KING US 82 (0132-03-036)

Items: 56

County: KING
Length: 0.0000 MILES (16.2225 MILES)
Highway: US 82
District: CHILDRESS
Control Number: 0132-03-036
DBE Goal: 0.0%
Project: F 2026(839)
Guaranty: $100,000.00
Time: 374 WORKING DAYS
Engineer's Estimate: $27,289,982.30
Date: 08/05/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263006
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00194650
Contract Type: FEDERAL
Project Description: REHABILITATION OF EXISTING ROADWAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$27,289,982.30
$28,760,605.30
Over/Under Est: 5.39% $1,470,623.00
$29,743,289.92
Over/Under Est: 8.99% $2,453,307.62
Amt Left: 3.42% $982,684.62
$29,815,595.55
Over/Under Est: 9.25% $2,525,613.25
Amt Left: 3.67% $1,054,990.25
Delta: -0.24% -$72,305.63
$30,406,275.05
Over/Under Est: 11.42% $3,116,292.75
Amt Left: 5.72% $1,645,669.75
Delta: -1.98% -$590,679.50
$31,812,630.06
Over/Under Est: 16.57% $4,522,647.76
Amt Left: 10.61% $3,052,024.76
Delta: -4.63% -$1,406,355.01

Bid Items & Bid Tabulations

56 Total 0 of 56
KING  |  US 82  |  CHILDRESS  |  0132-03-036  |  08/05/2026 1:00 PM CDT  |  $27,289,982.30  |  F 2026(839)  |  REHAB EXIST ROADWAY  |  374 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ZACK BURKETT CO.
OVERLAND CORPORATION
CK NEWBERRY, LLC
RK HALL, LLC
A. L. HELMCAMP, INC.
RMV (3") TRT/UNTRT BASE & ASPH PAV
SY 181,673.000 $6.120 $3.100 $1.050 $2.000 $3.300 $3.000
RMV (17") TRT/UNTRT BASE & ASPH PAV
SY 112,773.000 $12.500 $10.500 $5.750 $10.000 $12.130 $13.000
EXCAV (ROADWAY)
CY 21,934.000 $12.360 $10.800 $11.000 $15.000 $15.420 $23.000
EMBANK (FNL)(DC)(TY A)
CY 25,696.000 $26.390 $32.150 $24.000 $23.000 $12.370 $22.000
BACKFILL (TY A OR B)
STA 874.000 $202.130 $138.850 $271.730 $375.000 $219.440 $340.000
DRILL SEED (PERM_RURAL_SAND)
AC 47.000 $642.980 $677.350 $2,999.020 $600.000 $624.340 $620.000
VEGETATIVE WATERING
TGL 176.000 $26.920 $62.500 $1.000 $60.000 $70.060 $50.000
PROOF ROLLING
HR 31.000 $160.180 $0.010 $183.900 $75.000 $172.040 $210.000
FL BS (CMP IN PLC)(TY A GR 1-2) (8")
SY 127,119.000 $21.180 $24.650 $15.000 $17.250 $12.240 $17.500
CEMENT
TON 2,897.000 $231.620 $299.000 $250.000 $275.000 $296.420 $270.000
CEMENT TRT (EXIST MATL)(10")
SY 183,504.000 $4.320 $5.000 $1.500 $2.500 $3.960 $2.700
CEMENT TRT (SUBGRADE) (8")
SY 113,994.000 $4.100 $4.600 $1.000 $1.100 $3.630 $2.100
PRIME COAT (MC-30)
GAL 57,076.000 $5.820 $4.800 $5.370 $5.500 $6.300 $6.500
D-GR HMA TY-B PG70-28
TON 58,802.000 $96.000 $126.250 $153.000 $145.000 $145.360 $151.000
D-GR HMA TY-D SAC-A PG70-28
TON 65,824.000 $126.000 $137.250 $157.000 $150.000 $152.120 $161.000
TACK COAT
GAL 72,316.000 $4.500 $4.300 $5.000 $3.250 $5.380 $4.000
PLANE & TEXT ASPH CONC PAV(0" TO 2")
SY 57,233.000 $5.000 $2.400 $2.250 $1.000 $2.540 $3.600
RIPRAP (MOW STRIP)(4 IN)
CY 220.000 $773.730 $931.500 $670.330 $850.000 $848.000 $850.000
MOBILIZATION
LS 1.000 $2,471,357.270 $1,560,000.000 $2,906,400.000 $2,750,000.000 $2,432,502.000 $2,600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $5,000.000 $13,890.000 $11,500.000 $15,000.000 $20,611.760 $11,800.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $900.000 $0.010 $14,000.000 $15,000.000 $16,012.800 $18,000.000
TMA (STATIONARY)
DAY 752.000 $230.880 $200.000 $351.750 $275.000 $533.890 $200.000
TMA (MOBILE OPERATION)
