
CY 21.000 $240.000 $350.000 $79.000 $100.000 $1,135.000 $160.000 $500.000 $600.000 $150.000
REMOV CONC (PILE ENCASEMENT)
CY 5.000 $300.000 $3,000.000 $2,203.000 $500.000 $7,310.000 $1,600.000 $575.000 $12,000.000 $1,400.000
EMBANK (FNL)(OC)(TY C)
CY 20.000 $25.000 $95.000 $51.000 $40.000 $155.000 $250.000 $52.000 $300.000 $100.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 3,200.000 $15.700 $40.000 $55.000 $30.000 $35.000 $27.000 $77.000 $25.000 $25.000
CL A CONC (PLUG)
EA 1.000 $2,500.000 $2,000.000 $3,292.000 $1,000.000 $4,300.000 $4,900.000 $7,850.000 $10,000.000 $3,000.000
CL C CONC (COLLAR)
EA 16.000 $1,400.000 $1,500.000 $3,250.000 $1,000.000 $3,955.000 $2,300.000 $3,160.000 $7,500.000 $3,000.000
CL K CONCRETE (PEDESTAL)
EA 2.000 $2,500.000 $2,500.000 $5,993.000 $6,000.000 $2,700.000 $1,805.000 $5,800.000 $15,000.000 $10,000.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 1,507.000 $130.000 $170.000 $127.000 $200.000 $113.000 $150.000 $154.000 $180.000 $350.000
CONC STR REPAIR (STANDARD)
SF 1,027.000 $100.000 $150.000 $111.000 $150.000 $113.000 $150.000 $154.000 $180.000 $300.000
RIPRAP (CONC)(5 IN)
CY 22.000 $750.000 $1,600.000 $1,018.000 $600.000 $1,335.000 $1,006.000 $645.000 $1,500.000 $800.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 65.000 $180.000 $200.000 $170.000 $200.000 $800.000 $300.000 $360.000 $500.000 $350.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 960.000 $210.000 $210.000 $180.000 $300.000 $680.000 $253.000 $360.000 $750.000 $300.000
ELASTOMERIC BEARING (PLAIN)
EA 2.000 $2,000.000 $5,000.000 $1,441.000 $3,000.000 $1,000.000 $522.000 $1,375.000 $3,000.000 $5,000.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 1,419.000 $50.000 $45.000 $20.000 $40.000 $32.000 $25.000 $37.000 $45.000 $120.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 22,429.000 $38.000 $28.000 $26.000 $40.000 $24.000 $25.000 $40.000 $40.000 $50.000
MULTI-LAYER POLYMER OVERLAY
SY 583.000 $45.000 $50.000 $52.000 $60.000 $70.000 $34.100 $49.500 $110.000 $240.000
STR STEEL (MISCELLANEOUS BRIDGE)
LB 5.000 $2,000.000 $1,100.000 $964.000 $1,000.000 $1,100.000 $1,650.000 $936.000 $1,200.000 $800.000
STR STEEL (PEDESTAL)
LB 1,395.000 $15.840 $30.000 $32.000 $30.000 $43.000 $22.000 $31.250 $60.000 $75.000
HEADER TYPE EXPANSION JOINT
LF 92.000 $365.000 $270.000 $306.000 $150.000 $210.000 $93.000 $295.000 $800.000 $150.000
SHOT BLASTING
SY 583.000 $4.000 $10.000 $25.000 $5.000 $16.000 $3.500 $4.000 $40.000 $10.000
RAISING EXIST STRUCT
LS 3.000 $66,668.000 $14,000.000 $31,833.000 $50,000.000 $16,000.000 $152,000.000 $49,400.000 $36,000.000 $75,000.000
MOBILIZATION
LS 1.000 $241,000.000 $150,000.000 $140,000.000 $200,000.000 $246,000.000 $260,000.000 $279,000.000 $325,000.000 $305,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $4,200.000 $1,500.000 $8,885.000 $5,000.000 $48,000.000 $100,000.000 $48,500.000 $12,000.000 $34,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $2,000.000 $5,024.000 $1,000.000 $7,000.000 $15,000.000 $8,000.000 $15,000.000 $10,000.000
TMA (STATIONARY)
DAY 37.000 $250.000 $150.000 $2,530.000 $1,000.000 $450.000 $750.000 $1,010.000 $400.000 $350.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 30.000 $0.750 $4.000 $20.000 $2.000 $2.500 $2.000 $4.000 $100.000 $50.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 40.000 $0.680 $10.000 $20.000 $1.000 $1.250 $5.000 $2.500 $60.000 $50.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 141.000 $0.570 $4.000 $20.000 $5.000 $1.200 $5.000 $2.500 $30.000 $40.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 141.000 $0.590 $4.000 $20.000 $1.000 $1.200 $5.000 $2.500 $30.000 $40.000
REFL PAV MRKR TY II-C-R
EA 2.000 $6.000 $150.000 $20.000 $5.000 $20.000 $10.000 $500.000 $500.000 $30.000
REMOVE LEAD-CONTAINING COATING (OTHER)
LS 1.000 $2,000.000 $20,000.000 $10,000.000 $10,000.000 $12,500.000 $50,000.000 $2,250.000 $15,000.000 $20,000.000
Totals: $2,126,165.060 $1,880,325.000 $1,888,415.000 $2,373,471.000 $2,471,277.400 $2,604,782.800 $2,793,513.250 $3,321,645.000 $3,596,745.000