PREPARING ROW
|
STA
|
378.000
|
$900.000
|
$1,030.000
|
$220.000
|
$858.000
|
$675.805
|
$500.000
|
$500.000
|
$700.000
|
$1,165.500
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
316.000
|
$17.830
|
$19.200
|
$16.020
|
$25.000
|
$24.236
|
$62.200
|
$50.000
|
$30.000
|
$36.300
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
554.000
|
$15.330
|
$14.400
|
$16.020
|
$25.000
|
$21.058
|
$57.300
|
$50.000
|
$30.000
|
$36.300
|
|
|
REMOVING STAB BASE & ASPH PAV (0-6")
|
SY
|
679.000
|
$10.950
|
$14.700
|
$8.450
|
$6.000
|
$11.513
|
$14.100
|
$25.000
|
$20.000
|
$7.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (10")
|
SY
|
11,538.000
|
$13.850
|
$10.500
|
$14.700
|
$14.000
|
$4.740
|
$4.550
|
$30.000
|
$15.500
|
$16.400
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
11,822.000
|
$24.880
|
$10.300
|
$28.120
|
$41.000
|
$24.506
|
$20.050
|
$30.000
|
$75.000
|
$87.500
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
2,622.000
|
$40.000
|
$11.300
|
$23.560
|
$28.000
|
$31.653
|
$19.200
|
$35.000
|
$20.000
|
$115.500
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
78,835.000
|
$4.970
|
$0.920
|
$1.830
|
$1.600
|
$1.252
|
$4.450
|
$2.000
|
$8.000
|
$3.380
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
78,835.000
|
$0.630
|
$0.290
|
$0.330
|
$0.200
|
$0.291
|
$0.300
|
$0.300
|
$0.200
|
$0.280
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
39,418.000
|
$0.200
|
$0.160
|
$0.110
|
$0.200
|
$0.198
|
$0.200
|
$0.200
|
$0.150
|
$0.190
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
39,418.000
|
$0.200
|
$0.160
|
$0.110
|
$0.200
|
$0.198
|
$0.200
|
$0.200
|
$0.150
|
$0.190
|
|
|
VEGETATIVE WATERING
|
MG
|
1,230.000
|
$143.830
|
$31.500
|
$30.800
|
$57.000
|
$27.553
|
$16.500
|
$25.000
|
$60.000
|
$28.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
78,835.000
|
$3.030
|
$0.950
|
$1.820
|
$1.000
|
$1.716
|
$1.650
|
$2.000
|
$1.200
|
$1.650
|
|
|
PROOF ROLLING
|
HR
|
105.000
|
$67.500
|
$39.200
|
$71.500
|
$122.000
|
$98.440
|
$150.500
|
$100.000
|
$95.000
|
$156.000
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
8,987.000
|
$80.100
|
$97.000
|
$74.930
|
$98.000
|
$222.867
|
$132.250
|
$140.000
|
$108.000
|
$134.640
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
5,802.000
|
$10.000
|
$7.300
|
$6.350
|
$5.750
|
$5.115
|
$9.050
|
$7.000
|
$5.000
|
$12.500
|
|
|
AGGR(TY-PD GR-4 SAC-B)
|
CY
|
985.000
|
$264.320
|
$148.000
|
$121.580
|
$150.000
|
$115.774
|
$222.250
|
$140.000
|
$250.000
|
$174.210
|
|
|
AGGR (TY-PD GR-3 OR TY-PL GR-3)
|
CY
|
310.000
|
$311.500
|
$347.000
|
$260.780
|
$150.000
|
$175.705
|
$449.500
|
$300.000
|
$400.000
|
$238.700
|
|
|
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
|
GAL
|
46,646.000
|
$4.740
|
$6.000
|
$4.040
|
$5.100
|
$4.729
|
$5.700
|
$5.000
|
$6.000
|
$6.800
|
|
|
STRUCT EXCAV (PIPE)
|
CY
|
50.000
|
$34.880
|
$32.900
|
$7.820
|
$22.500
|
$36.400
|
$100.500
|
$100.000
|
$55.000
|
