KAUFMAN US 80 (0095-04-079)
Items: 29
County: KAUFMAN
Length: 0.0590 MILES (0.0509 MILES)
Highway: US 80
District: DALLAS
Control Number: 0095-04-079
DBE Goal: 0.0%
Project: F 2026(859)
Guaranty: $22,000.00
Time: 35 WORKING DAYS
Engineer's Estimate: $1,290,272.50
Date: 08/05/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263038
Type: BRIDGE MAINTENANCE
Project ID: A00217911
Contract Type: FEDERAL
Project Description: STABILIZE ERODED CHANNEL BANKS AND INSTALL STONE RIPRAP WITHIN THE CHANNEL AND AROUND BRIDGE BENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
NICHOLAS WADLINGTON
CODY JOLLEY
KAUFMAN US 80 (0095-04-079)
Project Name: N/A
Project: F 2026(859)
Engineer's Estimate: $1,290,272.50
Length: 0.0580 MILES (0.0509 MILES)
Project Class: BRIDGE MAINTENANCE
Limits From: AT BIG BRUSHY CREEK
Limits To: .
Project Description: STABILIZE ERODED CHANNEL BANKS AND INSTALL STONE RIPRAP WITHIN THE CHANNEL AND AROUND BRIDGE BENTS
Bidders (10)
E
Engineer's Estimate
$1,290,272.50
1
Awarded
$799,617.05
Over/Under Est:
-38.03%
-$490,655.45
$833,943.20
Over/Under Est:
-35.37%
-$456,329.30
Amt Left:
4.29%
$34,326.15
$1,032,635.00
Over/Under Est:
-19.97%
-$257,637.50
Amt Left:
29.14%
$233,017.95
Delta:
-23.83%
-$198,691.80
$1,075,319.55
Over/Under Est:
-16.66%
-$214,952.95
Amt Left:
34.48%
$275,702.50
Delta:
-4.13%
-$42,684.55
$1,115,554.60
Over/Under Est:
-13.54%
-$174,717.90
Amt Left:
39.51%
$315,937.55
Delta:
-3.74%
-$40,235.05
$1,152,052.22
Over/Under Est:
-10.71%
-$138,220.28
Amt Left:
44.08%
$352,435.17
Delta:
-3.27%
-$36,497.62
$1,178,670.00
Over/Under Est:
-8.65%
-$111,602.50
Amt Left:
47.4%
$379,052.95
Delta:
-2.31%
-$26,617.78
$1,278,223.60
Over/Under Est:
-0.93%
-$12,048.90
Amt Left:
59.85%
$478,606.55
Delta:
-8.45%
-$99,553.60
$1,287,749.20
Over/Under Est:
-0.2%
-$2,523.30
Amt Left:
61.05%
$488,132.15
Delta:
-0.75%
-$9,525.60
$1,795,935.56
Over/Under Est:
39.19%
$505,663.06
Amt Left:
124.6%
$996,318.51
Delta:
-39.46%
-$508,186.36
Bid Items & Bid Tabulations
29
Total
0 of 29
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $30,000.00 |