REMOVING CONC (RIPRAP)
|
SY
|
20.000
|
$15.000
|
$19.000
|
$20.000
|
$40.000
|
$18.000
|
$36.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
2,237.000
|
$15.000
|
$19.000
|
$30.000
|
$40.000
|
$18.000
|
$37.000
|
|
|
REMOVING CONC (CURB)
|
LF
|
14,599.000
|
$6.000
|
$5.400
|
$12.000
|
$16.600
|
$5.000
|
$12.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (2"-6")
|
SY
|
1,111.000
|
$10.000
|
$10.250
|
$20.000
|
$12.000
|
$21.300
|
$15.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
82.180
|
$180.000
|
$188.000
|
$200.000
|
$175.000
|
$164.070
|
$430.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
7,301.000
|
$1.500
|
$1.350
|
$3.000
|
$7.400
|
$0.500
|
$2.000
|
|
|
BLOCK SODDING
|
SY
|
7,301.000
|
$4.100
|
$6.500
|
$6.000
|
$5.250
|
$7.080
|
$7.000
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
7,301.000
|
$0.750
|
$0.420
|
$0.400
|
$0.600
|
$1.480
|
$0.410
|
|
|
VEGETATIVE WATERING
|
MG
|
2,180.000
|
$5.000
|
$0.010
|
$20.000
|
$42.000
|
$0.100
|
$21.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
858.000
|
$50.000
|
$65.000
|
$65.000
|
$81.000
|
$90.000
|
$81.000
|
|
|
PLANE ASPH CONC PAV(0" TO 3")
|
SY
|
11,990.000
|
$3.000
|
$2.200
|
$5.000
|
$2.500
|
$3.500
|
$5.000
|
|
|
FULL-DEPTH REPAIR CRCP (8"-10")
|
SY
|
7,036.000
|
$215.000
|
$213.000
|
$200.000
|
$191.500
|
$205.000
|
$225.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
32.000
|
$10.000
|
$10.250
|
$40.000
|
$30.000
|
$10.000
|
$68.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
3.000
|
$500.000
|
$820.000
|
$1,000.000
|
$835.000
|
$700.000
|
$1,000.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
4.000
|
$100.000
|
$450.000
|
$200.000
|
$650.000
|
$400.000
|
$200.000
|
|
|
RC PIPE (CL III)(21 IN)
|
LF
|
6.000
|
$130.000
|
$477.000
|
$200.000
|
$444.000
|
$425.000
|
$405.000
|
|
|
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
|
EA
|
1.000
|
$5,250.000
|
$6,800.000
|
$6,000.000
|
$6,000.000
|
$6,100.000
|
$8,000.000
|
|
|
INLET (COMPL)(CURB)(TY C1)
|
EA
|
1.000
|
$8,500.000
|
$8,100.000
|
$6,000.000
|
$9,650.000
|
$7,300.000
|
$9,500.000
|
|
|
ADJUSTING INLETS
|
EA
|
28.000
|
$3,000.000
|
$3,350.000
|
$4,000.000
|
$6,550.000
|
$3,100.000
|
$3,300.000
|
|
|
ADJUSTING INLET (CAP)
|
EA
|
2.000
|
$1,500.000
|
$2,650.000
|
$4,000.000
|
$4,500.000
|
$2,500.000
|
$3,400.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$430,850.770
|
$554,116.000
|
$580,000.000
|
$600,000.000
|
$600,000.000
|
$391,218.350
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$15,000.000
|
$23,000.000
|
$10,000.000
|
$5,000.000
|
$32,000.000
|
$12,500.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
63.000
|
$40.000
|
$41.000
|
$40.000
|
$65.000
|
$40.000
|
$41.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
63.000
|
$15.000
|
$12.300
|
$10.000
|
$25.000
|
$12.000
|
$13.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
877.000
|
$4.000
|
$4.110
|
$4.000
|
$4.400
|
$4.000
|
$4.100
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
877.000
|
$1.000
|
$0.260
|
$0.250
|
$1.250
|
$0.250
|
$0.300
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
2,741.000
|
$4.800
|
$6.200
|
$3.000
|
$5.000
|
$6.000
|
$7.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
2,741.000
|
$1.200
|
$1.040
|
$0.500
|
$1.200
|
$1.000
|
$1.150
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
14,599.000
|
$28.000
|
$45.000
|
$37.000
|
$37.500
|
$41.000
|
$24.000
|
|
|
INTERSECTIONS (CONC)
|
SY
|
622.000
|
$220.000
|
$104.000
|
$175.000
|
$99.000
|
$93.000
|
$140.000
|
|
|
INTERSECTIONS (ACP)
|
SY
|
676.000
|
$80.000
|
$47.000
|
$75.000
|
$52.500
|
$61.000
|
$185.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
435.000
|
$80.000
|
$64.000
|
$78.000
|
$70.000
|
$110.000
|
$263.000
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
1,615.000
|
$100.000
|
$100.000
|
$140.000
|
$98.000
|
$90.000
|
$160.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
10.000
|
$300.000
|
$268.000
|
$275.000
|
$375.000
|
$350.000
|
$350.000
|
|
|