$72.590
|
|
|
CUT & RESTORING PAV
|
SY
|
45.000
|
$254.340
|
$94.900
|
$159.500
|
$33.000
|
$117.700
|
$100.500
|
$125.000
|
$200.000
|
$186.220
|
|
|
FLOWABLE BACKFILL
|
CY
|
16.000
|
$433.330
|
$339.000
|
$330.000
|
$205.000
|
$260.000
|
$276.500
|
$300.000
|
$300.000
|
$262.340
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
64.000
|
$25.000
|
$13.300
|
$60.500
|
$35.000
|
$26.000
|
$42.700
|
$50.000
|
$5.000
|
$134.520
|
|
|
TEMPORARY SPL SHORING
|
SF
|
628.000
|
$47.060
|
$20.000
|
$82.500
|
$46.000
|
$26.750
|
$100.500
|
$100.000
|
$35.000
|
$33.240
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
4.000
|
$435.830
|
$1,110.000
|
$1,320.000
|
$1,355.000
|
$728.000
|
$1,130.000
|
$1,200.000
|
$1,000.000
|
$791.420
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
113.000
|
$435.830
|
$837.000
|
$880.000
|
$790.000
|
$583.150
|
$754.000
|
$850.000
|
$1,000.000
|
$679.210
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
17.000
|
$94.260
|
$185.000
|
$308.170
|
$138.000
|
$314.580
|
$175.750
|
$200.000
|
$225.000
|
$274.180
|
|
|
CMP AR (GAL STL DES 3)
|
LF
|
19.000
|
$166.430
|
$361.000
|
$321.610
|
$226.000
|
$474.010
|
$377.000
|
$425.000
|
$275.000
|
$346.860
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
68.000
|
$146.560
|
$174.000
|
$163.640
|
$173.000
|
$212.930
|
$271.500
|
$300.000
|
$200.000
|
$186.620
|
|
|
HEADWALL (CH - FW - A - 0) (DES= 3)
|
EA
|
2.000
|
$6,502.180
|
$5,240.000
|
$10,450.000
|
$7,150.000
|
$5,189.500
|
$3,420.000
|
$4,000.000
|
$10,000.000
|
$6,959.140
|
|
|
HEADWALL (CH - PW - S) (DIA= 24 IN)
|
EA
|
1.000
|
$6,502.180
|
$9,290.000
|
$6,050.000
|
$10,650.000
|
$7,039.950
|
$3,170.000
|
$3,500.000
|
$15,000.000
|
$8,534.220
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
1.000
|
$3,143.300
|
$2,890.000
|
$3,850.000
|
$1,980.000
|
$3,531.000
|
$2,310.000
|
$3,000.000
|
$5,000.000
|
$4,248.420
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$3,096.900
|
$4,250.000
|
$4,950.000
|
$1,770.000
|
$3,600.550
|
$2,510.000
|
$3,000.000
|
$5,000.000
|
$4,976.840
|
|
|
SET (TY II) (DES 3) (CMP) (4: 1) (C)
|
EA
|
2.000
|
$1,900.000
|
$2,140.000
|
$3,850.000
|
$2,055.000
|
$2,284.450
|
$2,510.000
|
$3,000.000
|
$4,500.000
|
$3,182.270
|
|
|
REMOV STR (SET)
|
EA
|
3.000
|
$1,224.520
|
$344.000
|
$1,650.000
|
$1,029.000
|
$1,658.500
|
$276.500
|
$2,000.000
|
$1,000.000
|
$1,292.330
|
|
|
REMOV STR (PIPE)
|
LF
|
65.000
|
$116.600
|
$22.600
|
$49.500
|
$29.000
|
$21.400
|
$50.300
|
$100.000
|
$50.000
|
$59.650
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$714,332.960
|
$450,000.000
|
$567,322.760
|
$449,000.000
|
$581,973.317
|
$445,000.000
|
$625,000.000
|
$625,000.000
|
$716,249.480
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
18.000
|
$8,596.120
|
$8,700.000
|
$7,289.150
|
$3,200.000
|
$5,388.432
|
$17,960.000
|
$30,000.000
|
$12,000.000
|
$8,828.520
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
