PREPARING ROW
|
STA
|
239.000
|
$950.000
|
$360.000
|
$700.000
|
$385.000
|
$302.500
|
$269.000
|
|
|
REMOV CONC (DRIVEWAYS)
|
SY
|
87.000
|
$15.000
|
$16.500
|
$18.000
|
$12.000
|
$20.000
|
$15.000
|
|
|
EXCAV (CHANNEL)
|
CY
|
18.000
|
$25.000
|
$44.000
|
$60.000
|
$100.000
|
$15.000
|
$80.000
|
|
|
SUBGR WIDEN (OC)
|
STA
|
228.000
|
$225.000
|
$225.000
|
$1,015.000
|
$500.000
|
$2.000
|
$350.000
|
|
|
EMBANK (VEH)(OC)(TY B)
|
CY
|
177.000
|
$30.000
|
$44.000
|
$38.000
|
$100.000
|
$15.000
|
$35.000
|
|
|
BACKFILL (TY A)
|
STA
|
239.000
|
$205.000
|
$225.000
|
$215.000
|
$526.050
|
$250.000
|
$370.000
|
|
|
ROAD GRADER WORK (ORD COMP)
|
STA
|
239.000
|
$200.000
|
$225.000
|
$190.000
|
$325.000
|
$157.000
|
$380.000
|
|
|
BROADCAST SEED (TEMP_WARM)
|
SY
|
39,779.000
|
$0.160
|
$0.176
|
$0.180
|
$0.170
|
$0.170
|
$0.160
|
|
|
BROADCAST SEED (TEMP_COOL)
|
SY
|
39,779.000
|
$0.160
|
$0.176
|
$0.180
|
$0.170
|
$0.170
|
$0.160
|
|
|
STRAW/HAY MLCH SEED(PERM_RURAL_CLAY)
|
SY
|
79,558.000
|
$0.280
|
$0.462
|
$0.470
|
$0.450
|
$0.440
|
$0.420
|
|
|
VEGETATIVE WATERING
|
TGL
|
478.000
|
$24.000
|
$0.001
|
$12.000
|
$10.000
|
$1.000
|
$25.000
|
|
|
PROOF ROLLING
|
HR
|
9.000
|
$85.000
|
$100.000
|
$150.000
|
$100.000
|
$100.000
|
$60.000
|
|
|
CEM TRT(PLNT MX)(CL N)(TY A)(GR 4)(12")
|
SY
|
15,198.000
|
$22.000
|
$45.000
|
$46.500
|
$68.610
|
$100.000
|
$94.400
|
|
|
ASPH (RC-250)
|
GAL
|
5,320.000
|
$5.500
|
$11.000
|
$6.250
|
$6.480
|
$4.380
|
$8.000
|
|
|
AGGR (TY-B, GR-4)(SAC-A)
|
CY
|
127.000
|
$95.000
|
$318.000
|
$230.000
|
$146.235
|
$236.900
|
$180.000
|
|
|
SP MIXES SP-C SAC-A PG64-22
|
TON
|
13,247.000
|
$150.000
|
$124.300
|
$118.000
|
$113.000
|
$132.920
|
$113.000
|
|
|
TACK COAT
|
GAL
|
7,583.000
|
$4.500
|
$4.895
|
$4.500
|
$4.450
|
$5.150
|
$4.450
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
|
SY
|
500.000
|
$75.000
|
$65.000
|
$85.000
|
$53.990
|
$87.550
|
$218.000
|
|
|
CUT & RESTORE CONC PAVING
|
SY
|
36.000
|
$160.000
|
$385.000
|
$230.000
|
$125.000
|
$200.000
|
$350.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
19.000
|
$100.000
|
$330.000
|
$225.000
|
$100.000
|
$200.000
|
$300.000
|
|
|
CUT AND RESTORE PAV (FLEX BASE)
|
SY
|
133.000
|
$85.000
|
$88.000
|
$85.000
|
$25.000
|
$50.000
|
$80.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
18.000
|
$10.000
|
$110.000
|
$50.000
|
$15.000
|
$10.000
|
$100.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,933.000
|
$20.000
|
$19.800
|
$50.000
|
$15.000
|
$30.000
|
$18.000
|
|
|
CONC STR REPAIR (STANDARD)
|
SF
|
200.000
|
$150.000
|
$93.500
|
$110.000
|
$75.000
|
$150.000
|
$85.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
27.000
|
$225.000
|
$143.000
|
$235.000
|
$303.200
|
$160.000
|
$130.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
288.000
|
$250.000
|
$247.500
|
$180.000
|
$303.200
|
$160.000
|
$225.000
|
|
|
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
|
LF
|
16.000
|
$1,000.000
|
$825.000
|
$1,025.000
|
$1,050.000
|
$700.000
|
$750.000
|
|
|
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
|
LF
|
20.000
|
$1,260.000
|
$962.500
|
$1,050.000
|
$1,200.000
|
$800.000
|
$875.000
|
|
|
CONC BOX CULV (8 FT X 4 FT)(EXTEND)
|
LF
|
18.000
|
$830.490
|
$990.000
|
$1,250.000
|
$1,350.000
|
$800.000
|
$900.000
|
|
|
CONC BOX CULV (10 FT X 8 FT)(EXTEND)
|
LF
|
10.000
|
$1,300.000
|
$1,045.000
|
$2,200.000
|
$1,500.000
|
$1,100.000
|
$950.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
794.000
|
$50.000
|
$55.000
|
$58.000
|
$52.000
|
$55.000
|
$50.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
450.000
|
$80.000
|
$82.500
|
$77.000
|
$80.000
|
$65.000
|
