PREPARING ROW
|
STA
|
192.000
|
$1,000.000
|
$350.000
|
$1,500.000
|
$1,041.670
|
$600.000
|
$890.000
|
$448.620
|
$927.590
|
$1,840.000
|
$1,400.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
26,166.000
|
$15.000
|
$13.000
|
$7.500
|
$12.270
|
$10.000
|
$12.650
|
$12.230
|
$12.690
|
$8.000
|
$25.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
22,730.000
|
$10.000
|
$8.600
|
$4.000
|
$9.990
|
$7.000
|
$9.350
|
$5.700
|
$10.930
|
$15.500
|
$9.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
67,074.000
|
$1.500
|
$1.110
|
$1.000
|
$1.260
|
$1.250
|
$1.650
|
$0.880
|
$0.960
|
$1.750
|
$1.300
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
67,074.000
|
$0.150
|
$0.170
|
$0.200
|
$0.120
|
$0.120
|
$0.170
|
$0.190
|
$0.140
|
$0.120
|
$0.300
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
SY
|
33,537.000
|
$0.150
|
$0.110
|
$0.200
|
$0.120
|
$0.090
|
$0.110
|
$0.120
|
$0.110
|
$0.120
|
$0.300
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
SY
|
33,537.000
|
$0.150
|
$0.110
|
$0.200
|
$0.120
|
$0.090
|
$0.110
|
$0.120
|
$0.100
|
$0.120
|
$0.300
|
|
|
VEGETATIVE WATERING
|
MG
|
545.000
|
$25.000
|
$23.200
|
$20.000
|
$16.650
|
$20.000
|
$15.000
|
$13.630
|
$30.920
|
$32.000
|
$33.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY C)
|
SY
|
67,074.000
|
$1.250
|
$0.800
|
$1.000
|
$0.940
|
$0.920
|
$0.830
|
$0.920
|
$1.110
|
$1.020
|
$1.400
|
|
|
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
|
CY
|
13,716.000
|
$50.000
|
$52.000
|
$44.000
|
$54.430
|
$42.000
|
$47.700
|
$50.720
|
$44.870
|
$48.000
|
$77.000
|
|
|
PRIME COAT (MULTI OPTION)
|
GAL
|
9,475.000
|
$4.250
|
$4.200
|
$4.000
|
$3.830
|
$3.500
|
$4.000
|
$5.140
|
$4.760
|
$4.000
|
$4.500
|
|
|
ASPH (TIER I)
|
GAL
|
40,107.000
|
$3.250
|
$3.450
|
$3.000
|
$3.310
|
$2.800
|
$3.200
|
$3.260
|
$3.520
|
$3.800
|
$4.200
|
|
|
AGGR(TY-PD GR-4 SAC-B)
|
CY
|
879.000
|
$93.000
|
$103.000
|
$104.000
|
$98.060
|
$100.000
|
$111.000
|
$104.140
|
$123.680
|
$110.000
|
$118.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 1")
|
SY
|
666.000
|
$2.000
|
$8.400
|
$7.000
|
$3.610
|
$4.500
|
$4.000
|
$8.480
|
$5.370
|
$3.000
|
$6.700
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
4,304.000
|
$2.600
|
$4.200
|
$3.000
|
$3.610
|
$4.500
|
$4.000
|
$1.920
|
$3.670
|
$3.000
|
$4.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
135.000
|
$5.000
|
$21.100
|
$15.000
|
$22.390
|
$21.000
|
$22.000
|
$24.980
|
$3.780
|
$22.000
|
$22.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
8,644.000
|
$20.000
|
$27.700
|
$29.000
|
$25.000
|
$40.000
|
$42.300
|
$36.450
|
$22.260
|
$50.000
|
$39.000
|
|
|
RETAINING WALL (MSE)
|
SF
|
5,354.000
|
$55.000
|
$56.000
|
$80.000
|
$39.000
|
$81.000
|
$65.000
|
$79.720
|
$49.320
|
$62.000
|
$59.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
44.000
|
$250.000
|
$343.000
|
$370.000
|
$351.510
|
$395.000
|
$360.000
|
$405.910
|
$222.380
|
$275.000
|
$370.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
1,068.000
|
$435.000
|
$411.000
|
$435.000
|
$390.000
|
$400.000
|
$418.000
|
$439.320
|
$357.950
|
$420.000
|
$430.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
80.000
|
$450.000
|
$421.000
|
$515.000
|
$400.000
|
$415.000
|
$488.000
|
$480.850
|
$444.610
|
$445.000
|
