PREPARING ROW
|
STA
|
21.120
|
$4,500.000
|
$2,375.000
|
$1,950.000
|
$3,000.000
|
$2,689.920
|
|
|
REMOVING STAB BASE AND ASPH PAV (10")
|
SY
|
3,997.500
|
$12.000
|
$4.700
|
$12.000
|
$15.000
|
$9.600
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
1,380.000
|
$10.000
|
$9.750
|
$15.000
|
$15.000
|
$21.030
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
540.000
|
$13.000
|
$12.550
|
$15.000
|
$25.000
|
$40.950
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY A)
|
CY
|
2,776.000
|
$18.000
|
$46.700
|
$25.000
|
$35.000
|
$46.850
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
2,895.500
|
$0.500
|
$1.570
|
$3.500
|
$1.650
|
$1.980
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
SY
|
2,895.500
|
$0.350
|
$1.570
|
$3.500
|
$1.650
|
$1.980
|
|
|
PROOF ROLLING
|
HR
|
185.000
|
$100.000
|
$21.000
|
$100.000
|
$95.000
|
$82.710
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
1,736.000
|
$105.000
|
$110.400
|
$103.000
|
$137.200
|
$102.750
|
|
|
REWORK BS MTL (TY A) (8") (ORD COMP)
|
SY
|
5,310.000
|
$6.000
|
$2.600
|
$9.000
|
$6.000
|
$12.450
|
|
|
PRIME COAT (MC-30)
|
GAL
|
975.000
|
$7.500
|
$6.800
|
$9.000
|
$12.000
|
$10.870
|
|
|
CEM STABIL BKFL
|
CY
|
232.000
|
$150.000
|
$235.000
|
$150.000
|
$200.000
|
$100.540
|
|
|
TEMPORARY SPL SHORING
|
SF
|
720.300
|
$17.000
|
$11.700
|
$40.000
|
$35.000
|
$66.500
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
164.000
|
$175.000
|
$257.500
|
$300.000
|
$350.000
|
$230.290
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
510.000
|
$270.000
|
$392.000
|
$450.000
|
$450.000
|
$268.680
|
|
|
CL C CONC (ABUT)
|
CY
|
95.400
|
$1,100.000
|
$957.000
|
$1,400.000
|
$1,100.000
|
$1,210.480
|
|
|
REINF CONC SLAB
|
SF
|
6,300.000
|
$24.500
|
$26.950
|
$25.000
|
$28.000
|
$61.980
|
|
|
APPROACH SLAB
|
CY
|
91.000
|
$660.000
|
$768.000
|
$600.000
|
$1,015.000
|
$783.240
|
|
|
RETAINING WALL (MSE)
|
SF
|
1,524.000
|
$45.000
|
$83.400
|
$90.000
|
$110.000
|
$174.120
|
|
|
PRESTR CONC GIRDER (TX40)
|
LF
|
358.000
|
$135.000
|
$261.000
|
$210.000
|
$265.000
|
$324.750
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
478.000
|
$154.000
|
$256.000
|
$230.000
|
$265.000
|
$327.890
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
38.000
|
$500.000
|
$578.000
|
$600.000
|
$485.000
|
$723.810
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
433.000
|
$170.000
|
$126.300
|
$235.000
|
$175.000
|
$300.730
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
385.000
|
$225.000
|
$148.200
|
$225.000
|
$175.000
|
$300.410
|
|
|
RIPRAP (STONE PROTECTION)(15 IN)
|
CY
|
241.000
|
$250.000
|
$134.900
|
$225.000
|
$175.000
|
$248.440
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
100.900
|
$450.000
|
$695.000
|
$600.000
|
$495.000
|
$686.900
|
|
|
RAIL (TY T223)
|
LF
|
519.000
|
$150.000
|
$101.000
|
$150.000
|
$95.000
|
$185.930
|
|
|
RAIL (TY SSTR)
|
LF
|
240.000
|
$125.000
|
$88.000
|
$110.000
|
$95.000
|
$216.280
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
|
LF
|
118.000
|
$140.000
|
$115.000
|
$200.000
|
$130.000
|
$42.160
|
|
|
GABIONS (GALV)
|
CY
|
80.000
|
$220.000
|
$258.000
|
$600.000
|
$300.000
|
$371.030
|
|
|
CONC BOX CULV (12 FT X 6 FT)
|
LF
|
96.000
|
$950.000
|
$981.000
|
$1,955.000
|
$1,975.000
|
$2,768.390
|
|
|
CONC BOX CULV (8 FT X 3 FT)
|
LF
|
192.000
|
$950.000
|
$709.000
|
$975.000
|
$935.000
|
$1,520.550
|
|
|
CONC BOX CULV (12 FT X 5 FT)
|
LF
|
160.000
|
$900.000
|
$852.000
|
$1,875.000
|
$1,875.000
|
$2,472.360
|
|
|
WINGWALL (PW - 1) (HW=5 FT)
|
EA
|
2.000
|
$20,000.000
|
$14,420.000
|
$20,000.000
|
$24,780.000
|
$38,382.290
|
|
|
WINGWALL (PW - 1) (HW=8 FT)
|
EA
|
2.000
|
$29,000.000
|
$19,910.000
|
$23,500.000
|
$37,609.600
|
$44,779.340
|
|
|
WINGWALL (PW - 1) (HW=9 FT)
|
EA
|
2.000
|
$38,000.000
|
$17,470.000
|
$27,000.000
|
$37,766.400
|
$51,176.380