124.000
|
$44.000
|
$42.400
|
$44.550
|
$44.500
|
$42.120
|
$40.700
|
$50.000
|
$48.000
|
$40.500
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,228.000
|
$46.290
|
$50.900
|
$47.300
|
$53.500
|
$44.200
|
$42.700
|
$50.000
|
$43.000
|
$42.500
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,352.000
|
$17.700
|
$21.200
|
$2.200
|
$22.250
|
$9.235
|
$8.900
|
$10.000
|
$23.000
|
$8.880
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$15.430
|
$42.400
|
$5.500
|
$44.500
|
$23.556
|
$22.750
|
$25.000
|
$28.000
|
$22.650
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$8.000
|
$21.200
|
$2.200
|
$22.250
|
$9.880
|
$9.550
|
$10.000
|
$15.000
|
$9.500
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
25,747.000
|
$5.000
|
$4.500
|
$4.400
|
$4.750
|
$3.380
|
$3.250
|
$4.000
|
$4.000
|
$3.250
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
25,747.000
|
$1.180
|
$0.900
|
$0.550
|
$1.000
|
$0.520
|
$0.500
|
$1.000
|
$1.500
|
$0.500
|
|
|
CONSTRUCTING DETOURS
|
SY
|
641.000
|
$126.430
|
$94.600
|
$241.190
|
$92.000
|
$84.851
|
$123.000
|
$150.000
|
$175.000
|
$101.200
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
260.000
|
$111.000
|
$179.000
|
$51.150
|
$120.000
|
$87.740
|
$291.500
|
$150.000
|
$75.000
|
$84.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
40.000
|
$54.530
|
$56.300
|
$168.040
|
$91.500
|
$30.763
|
$262.000
|
$250.000
|
$100.000
|
$117.050
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$56.120
|
$40.800
|
$168.040
|
$90.500
|
$30.495
|
$242.250
|
$150.000
|
$100.000
|
$110.010
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
60.000
|
$17.560
|
$76.700
|
$152.400
|
$12.500
|
$20.651
|
$201.250
|
$125.000
|
$50.000
|
$160.140
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
120.000
|
$28.650
|
$55.300
|
$50.200
|
$15.500
|
$20.651
|
$149.500
|
$75.000
|
$50.000
|
$85.610
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
40.000
|
$20.920
|
$49.300
|
$75.300
|
$24.000
|
$24.343
|
$273.500
|
$100.000
|
$75.000
|
$105.680
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$26.490
|
$49.300
|
$75.300
|
$18.000
|
$24.075
|
$112.000
|
$100.000
|
$75.000
|
$72.320
|
|
|
DRIVEWAYS (CONC)
|
SY
|
472.000
|
$91.890
|
$155.000
|
$178.840
|
$116.000
|
$261.947
|
$191.250
|
$150.000
|
$130.000
|
$141.520
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
3,329.000
|
$41.890
|
$57.000
|
$71.500
|
$44.000
|
$37.536
|
$85.600
|
$50.000
|
$60.000
|
$56.500
|
|
|
TURNOUTS (CONC)
|
SY
|
26.000
|
$208.500
|
$154.000
|
$220.000
|
$125.000
|
$320.797
|
$244.000
|
$400.000
|
$150.000
|
$130.200
|
|
|
TURNOUTS (SURF TREAT)
|
SY
|
457.000
|
$85.270
|
$56.600
|
$13.200
|
$50.250
|
$48.792
|
$95.500
|
$50.000
|
$60.000
|
$56.500
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,200.000
|
$35.830
|
$23.900
|
$27.500
|
$25.000
|
$25.740
|
$25.400
|
$30.000
|
$30.000
|
$23.720
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
