PREPARING ROW
|
STA
|
665.000
|
$500.000
|
$383.000
|
$273.890
|
$1,010.000
|
$800.000
|
$1,100.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
50,892.000
|
$11.000
|
$8.230
|
$12.540
|
$8.000
|
$10.000
|
$13.500
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
13,971.000
|
$10.000
|
$7.000
|
$12.320
|
$5.000
|
$10.000
|
$36.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
215,709.000
|
$0.750
|
$0.660
|
$0.850
|
$0.600
|
$0.600
|
$0.600
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
215,709.000
|
$0.270
|
$0.340
|
$0.320
|
$0.330
|
$0.320
|
$0.300
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
107,855.000
|
$0.250
|
$0.320
|
$0.300
|
$0.310
|
$0.280
|
$0.300
|
|
|
CELL FBR MLCH SEED(TEMP)(COOL)
|
SY
|
107,855.000
|
$0.250
|
$0.320
|
$0.300
|
$0.310
|
$0.280
|
$0.300
|
|
|
VEGETATIVE WATERING
|
MG
|
4,329.000
|
$10.000
|
$12.000
|
$17.390
|
$5.000
|
$5.000
|
$7.000
|
|
|
SOIL RETENTION BLANKETS (CL 2) (TY F)
|
SY
|
2,288.000
|
$2.150
|
$2.940
|
$2.750
|
$3.000
|
$2.250
|
$1.900
|
|
|
FL BS (COMP IN PLC)(TY A OR B GR 2)(8")
|
SY
|
207,011.000
|
$9.000
|
$11.400
|
$11.060
|
$12.000
|
$14.500
|
$14.500
|
|
|
REWORK BS MTL (TY B) (8") (ORD COMP)
|
SY
|
142,659.000
|
$1.100
|
$1.480
|
$2.010
|
$1.400
|
$2.750
|
$3.000
|
|
|
LIME (HYDRATED LIME (DRY))
|
TON
|
835.000
|
$110.000
|
$157.000
|
$172.880
|
$160.000
|
$155.000
|
$220.000
|
|
|
LIME TRT (EXST MATL) (12")
|
SY
|
46,372.000
|
$3.000
|
$3.400
|
$2.930
|
$3.400
|
$2.500
|
$5.000
|
|
|
CEMENT
|
TON
|
4,259.000
|
$140.000
|
$156.000
|
$174.470
|
$156.000
|
$150.000
|
$170.000
|
|
|
CEMENT TREAT (EXIST MATL)(12")
|
SY
|
236,584.000
|
$1.500
|
$1.000
|
$2.020
|
$2.200
|
$2.000
|
$2.000
|
|
|
ASPH (AC-20-5TR)
|
GAL
|
157,328.000
|
$3.500
|
$3.000
|
$3.020
|
$3.200
|
$3.000
|
$3.300
|
|
|
ASPH (HFRS-2P)
|
GAL
|
66,244.000
|
$3.800
|
$3.200
|
$3.090
|
$3.200
|
$3.500
|
$3.350
|
|
|
AGGR(TY-PB GR-3 SAC-B)
|
CY
|
1,801.000
|
$107.000
|
$133.000
|
$119.940
|
$150.000
|
$115.000
|
$119.000
|
|
|
AGGR (TY-B GR-5 OR TY-L GR-5)
|
CY
|
1,753.000
|
$98.000
|
$112.000
|
$84.000
|
$150.000
|
$90.000
|
$94.000
|
|
|
AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B)
|
CY
|
1,656.000
|
$105.000
|
$132.000
|
$109.000
|
$125.000
|
$115.000
|
$130.000
|
|
|
CEM STABIL BKFL
|
CY
|
792.000
|
$165.000
|
$100.000
|
$85.480
|
$125.000
|
$150.000
|
$65.000
|
|
|
CUT & RESTORING PAV
|
SY
|
817.000
|
$150.000
|
$12.000
|
$87.940
|
$35.000
|
$55.000
|
$140.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
723.000
|
$12.000
|
$13.250
|
$2.220
|
$11.000
|
$5.000
|
$1.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(12 IN)
|
CY
|
258.000
|
$95.000
|
$134.000
|
$133.910
|
$188.000
|
$90.000
|
$200.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
230.000
|
$475.000
|
$429.000
|
$533.640
|
$540.000
|
$500.000
|
$300.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)
|
LF
|
80.000
|
$160.000
|
$211.000
|
$232.620
|
$245.000
|
$280.000
|
$280.000
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
76.000
|
$500.000
|
$228.000
|
$245.890
|
$265.000
|
$300.000
|
$308.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
6,431.000
|
$60.000
|
$54.000
|
$45.160
|
$63.000
|
$60.000
|
$85.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
550.000
|
$75.000
|
$65.000
|
$53.540
|
$77.000
|
$80.000
|
$115.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
243.000
|
$115.000
|
$90.000
|
$77.520
|
$110.000
|
$130.000
|
$150.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
186.000
|
$135.000
|
$120.000
|
$98.780
|
$130.000
|
$140.000