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
4.000
|
$40,000.000
|
$19,610.000
|
$27,500.000
|
$20,000.000
|
$34,001.870
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$50,000.000
|
$41,980.000
|
$85,000.000
|
$50,000.000
|
$58,754.780
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$328,009.630
|
$380,450.000
|
$360,000.000
|
$310,000.000
|
$189,546.750
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
21.000
|
$6,000.000
|
$2,475.000
|
$1,150.000
|
$7,000.000
|
$1,279.410
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,040.000
|
$35.000
|
$30.300
|
$45.000
|
$31.900
|
$38.380
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,040.000
|
$10.000
|
$12.550
|
$10.000
|
$13.200
|
$16.630
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
6,662.000
|
$3.000
|
$2.300
|
$4.000
|
$2.420
|
$2.880
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
6,662.000
|
$1.000
|
$1.050
|
$1.500
|
$1.100
|
$1.410
|
|
|
CONSTRUCTING DETOURS
|
SY
|
4,812.000
|
$55.000
|
$85.100
|
$117.500
|
$115.000
|
$110.220
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
520.000
|
$38.000
|
$22.800
|
$70.000
|
$25.000
|
$147.710
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$50.000
|
$25.400
|
$70.000
|
$25.000
|
$196.550
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
1,440.000
|
$10.000
|
$5.750
|
$17.500
|
$12.000
|
$19.670
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
240.000
|
$12.000
|
$10.650
|
$17.500
|
$12.000
|
$88.500
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 1)
|
LF
|
1,440.000
|
$8.000
|
$5.750
|
$17.500
|
$18.000
|
$22.180
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 2)
|
LF
|
240.000
|
$10.000
|
$10.400
|
$17.500
|
$18.000
|
$37.590
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
520.000
|
$8.000
|
$17.200
|
$17.500
|
$18.000
|
$17.510
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$10.000
|
$18.900
|
$17.500
|
$18.000
|
$47.070
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,475.000
|
$25.000
|
$25.500
|
$32.000
|
$26.840
|
$31.350
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$2,500.000
|
$2,217.000
|
$2,600.000
|
$2,333.880
|
$2,718.750
|
|
|
MTL W - BEAM GD FEN (LOW FILL CULVERT)
|
LF
|
350.000
|
$90.000
|
$98.600
|
$120.000
|
$103.730
|
$121.540
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
758.000
|
$4.000
|
$3.140
|
$5.000
|
$3.300
|
$3.970
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
20.000
|
$3,000.000
|
$3,455.000
|
$3,900.000
|
$3,635.500
|
$4,234.850
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$350.000
|
$392.000
|
$325.000
|
$412.500
|
$486.180
|
|
|
CHAIN LINK FENCE (REMOVE)
|
LF
|
4,275.500
|
$6.000
|
$2.850
|
$5.500
|
$6.600
|
$2.970
|
|
|
WIRE FENCE (TY C)
|
LF
|
4,275.500
|
$15.000
|
$11.450
|
$17.000
|
$22.000
|
$25.040
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
16.000
|
$650.000
|
$889.000
|
$725.000
|
$33.000
|
$1,092.690
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
12.000
|
$100.000
|
$155.000
|
$100.000
|
$55.000
|
$196.290
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
18.000
|
$25.000
|
$26.000
|
$35.000
|
$55.000
|
$39.660
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
71.000
|
$30.000
|
$31.000
|
$40.000
|
$55.000
|
$39.660
|
|
|
PAVEMENT SEALER 4"
|
LF
|
6,104.000
|
$0.500
|
$1.380
|
$3.000
|
$1.450
|
$1.730
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
102.000
|
$4.000
|
$33.450
|
$35.000
|
$35.200
|
$42.220
|
|
|
D-GR HMA TY-C SAC-A PG76-22
|
TON
|
534.000
|
$155.000
|
$418.000
|
$158.000
|
$265.000
|
$166.320
|
|
|
HPPM W/RET REQ TY I(W)4"(SLD)(100MIL)
|
LF
|
2,054.000
|
$0.500
|
$2.350
|
$3.000
|
$2.470
|
$2.940
|
|
|
HPPM W/RET REQ TY I(Y)4"(SLD)(100MIL)
|
LF
|
4,050.000
|
$1.000
|
$2.350
|
$3.000
|
$2.470
|
$2.940
|
|
Totals: |
$3,608,105.905
|
$3,804,555.920
|
$4,569,248.250
|
$4,675,276.410
|
$5,415,621.677
|