PREPARING ROW
|
STA
|
325.000
|
$600.000
|
$133.200
|
$400.000
|
$661.400
|
$300.000
|
$500.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
86.000
|
$45.000
|
$29.520
|
$30.000
|
$29.300
|
$25.000
|
$50.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
34,649.000
|
$15.000
|
$13.170
|
$3.500
|
$10.500
|
$27.000
|
$10.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
325.000
|
$600.000
|
$265.280
|
$1,000.000
|
$388.500
|
$960.000
|
$225.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY A)
|
CY
|
10,939.000
|
$35.000
|
$5.410
|
$22.000
|
$10.600
|
$28.000
|
$11.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
AC
|
22.400
|
$700.000
|
$888.000
|
$1,351.540
|
$1,315.320
|
$1,202.000
|
$1,200.000
|
|
|
CEMENT
|
TON
|
2,196.000
|
$262.000
|
$215.180
|
$200.000
|
$209.000
|
$209.000
|
$200.000
|
|
|
CEMENT TREAT (EXIST MATL) (10")
|
SY
|
133,025.000
|
$4.000
|
$1.750
|
$2.760
|
$2.600
|
$2.700
|
$2.250
|
|
|
ASPHALT STAB BASE (GR 1)(PG 64)
|
TON
|
44,674.000
|
$115.000
|
$119.870
|
$108.000
|
$96.400
|
$97.400
|
$95.000
|
|
|
PRIME COAT (RC-250)
|
GAL
|
24,120.000
|
$5.000
|
$4.890
|
$5.200
|
$5.240
|
$4.570
|
$5.000
|
|
|
AGGR(TY-PB GR-5 SAC-A)
|
CY
|
862.000
|
$145.000
|
$208.590
|
$220.000
|
$160.020
|
$240.000
|
$200.000
|
|
|
CEM STABIL BKFL
|
CY
|
315.000
|
$190.000
|
$126.530
|
$150.000
|
$470.170
|
$197.000
|
$200.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
665.000
|
$27.500
|
$13.320
|
$20.000
|
$4.680
|
$58.000
|
$25.000
|
|
|
RIPRAP (CONC) (CL B) (4")
|
CY
|
26.000
|
$300.000
|
$1,332.000
|
$525.000
|
$850.000
|
$985.000
|
$800.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
28.000
|
$240.000
|
$333.000
|
$200.000
|
$215.000
|
$275.000
|
$300.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
42.000
|
$770.000
|
$777.000
|
$525.000
|
$825.000
|
$840.000
|
$800.000
|
|
|
RAIL (TY T631)
|
LF
|
80.000
|
$112.000
|
$94.350
|
$120.000
|
$112.500
|
$105.000
|
$125.000
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
666.000
|
$653.000
|
$488.520
|
$500.000
|
$600.000
|
$565.000
|
$725.000
|
|
|
CONC BOX CULV (8 FT X 3 FT)
|
LF
|
68.000
|
$755.000
|
$1,173.750
|
$1,000.000
|
$1,100.000
|
$913.000
|
$1,325.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
30.000
|
$250.000
|
$88.520
|
$94.000
|
$160.000
|
$141.000
|
$225.000
|
|
|
RC PIPE (ARCH)(CL IV)(DES 3)
|
LF
|
233.000
|
$430.000
|
$225.250
|
$274.000
|
$350.000
|
$302.000
|
$325.000
|
|
|
RC PIPE (ARCH)(CL IV)(DES 1)
|
LF
|
182.000
|
$296.000
|
$200.600
|
$234.000
|
$250.000
|
$222.000
|
$350.000
|
|
|
WINGWALL (PW - 1) (HW=4 FT)
|
EA
|
2.000
|
$15,000.000
|
$15,540.000
|
$16,000.000
|
$18,000.000
|
$23,800.000
|
$25,000.000
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
28.000
|
$5,500.000
|
$11,655.000
|
$5,500.000
|
$5,800.000
|
$8,900.000
|
$12,500.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,690.000
|
$3,885.000
|
$2,000.000
|
$4,800.000
|
$2,950.000
|
$4,000.000
|
|
|
SET (TY II) (DES 1) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$2,300.000
|
$2,775.000
|
$2,000.000
|
$3,800.000
|
$3,450.000
|
$4,500.000
|
|
|
SET (TY II) (DES 3) (RCP) (4: 1) (C)
|
EA
|
10.000
|
$2,600.000
|
$3,330.000
|
$2,800.000
|
$4,600.000
|
$4,850.000
|
$5,000.000
|
|
|
REMOV STR (SET)
|
EA
|
38.000
|
$590.000
|
$423.080
|
$150.000
|
$750.000
|
$640.000
|
$1,500.000
|
|
|
REMOV STR (PIPE)
|
EA
|
22.000
|
$280.000
|
$461.540
|
$300.000
|
$1,250.000
|
$1,200.000
|
$1,500.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,341,326.890
|
$566,000.000
|
$750,000.000
|
$1,144,404.550
|
$1,375,000.000
|
$1,300,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
29.000
|
$4,500.000
|
$1,665.000
|
$1,500.000
|
$4,802.840
|
$9,700.000
|
$19,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
265.000
|
$71.000
|
$72.150
|
$74.000
|
$100.870
|
$93.000
|
$95.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
265.000
|
$30.000
|
$27.750
|
$38.000
|
$12.720
|
$15.000
|
$12.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,210.000
|
$5.200
|
$4.440
|
$3.500
|
$4.890
|
$4.500
|
$4.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,210.000
|
$2.730
|
$0.560
|
$2.000
|
$1.050
|
$2.000
|
$1.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
16,247.000
|
$90.000
|
$33.910
|
$41.000
|
$41.400
|
$42.000
|
$65.000
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
960.000
|
$89.000
|
$85.770
|
$78.000
|
$96.000
|
$70.000
|
$150.000
|
|
|
ONE-WAY TRAFFIC CONTROL (PORT TRAF SIG)
|
DAY
|
600.000
|
$185.000
|
$149.850
|
$200.000