|
$195.000
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
129.000
|
$280.000
|
$145.000
|
$131.330
|
$160.000
|
$225.000
|
$225.000
|
|
|
RC PIPE (CL III)(60 IN)
|
LF
|
125.000
|
$250.000
|
$300.000
|
$268.650
|
$360.000
|
$360.000
|
$373.000
|
|
|
RC PIPE (CL IV)(18 IN)
|
LF
|
331.000
|
$85.000
|
$58.000
|
$51.440
|
$74.000
|
$90.000
|
$95.000
|
|
|
RC PIPE (CL IV)(24 IN)
|
LF
|
646.000
|
$73.400
|
$82.000
|
$61.920
|
$100.000
|
$100.000
|
$115.000
|
|
|
RC PIPE (CL IV)(36 IN)
|
LF
|
306.000
|
$243.800
|
$145.000
|
$111.990
|
$160.000
|
$165.000
|
$205.000
|
|
|
RC PIPE (CL IV)(42 IN)
|
LF
|
241.000
|
$200.000
|
$180.000
|
$147.660
|
$200.000
|
$220.000
|
$250.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
1.000
|
$4,000.000
|
$6,600.000
|
$4,500.000
|
$7,500.000
|
$5,500.000
|
$5,500.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 60 IN)
|
EA
|
6.000
|
$9,500.000
|
$15,000.000
|
$14,000.000
|
$15,000.000
|
$15,000.000
|
$9,000.000
|
|
|
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
|
EA
|
2.000
|
$4,894.810
|
$5,300.000
|
$8,500.000
|
$5,800.000
|
$4,500.000
|
$2,500.000
|
|
|
SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C)
|
EA
|
2.000
|
$5,315.000
|
$5,400.000
|
$9,500.000
|
$5,800.000
|
$6,500.000
|
$2,600.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 3 FT)(3:1) (C)
|
EA
|
4.000
|
$3,500.000
|
$5,650.000
|
$11,000.000
|
$5,900.000
|
$3,200.000
|
$3,100.000
|
|
|
SET (TY II) (18 IN) (RCP) (3: 1) (C)
|
EA
|
16.000
|
$750.000
|
$600.000
|
$843.400
|
$750.000
|
$700.000
|
$1,100.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
194.000
|
$900.000
|
$725.000
|
$1,022.260
|
$850.000
|
$1,000.000
|
$1,275.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
31.000
|
$1,000.000
|
$750.000
|
$1,049.310
|
$900.000
|
$800.000
|
$1,200.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
16.000
|
$1,200.000
|
$1,000.000
|
$1,291.200
|
$950.000
|
$1,200.000
|
$1,400.000
|
|
|
SET (TY II) (30 IN) (RCP) (3: 1) (C)
|
EA
|
8.000
|
$1,500.000
|
$1,350.000
|
$1,479.240
|
$1,200.000
|
$1,500.000
|
$1,600.000
|
|
|
SET (TY II) (36 IN) (RCP) (3: 1) (C)
|
EA
|
14.000
|
$2,500.000
|
$2,350.000
|
$2,459.430
|
$2,500.000
|
$2,200.000
|
$1,900.000
|
|
|
SET (TY II) (42 IN) (RCP) (3: 1) (C)
|
EA
|
16.000
|
$3,000.000
|
$3,100.000
|
$3,296.240
|
$3,500.000
|
$2,800.000
|
$2,200.000
|
|
|
REMOV STR (SET)
|
EA
|
10.000
|
$250.000
|
$300.000
|
$550.000
|
$185.000
|
$350.000
|
$400.000
|
|
|
REMOV STR (PIPE)
|
EA
|
118.000
|
$500.000
|
$310.000
|
$350.000
|
$800.000
|
$400.000
|
$800.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$994,229.200
|
$376,700.000
|
$398,555.670
|
$900,000.000
|
$1,050,000.000
|
$950,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
19.000
|
$2,500.000
|
$9,630.000
|
$17,079.550
|
$7,000.000
|
$5,000.000
|
$12,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
5,640.000
|
$25.000
|
$26.740
|
$25.000
|
$26.000
|
$26.000
|
$30.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
5,640.000
|
$5.000
|
$9.500
|
$9.000
|
$9.000
|
$5.000
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
12,094.000
|
$3.000
|
$2.500
|
$2.350
|
$2.500
|
$2.500
|
$3.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
12,094.000
|
$0.500
|
$0.800
|
$0.750
|
$0.800
|
$0.500
|
$1.000
|
|
|
CONC CURB (RIBBON)
|
LF
|
338.000
|
$35.000
|
$53.000
|
$55.200
|
$50.000
|
$50.000
|
$8.000
|
|
|
INTERSECTIONS (ACP)
|
SY
|
658.000
|
$24.000
|
$43.250
|
$55.850
|
$44.000
|
$35.000
|
$43.000
|
|
|
TURNOUTS (SURF TREAT)
|
SY
|
1,099.000
|
$136.000
|
$45.350
|
$23.590
|