EA
|
4.000
|
$1,167.330
|
$1,270.000
|
$1,485.000
|
$1,350.000
|
$1,404.000
|
$1,410.000
|
$1,500.000
|
$1,500.000
|
$1,264.980
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$3,783.330
|
$3,130.000
|
$3,850.000
|
$3,275.000
|
$3,551.600
|
$3,800.000
|
$3,500.000
|
$3,250.000
|
$3,109.750
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
27.000
|
$338.080
|
$382.000
|
$335.500
|
$340.000
|
$374.400
|
$306.500
|
$400.000
|
$400.000
|
$360.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
5.000
|
$741.900
|
$690.000
|
$665.500
|
$675.000
|
$676.000
|
$608.000
|
$750.000
|
$700.000
|
$650.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
12.000
|
$52.740
|
$37.100
|
$26.400
|
$28.500
|
$36.400
|
$25.650
|
$40.000
|
$30.000
|
$35.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
40.000
|
$853.330
|
$743.000
|
$770.000
|
$750.000
|
$728.000
|
$678.000
|
$800.000
|
$675.000
|
$700.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
9.000
|
$1,515.430
|
$796.000
|
$913.000
|
$925.000
|
$780.000
|
$834.000
|
$850.000
|
$830.000
|
$750.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
42.000
|
$897.500
|
$849.000
|
$880.000
|
$875.000
|
$832.000
|
$789.000
|
$900.000
|
$785.000
|
$800.000
|
|
|
IN SM RD SN SUP&AM TYFRP(1)UA(P)
|
EA
|
2.000
|
$450.000
|
$743.000
|
$1,144.000
|
$1,160.000
|
$728.000
|
$1,050.000
|
$800.000
|
$1,040.000
|
$700.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
8.000
|
$1,075.830
|
$1,030.000
|
$990.000
|
$960.000
|
$1,014.000
|
$864.000
|
$1,200.000
|
$860.000
|
$975.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
|
EA
|
3.000
|
$980.550
|
$1,460.000
|
$1,149.500
|
$1,160.000
|
$1,430.000
|
$1,050.000
|
$1,600.000
|
$1,045.000
|
$1,375.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
104.000
|
$167.600
|
$106.000
|
$115.500
|
$120.000
|
$104.000
|
$105.500
|
$125.000
|
$125.000
|
$100.000
|
|
|
REMOVE SM RD SN SUP&AM (SIGN ONLY)
|
EA
|
1.000
|
$124.710
|
$79.600
|
$93.500
|
$95.000
|
$78.000
|
$85.400
|
$100.000
|
$100.000
|
$75.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
20.000
|
$39.250
|
$34.000
|
$22.000
|
$27.000
|
$33.280
|
$19.600
|
$30.000
|
$25.000
|
$32.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
21.000
|
$101.390
|
$79.600
|
$80.300
|
$81.000
|
$78.000
|
$72.900
|
$85.000
|
$80.000
|
$75.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
75,852.000
|
$1.260
|
$0.400
|
$0.390
|
$0.400
|
$0.478
|
$1.050
|
$0.500
|
$0.500
|
$1.050
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
1,435.000
|
$13.330
|
$1.100
|
$1.050
|
$1.100
|
$0.499
|
$20.100
|
$0.550
|
$1.250
|
$20.000
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
572.000
|
$13.330
|
$9.700
|
$9.900
|
$9.500
|
$4.992
|
$38.200
|
$5.500
|
$10.000
|
$38.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
3,742.000
|
$1.250
|
$1.500
|
$1.100
|
$2.500
|
$1.605
|
$2.250
|
$1.250
|
$4.000
|
$1.630