$75.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
170.000
|
$115.000
|
$121.000
|
$110.000
|
$115.000
|
$85.000
|
$110.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
176.000
|
$160.000
|
$165.000
|
$140.000
|
$170.000
|
$105.000
|
$150.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
1.000
|
$6,000.000
|
$7,150.000
|
$9,000.000
|
$6,000.000
|
$5,000.000
|
$6,500.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 24 IN)
|
EA
|
7.000
|
$5,500.000
|
$7,700.000
|
$9,000.000
|
$6,500.000
|
$5,000.000
|
$7,000.000
|
|
|
WINGWALL (FW - S) (HW=5 FT)
|
EA
|
2.000
|
$14,800.000
|
$24,200.000
|
$16,500.000
|
$10,000.000
|
$10,000.000
|
$22,000.000
|
|
|
WINGWALL (FW - S) (HW=6 FT)
|
EA
|
2.000
|
$16,575.000
|
$25,300.000
|
$18,000.000
|
$12,000.000
|
$12,000.000
|
$23,000.000
|
|
|
WINGWALL (FW - S) (HW=8 FT)
|
EA
|
2.000
|
$25,000.000
|
$27,500.000
|
$26,000.000
|
$20,000.000
|
$14,000.000
|
$25,000.000
|
|
|
WINGWALL (PW - 2) (HW=10 FT)
|
EA
|
1.000
|
$30,000.000
|
$30,800.000
|
$30,000.000
|
$50,000.000
|
$80,000.000
|
$28,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
110.000
|
$800.000
|
$825.000
|
$970.000
|
$750.000
|
$750.000
|
$750.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
8.000
|
$1,000.000
|
$1,100.000
|
$1,200.000
|
$1,200.000
|
$800.000
|
$1,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
46.000
|
$1,400.000
|
$1,375.000
|
$1,405.000
|
$1,300.000
|
$950.000
|
$1,250.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
16.000
|
$2,600.000
|
$2,750.000
|
$2,960.000
|
$2,800.000
|
$2,600.000
|
$2,500.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (P)
|
EA
|
12.000
|
$6,500.000
|
$6,050.000
|
$5,700.000
|
$6,400.000
|
$4,400.000
|
$5,500.000
|
|
|
REMOV & RE - LAY PIPE (24 IN)
|
LF
|
48.000
|
$65.000
|
$38.500
|
$40.000
|
$40.000
|
$20.000
|
$35.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
10.000
|
$550.000
|
$1,100.000
|
$1,500.000
|
$1,200.000
|
$500.000
|
$1,000.000
|
|
|
REMOV STR (SET)
|
EA
|
24.000
|
$100.000
|
$104.500
|
$315.000
|
$100.000
|
$100.000
|
$95.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
7.000
|
$1,000.000
|
$990.000
|
$1,500.000
|
$1,000.000
|
$1,000.000
|
$900.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,184.000
|
$8.000
|
$7.700
|
$17.000
|
$8.000
|
$5.000
|
$7.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
8.000
|
$83.380
|
$165.000
|
$195.000
|
$75.000
|
$150.000
|
$150.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$419,862.000
|
$300,000.000
|
$400,000.000
|
$454,965.321
|
$400,000.000
|
$293,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$3,000.000
|
$4,600.000
|
$4,000.000
|
$5,410.000
|
$1,575.790
|
$8,327.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$12,000.000
|
$15,000.000
|
$19,250.000
|
$19,500.000
|
$10,000.000
|
$18,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
160.000
|
$150.000
|
$150.000
|
$230.000
|
$150.000
|
$200.000
|
$185.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
80.000
|
$85.000
|
$40.000
|
$120.000
|
$150.000
|
$200.000
|
$150.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
720.000
|
$45.000
|
$58.300
|
$58.000
|
$65.000
|
$55.650
|
$53.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
720.000
|
$10.000
|
$11.000
|
$11.000
|
$10.000
|
$10.500
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,080.000
|
$4.500
|
$4.950
|
$5.000
|
$5.500
|
$4.730
|
$4.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,080.000
|
$1.000
|
$0.550
|
$1.000
|
$1.000
|
$0.530
|
$0.500
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
1.000
|
$5,000.000
|
$3,800.000
|
$5,500.000
|
$10,000.000
|
$5,000.000
|
$7,500.000
|
|
|
INTERSECTIONS (ACP)
|
SY