MAILBOX INSTALL-D (TWW-POST) TY 4
|
EA
|
2.000
|
$330.000
|
$322.000
|
$285.500
|
$428.000
|
$400.000
|
$400.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
2.000
|
$700.000
|
$780.000
|
$760.000
|
$860.000
|
$800.000
|
$800.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
54.000
|
$750.000
|
$673.000
|
$815.250
|
$700.000
|
$650.000
|
$650.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
30.000
|
$800.000
|
$845.000
|
$905.750
|
$910.000
|
$850.000
|
$850.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
1.000
|
$1,500.000
|
$1,015.000
|
$1,105.000
|
$1,040.000
|
$970.000
|
$970.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
5.000
|
$1,100.000
|
$1,175.000
|
$1,190.000
|
$1,230.000
|
$1,150.000
|
$1,150.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
3.000
|
$1,150.000
|
$1,185.000
|
$1,290.000
|
$1,180.000
|
$1,100.000
|
$1,100.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
|
EA
|
1.000
|
$1,400.000
|
$1,485.000
|
$1,410.000
|
$1,480.000
|
$1,385.000
|
$1,385.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$750.000
|
$755.000
|
$695.000
|
$675.000
|
$630.000
|
$650.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
90.000
|
$150.000
|
$85.000
|
$75.000
|
$21.000
|
$20.000
|
$22.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
2,851.000
|
$2.000
|
$1.100
|
$4.000
|
$1.700
|
$0.550
|
$1.300
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
554.000
|
$1.500
|
$1.100
|
$4.000
|
$1.700
|
$0.570
|
$1.300
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
2,216.000
|
$1.500
|
$1.000
|
$0.910
|
$1.050
|
$1.100
|
$1.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
768.000
|
$9.500
|
$6.400
|
$6.100
|
$7.000
|
$10.000
|
$7.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
26.000
|
$150.000
|
$123.000
|
$120.000
|
$150.000
|
$125.000
|
$132.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
18.000
|
$185.000
|
$128.000
|
$124.000
|
$185.000
|
$200.000
|
$135.000
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
|
EA
|
192.000
|
$45.000
|
$36.000
|
$35.000
|
$32.000
|
$20.000
|
$38.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
4,128.000
|
$0.700
|
$0.620
|
$0.600
|
$1.050
|
$0.800
|
$0.700
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
15,189.000
|
$0.600
|
$0.560
|
$0.540
|
$0.550
|
$0.520
|
$0.600
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
420.000
|
$0.650
|
$1.050
|
$1.000
|
$1.050
|
$1.000
|
$1.100
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
15,657.000
|
$0.650
|
$0.570
|
$0.540
|
$0.550
|
$0.550
|
$0.600
|
|
REFL PAV MRKR TY I-C
|
EA
|
321.000
|
$6.000
|
$4.120
|
$4.000
|
$4.250
|
$4.000
|
$4.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
140.000
|
$6.500
|
$4.120
|
$4.000
|
$4.250
|
$6.000
|
$4.500
|
|
|
FULL - WIDTH MOWING
|
CYC
|
3.000
|
$5,000.000
|
$2,035.000
|
$2,500.000
|
$700.000
|
$3,000.000
|
$4,500.000
|
|
|
DRAIN INLET CLEANING
|
EA
|
49.000
|
$500.000
|
$615.000
|
$350.000
|
$580.000
|
$200.000
|
$300.000
|
|
|
CAM (ASPHALT) PG(76-22)
|
TON
|
333.400
|
$155.000
|
$200.000
|
$208.000
|
$208.000
|
$210.000
|
$225.000
|
|
|
CAM (AGGREGATE)
|
TON
|
4,162.820
|
$140.000
|
$200.000
|
$208.000
|
$208.000
|
$210.000
|
$225.000
|
|
|
MEMBRANE UNDERSEAL
|
GAL
|
14,044.000
|
$5.500
|
$3.900
|
$4.000
|
$4.000
|
$4.500
|
$4.500
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
8,058.010
|
$110.000
|
$130.000
|
$130.000
|
$130.000
|
$151.000
|
$150.000
|
|
|
TACK COAT
|
GAL
|
7,745.000
|
$4.000
|
$0.010
|
$0.010
|
$0.010
|
$1.000
|
$1.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
5.000
|
$12,000.000
|
$7,400.000
|
$7,500.000
|
$10,000.000
|
$200.000
|
$10,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
134.000
|
$250.000
|
$258.000
|
$150.000
|
$120.000
|
$305.000
|
$300.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
240.000
|
$100.000
|
$0.010
|
$75.000
|
$60.000
|
$10.000
|
$150.000
|
|
Totals: |
$5,211,158.470
|
$5,861,108.950
|
$5,979,863.660
|
$5,999,925.660
|
$6,083,861.053
|
$6,294,294.310
|