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
4,014.000
|
$7.830
|
$1.500
|
$1.100
|
$2.500
|
$1.605
|
$2.250
|
$1.250
|
$4.000
|
$1.630
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
228.000
|
$1.970
|
$1.100
|
$1.050
|
$1.100
|
$2.382
|
$3.950
|
$3.000
|
$1.250
|
$3.950
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
1.000
|
$249.780
|
$227.000
|
$220.000
|
$225.000
|
$182.000
|
$452.000
|
$200.000
|
$300.000
|
$450.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
1.000
|
$266.270
|
$256.000
|
$247.500
|
$250.000
|
$192.400
|
$502.000
|
$225.000
|
$300.000
|
$500.000
|
|
|
PAVEMENT SEALER 6"
|
LF
|
140,206.000
|
$0.570
|
$0.280
|
$0.280
|
$0.300
|
$0.468
|
$0.350
|
$0.500
|
$0.350
|
$0.360
|
|
|
PAVEMENT SEALER 8"
|
LF
|
228.000
|
$0.870
|
$0.570
|
$0.550
|
$0.600
|
$0.614
|
$1.050
|
$0.750
|
$0.750
|
$1.050
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
1.000
|
$120.170
|
$28.400
|
$27.500
|
$28.000
|
$104.000
|
$125.500
|
$125.000
|
$50.000
|
$125.000
|
|
|
PAVEMENT SEALER (WORD)
|
EA
|
1.000
|
$125.690
|
$34.100
|
$33.000
|
$33.500
|
$109.200
|
$150.750
|
$125.000
|
$50.000
|
$150.000
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(090MIL)
|
LF
|
74,574.000
|
$2.020
|
$0.910
|
$0.880
|
$0.900
|
$1.768
|
$1.250
|
$2.000
|
$1.000
|
$1.250
|
|
|
REF PROF PAV MRK TY I(Y)6"(SLD)(090MIL)
|
LF
|
62,682.000
|
$2.380
|
$0.910
|
$0.880
|
$0.900
|
$1.768
|
$1.250
|
$2.000
|
$1.000
|
$1.250
|
|
|
REF PROF PAV MRK TY I(Y)6"(BRK)(090MIL)
|
LF
|
2,950.000
|
$1.570
|
$0.970
|
$0.940
|
$0.950
|
$1.820
|
$1.300
|
$2.000
|
$1.100
|
$1.280
|
|
REFL PAV MRKR TY I-C
|
EA
|
12.000
|
$6.580
|
$6.800
|
$6.600
|
$6.700
|
$4.420
|
$20.100
|
$5.000
|
$8.000
|
$20.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
944.000
|
$7.570
|
$6.800
|
$6.600
|
$6.700
|
$4.160
|
$8.400
|
$5.500
|
$8.000
|
$8.350
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
65,327.000
|
$0.880
|
$0.400
|
$0.830
|
$0.400
|
$0.364
|
$0.500
|
$0.500
|
$0.500
|
$0.500
|
|
|
DITCH CLEANING AND RESHAPING (FOOT)
|
LF
|
36,896.000
|
$37.500
|
$1.750
|
$3.180
|
$21.350
|
$4.794
|
$5.650
|
$3.000
|
$3.000
|
$10.500
|
|
|
PREFORMED CENTERLINE RUMBLE STRIP
|
LF
|
72.000
|
$8.740
|
$22.700
|
$22.000
|
$22.250
|
$104.000
|
$42.200
|
$50.000
|
$25.000
|
$208.670
|
|
|
TMA (STATIONARY)
|
DAY
|
13.000
|
$232.680
|
$248.000
|
$550.000
|
$250.000
|
$321.000
|
$1,010.000
|
$500.000
|
$1,000.000
|
$269.860
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
43.000
|
$401.830
|
$493.000
|
$110.000
|
$450.000
|
$592.780
|
$1,040.000
|
$500.000
|
$1,250.000
|
$347.120
|
|
|
DRIVEWAY ASSISTANCE DEVICE(DAD) SYSTEM
|
MO
|
14.500
|
$10,619.510
|
$10,400.000
|
$13,750.000
|
$8,815.000
|
$14,525.423
|
$16,530.000
|
$25,000.000
|
$20,000.000
|
$12,081.590
|
|
Totals: |
$7,160,914.835
|
$4,477,118.860
|
$4,607,328.680
|
$5,399,445.000
|
$5,831,190.248
|
$5,928,107.450
|
$6,427,861.450
|
$6,634,821.250
|
$7,162,487.355
|