$24.000
|
$23.000
|
$35.000
|
|
|
DRIVEWAYS AND TURNOUTS (SURF TREAT)
|
SY
|
12,714.000
|
$20.000
|
$34.000
|
$31.440
|
$29.000
|
$30.000
|
$35.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
3,275.000
|
$25.000
|
$18.000
|
$19.500
|
$18.000
|
$24.000
|
$24.000
|
|
|
MTL BEAM GD FEN TRANS (T101)
|
EA
|
8.000
|
$900.000
|
$1,400.000
|
$990.000
|
$1,100.000
|
$1,100.000
|
$1,500.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
800.000
|
$3.000
|
$4.250
|
$1.750
|
$4.500
|
$4.000
|
$6.500
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
8.000
|
$175.000
|
$400.000
|
$150.000
|
$380.000
|
$150.000
|
$1,600.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
24.000
|
$2,600.000
|
$2,620.000
|
$2,475.000
|
$2,600.000
|
$2,900.000
|
$2,600.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
43.000
|
$150.000
|
$123.000
|
$124.490
|
$125.000
|
$200.000
|
$130.000
|
|
|
MAILBOX INSTALL-D (WC-POST) TY 3
|
EA
|
3.000
|
$270.000
|
$166.000
|
$167.790
|
$165.000
|
$250.000
|
$165.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
8.000
|
$500.000
|
$500.000
|
$487.130
|
$475.000
|
$600.000
|
$500.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
128.000
|
$350.000
|
$380.000
|
$384.290
|
$375.000
|
$500.000
|
$400.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
4.000
|
$450.000
|
$423.000
|
$427.590
|
$420.000
|
$550.000
|
$400.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
|
EA
|
1.000
|
$800.000
|
$840.000
|
$849.760
|
$830.000
|
$850.000
|
$800.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$700.000
|
$800.000
|
$736.100
|
$720.000
|
$700.000
|
$750.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
131.000
|
$50.000
|
$48.000
|
$48.710
|
$50.000
|
$90.000
|
$50.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
74.000
|
$65.000
|
$59.000
|
$59.540
|
$60.000
|
$65.000
|
$62.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
28.000
|
$45.000
|
$35.000
|
$30.310
|
$30.000
|
$32.000
|
$30.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(BRK)
|
LF
|
6,390.000
|
$0.890
|
$1.070
|
$1.000
|
$0.200
|
$1.100
|
$1.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
107,135.000
|
$2.000
|
$0.750
|
$0.700
|
$0.200
|
$0.750
|
$0.750
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
13,390.000
|
$1.000
|
$1.000
|
$0.030
|
$0.650
|
$1.000
|
$0.600
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
251.000
|
$9.000
|
$6.420
|
$15.000
|
$6.500
|
$6.200
|
$6.500
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
|
LF
|
134,290.000
|
$0.650
|
$0.640
|
$0.700
|
$0.650
|
$0.620
|
$0.650
|
|
|
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
|
LF
|
5,580.000
|
$0.900
|
$1.070
|
$0.740
|
$1.100
|
$1.200
|
$1.100
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
106,325.000
|
$0.650
|
$0.640
|
$0.700
|
$0.650
|
$0.620
|
$0.650
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,598.000
|
$4.000
|
$3.640
|
$3.850
|
$3.600
|
$3.500
|
$3.750
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
6.000
|
$10,000.000
|
$6,400.000
|
$13,488.660
|
$5,000.000
|
$10,000.000
|
$30,000.000
|
|
|
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
|
LF
|
90.000
|
$15.000
|
$21.390
|
$15.000
|
$22.000
|
$25.000
|
$60.000
|
|
|
TMA (STATIONARY)
|
DAY
|
304.000
|
$194.000
|
$270.000
|
$152.160
|
$200.000
|
$200.000
|
$165.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
42.000
|
$175.000
|
$500.000
|
$152.160
|
$55.000
|
$500.000
|
$200.000
|
|
Totals: |
$10,021,113.850
|
$9,543,192.090
|
$10,181,938.480
|
$10,936,801.820
|
$11,576,158.580
|
$13,202,571.600
|