|
$492.130
|
$25.000
|
$250.000
|
|
|
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
|
LF
|
450.000
|
$73.000
|
$36.450
|
$23.000
|
$85.000
|
$38.000
|
$100.000
|
|
|
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
|
LF
|
8,550.000
|
$6.500
|
$13.710
|
$13.000
|
$52.000
|
$22.000
|
$30.000
|
|
|
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
|
LF
|
450.000
|
$14.000
|
$36.450
|
$11.000
|
$50.000
|
$33.000
|
$50.000
|
|
|
INTERSECTIONS (SURF TREAT)
|
SY
|
1,048.000
|
$50.000
|
$9.660
|
$100.000
|
$48.300
|
$63.000
|
$85.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
135.000
|
$120.000
|
$138.750
|
$140.000
|
$120.000
|
$175.000
|
$125.000
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
2,200.000
|
$45.000
|
$9.650
|
$100.000
|
$48.300
|
$61.000
|
$95.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
64,970.000
|
$0.130
|
$0.220
|
$0.150
|
$0.150
|
$0.110
|
$0.150
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
32,485.000
|
$0.130
|
$0.220
|
$0.150
|
$0.160
|
$0.110
|
$0.150
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
625.000
|
$28.000
|
$27.750
|
$25.000
|
$23.300
|
$28.250
|
$30.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$4,150.000
|
$3,219.000
|
$3,600.000
|
$3,400.000
|
$3,100.000
|
$3,100.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
30.000
|
$1,370.000
|
$1,665.000
|
$800.000
|
$900.000
|
$1,100.000
|
$600.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$911.000
|
$555.000
|
$900.000
|
$875.000
|
$725.000
|
$700.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$9,000.000
|
$8,325.000
|
$7,400.000
|
$8,125.000
|
$8,000.000
|
$9,500.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
4.000
|
$375.000
|
$199.800
|
$370.000
|
$180.000
|
$350.000
|
$200.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
4.000
|
$650.000
|
$666.000
|
$630.000
|
$600.000
|
$590.000
|
$600.000
|
|
|
TEMP RD IL (RD IL ASM)
|
MO
|
29.000
|
$3,360.000
|
$3,330.000
|
$1,100.000
|
$762.840
|
$1,800.000
|
$3,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
76.000
|
$695.000
|
$638.250
|
$650.000
|
$575.000
|
$615.000
|
$575.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
1.000
|
$1,100.000
|
$1,054.500
|
$910.000
|
$800.000
|
$855.000
|
$800.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
1.000
|
$1,200.000
|
$1,054.500
|
$950.000
|
$950.000
|
$895.000
|
$950.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
80.000
|
$81.000
|
$88.800
|
$75.000
|
$100.000
|
$70.000
|
$100.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
10.000
|
$47.300
|
$49.950
|
$38.000
|
$45.000
|
$35.000
|
$40.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
20.000
|
$75.000
|
$88.800
|
$155.000
|
$80.000
|
$145.000
|
$80.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
3,243.000
|
$1.700
|
$1.110
|
$2.000
|
$1.690
|
$1.750
|
$1.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
24.000
|
$8.120
|
$55.500
|
$53.000
|
$50.000
|
$50.000
|
$17.000
|
|
|
PAVEMENT SEALER 6"
|
LF
|
217,908.000
|
$0.340
|
$0.240
|
$0.250
|
$0.220
|
$0.220
|
$0.250
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
64,987.000
|
$0.680
|
$0.730
|
$0.700
|
$0.660
|
$0.660
|
$0.700
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
4,174.000
|
$0.850
|
$0.980
|
$1.000
|
$0.880
|
$0.880
|
$0.700
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
39,793.000
|
$0.680
|
$0.730
|
$0.700
|
$0.660
|
$0.660
|
$0.700
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
707.000
|
$2.850
|
$5.550
|
$6.000
|
$5.000
|
$5.000
|
$5.000
|
|
|
STRIP MOWING
|
CYC
|
3.000
|
$3,100.000
|
$5,550.000
|
$2,300.000
|
$4,880.000
|
$2,500.000
|
$5,000.000
|
|
|
FULL - WIDTH MOWING
|
CYC
|
3.000
|
$3,500.000
|
$7,770.000
|
$2,500.000
|
$6,710.000
|
$3,800.000
|
$6,500.000
|
|
|
D-GR HMA TY-C SAC-A PG76-22
|
TON
|
13,508.000
|
$130.000
|
$156.910
|
$140.000
|
$127.300
|
$145.000
|
$145.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$12,175.000
|
$6,105.000
|
$30,000.000
|
$10,000.000
|
$18,000.000
|
$25,000.000
|
|
|
TMSP RADAR SPEED CONTROL MONITOR
|
EA
|
2.000
|
$11,000.000
|
$12,210.000
|
$11,000.000
|
$12,000.000
|
$10,875.000
|
$15,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
510.000
|
$276.000
|
$72.150
|
$188.000
|
$350.000
|
$200.000
|
$300.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
920.000
|
$80.000
|
$16.650
|
$66.000
|
$95.000
|
$80.000
|
$25.000
|
|
Totals: |
$14,758,445.790
|
$12,342,227.720
|
$12,348,481.246
|
$12,825,010.328
|
$13,797,058.530
|
$13,999,639.300
|