|
298.000
|
$120.000
|
$58.000
|
$45.000
|
$63.000
|
$46.350
|
$58.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
87.000
|
$100.000
|
$110.000
|
$135.000
|
$100.000
|
$100.000
|
$115.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
78.000
|
$55.000
|
$58.000
|
$60.000
|
$63.000
|
$44.000
|
$58.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
998.000
|
$25.000
|
$25.000
|
$45.000
|
$37.030
|
$40.000
|
$35.000
|
|
|
TURNOUTS (ACP)
|
SY
|
1,058.000
|
$80.000
|
$150.000
|
$57.000
|
$100.950
|
$58.710
|
$148.000
|
|
|
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
|
LF
|
47,734.000
|
$0.240
|
$0.310
|
$0.220
|
$0.083
|
$0.210
|
$1.200
|
|
|
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
|
LF
|
23,867.000
|
$0.220
|
$0.310
|
$0.220
|
$0.110
|
$0.210
|
$1.200
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
1.000
|
$400.000
|
$715.000
|
$785.000
|
$715.000
|
$736.450
|
$600.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
41.000
|
$295.000
|
$295.000
|
$325.000
|
$295.000
|
$303.850
|
$200.000
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
4.000
|
$350.000
|
$355.000
|
$390.000
|
$355.000
|
$365.650
|
$400.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
36.000
|
$600.000
|
$635.000
|
$700.000
|
$635.000
|
$654.050
|
$750.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
22.000
|
$850.000
|
$735.000
|
$815.000
|
$735.000
|
$757.050
|
$700.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
3.000
|
$1,069.000
|
$1,199.000
|
$1,320.000
|
$1,199.000
|
$1,234.970
|
$900.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
1.000
|
$685.000
|
$585.000
|
$650.000
|
$585.000
|
$602.550
|
$1,500.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
60.000
|
$80.000
|
$79.000
|
$90.000
|
$79.000
|
$81.370
|
$80.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
27.000
|
$60.000
|
$65.000
|
$72.000
|
$65.000
|
$66.950
|
$300.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
48,988.000
|
$0.250
|
$0.320
|
$0.310
|
$0.270
|
$0.290
|
$0.280
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
72.000
|
$3.150
|
$5.000
|
$5.500
|
$4.000
|
$5.150
|
$5.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
|
LF
|
2,550.000
|
$0.300
|
$0.320
|
$0.310
|
$0.300
|
$0.290
|
$0.280
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
51,252.000
|
$0.280
|
$0.320
|
$0.310
|
$0.270
|
$0.290
|
$0.280
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
2,267.000
|
$2.000
|
$1.000
|
$1.500
|
$2.450
|
$1.000
|
$1.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
370.000
|
$0.990
|
$2.200
|
$1.100
|
$1.000
|
$1.030
|
$1.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
|
LF
|
90.000
|
$10.000
|
$12.100
|
$7.200
|
$13.250
|
$6.700
|
$6.500
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(090MIL)
|
EA
|
4.000
|
$36.500
|
$82.500
|
$110.000
|
$95.000
|
$103.000
|
$100.000
|
|
TY I HIGH PERF PM (W)6"(SLD)(090MIL)
|
LF
|
47,738.000
|
$0.850
|
$0.605
|
$0.950
|
$0.750
|
$0.880
|
$0.850
|
|
TY I HIGH PERF PM (Y)6"(BRK)(090MIL)
|
LF
|
2,550.000
|
$0.850
|
$0.627
|
$1.100
|
$0.800
|
$1.030
|
$1.000
|
|
TY I HIGH PERF PM (Y)6"(SLD)(090MIL)
|
LF
|
29,652.000
|
$0.850
|
$0.605
|
$0.950
|
$0.750
|
$0.880
|
$0.850
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,038.000
|
$5.750
|
$4.389
|
$5.500
|
$4.500
|
$5.150
|
$5.000
|
|
|
ELIM EXT PM & MRKS (6")
|
LF
|
12,800.000
|
$0.150
|
$0.759
|
$0.350
|
$1.250
|
$0.310
|
$0.300
|
|
|
CNC CRACK REPAIR (DISCRETE)(INJECT)
|
LF
|
18.000
|
$150.000
|
$275.000
|
$200.000
|
$150.000
|
$20.000
|
$250.000
|
|
Totals: |
$4,618,483.940
|
$4,580,817.959
|
$4,883,905.320
|
$4,997,151.088
|
$5,259,588.790
|
$5,351,772.090
|