HR 600.000 $51.340 $0.010 $0.010 $25.000 $101.350 $60.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 2,606.000 $7.500 $5.000 $10.300 $8.000 $5.140 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,606.000 $1.130 $1.000 $1.070 $1.000 $1.060 $1.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 12.000 $4,860.000 $2,000.000 $12,401.310 $6,500.000 $4,600.400 $8,000.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 1,620.000 $18.090 $26.450 $10.010 $25.000 $26.850 $30.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 1,620.000 $14.490 $17.250 $4.770 $15.000 $13.220 $23.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,620.000 $19.530 $17.250 $10.010 $15.000 $26.850 $23.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 176,306.000 $0.250 $0.230 $0.070 $0.150 $0.150 $0.210
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 142,710.000 $0.260 $0.260 $0.090 $0.150 $0.150 $0.240
MTL W-BEAM GD FEN (STEEL POST)
LF 4,125.000 $36.220 $39.100 $32.000 $35.000 $33.920 $34.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 16.000 $2,942.520 $3,220.000 $2,300.000 $2,800.000 $3,022.040 $2,400.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,706.300 $1,955.000 $1,450.000 $1,700.000 $1,537.000 $1,500.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 16.000 $1,086.250 $920.000 $850.000 $800.000 $901.000 $900.000
REMOVE METAL BEAM GUARD FENCE
LF 4,125.000 $1.410 $1.150 $3.000 $1.000 $3.180 $3.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 4.000 $275.000 $230.000 $330.000 $200.000 $349.800 $350.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 12.000 $272.460 $230.000 $300.000 $200.000 $318.000 $320.000
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $3,780.250 $3,680.000 $3,150.000 $3,200.000 $3,339.000 $3,300.000
GUARDRAIL END TREATMENT (REMOVE)
EA 12.000 $245.570 $230.000 $300.000 $200.000 $318.000 $320.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $1,372.820 $1,725.000 $2,750.000 $1,500.000 $2,915.000 $1,800.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $753.470 $1,150.000 $1,500.000 $1,000.000 $1,590.000 $1,200.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $8,667.080 $11,500.000 $10,500.000 $10,000.000 $11,130.000 $10,500.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 130,765.000 $0.410 $0.210 $0.250 $0.200 $0.190 $0.190
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 384.000 $3.160 $14.380 $3.000 $12.500 $13.250 $13.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 172,400.000 $0.410 $0.210 $0.250 $0.200 $0.190 $0.190
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 8,959.000 $0.820 $0.860 $0.800 $0.750 $0.800 $0.800
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 8.000 $378.840 $460.000 $375.000 $400.000 $424.000 $430.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 32,585.000 $0.820 $0.750 $0.550 $0.650 $0.690 $0.700
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 154,350.000 $0.780 $0.690 $0.520 $0.600 $0.640 $0.630
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 1,013.000 $1.620 $0.810 $0.550 $0.700 $0.740 $0.750
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 150,290.000 $1.160 $0.690 $0.520 $0.600 $0.640 $0.630
REFL PAV MRKR TY II-A-A
EA 180.000 $4.820 $11.500 $3.900 $10.000 $10.600 $11.000
REFL PAV MRKR TY II-C-R
EA 1,051.000 $4.150 $5.750 $3.800 $5.000 $5.300 $5.300
ELIM EXT PM & MRKS (6")
LF 96,434.000 $1.100 $0.690 $0.520 $0.600 $0.640 $0.600
ELIM EXT PM & MRKS (24")
LF 384.000 $2.950 $5.750 $3.000 $5.000 $5.300 $5.300
Totals: $27,289,982.300 $28,760,605.300 $29,743,289.920 $29,815,595.550 $30,406,275.050 $31,812,630.060
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,148.96
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $540,017.21
Total: $541,166.17