$440.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
205.000
|
$150.000
|
$144.000
|
$140.000
|
$140.000
|
$150.000
|
$177.000
|
$242.520
|
$126.150
|
$235.000
|
$250.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
171.000
|
$485.000
|
$559.000
|
$485.000
|
$550.000
|
$550.000
|
$500.000
|
$440.730
|
$460.290
|
$580.000
|
$583.000
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL3)
|
LF
|
307.000
|
$40.000
|
$26.400
|
$90.000
|
$25.750
|
$40.000
|
$28.000
|
$31.220
|
$37.470
|
$39.000
|
$29.000
|
|
|
RAIL (TY SSTR) (W/DRAIN SLOTS)
|
LF
|
687.000
|
$60.000
|
$72.000
|
$90.000
|
$60.000
|
$150.000
|
$87.600
|
$88.520
|
$111.890
|
$65.000
|
$128.000
|
|
|
RETROFIT RAIL (TY T631)
|
LF
|
977.000
|
$85.000
|
$56.700
|
$65.000
|
$55.000
|
$70.000
|
$69.000
|
$65.180
|
$51.330
|
$58.000
|
$97.000
|
|
|
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
|
LF
|
18.000
|
$500.000
|
$522.000
|
$660.000
|
$554.120
|
$530.000
|
$554.000
|
$618.240
|
$518.470
|
$550.000
|
$567.000
|
|
|
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
|
LF
|
24.000
|
$525.000
|
$496.000
|
$690.000
|
$526.140
|
$500.000
|
$525.000
|
$587.010
|
$746.830
|
$525.000
|
$538.000
|
|
|
CONC BOX CULV (10 FT X 9 FT)(EXTEND)
|
LF
|
10.000
|
$1,000.000
|
$2,120.000
|
$2,300.000
|
$2,250.080
|
$2,150.000
|
$2,250.000
|
$2,510.410
|
$1,629.440
|
$2,200.000
|
$2,300.000
|
|
|
CONC BOX CULV (10 FT X 10 FT)(EXTEND)
|
LF
|
56.000
|
$1,250.000
|
$1,210.000
|
$1,600.000
|
$1,200.000
|
$1,225.000
|
$1,280.000
|
$1,430.060
|
$1,303.550
|
$1,250.000
|
$1,310.000
|
|
|
CONC BOX CULV (5 FT X 6.5 FT)(EXTEND)
|
LF
|
27.000
|
$250.000
|
$728.000
|
$1,000.000
|
$772.420
|
$740.000
|
$770.000
|
$861.780
|
$1,156.370
|
$850.000
|
$790.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
80.000
|
$70.000
|
$127.000
|
$180.000
|
$134.330
|
$130.000
|
$134.000
|
$149.880
|
$81.170
|
$130.000
|
$137.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
4.000
|
$160.000
|
$227.000
|
$300.000
|
$240.680
|
$230.000
|
$240.000
|
$268.530
|
$108.430
|
$235.000
|
$245.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
10.000
|
$165.000
|
$227.000
|
$325.000
|
$240.680
|
$230.000
|
$240.000
|
$268.530
|
$130.270
|
$240.000
|
$245.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
7.000
|
$6,000.000
|
$6,180.000
|
$7,500.000
|
$6,300.000
|
$6,300.000
|
$6,500.000
|
$7,325.160
|
$5,962.590
|
$6,500.000
|
$6,700.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
1.000
|
$6,500.000
|
$7,620.000
|
$10,000.000
|
$8,000.000
|
$7,800.000
|
$8,000.000
|
$9,029.990
|
$7,098.740
|
$8,000.000
|
$8,300.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 30 IN)
|
EA
|
1.000
|
$9,500.000
|
$7,120.000
|
$17,000.000
|
$7,000.000
|
$7,200.000
|
$7,500.000
|
$8,436.750
|
$10,295.940
|
$7,500.000
|
$7,700.000
|
|
|
WINGWALL (FW - 0) (HW=5 FT)
|
EA
|
1.000
|
$8,750.000
|
$12,400.000
|
$12,597.000
|
$13,000.000
|
$12,500.000
|
$13,000.000
|
$14,675.310
|
$9,692.050
|
$13,000.000
|
$13,500.000
|
|
|
WINGWALL (PW - 1) (HW=12 FT)
|
EA
|
2.000
|
$45,000.000
|
$54,600.000
|
$102,500.000
|
$50,000.000
|
$55,000.000
|
$58,000.000
|
$64,633.800
|
$83,587.490
|
$57,000.000
|
$59,000.000
|
|
|
WINGWALL (PW - 1) (HW=5 FT)
|
EA
|
3.000
|
$14,000.000
|
$11,300.000
|
$17,500.000
|
$12,000.000
|
$11,500.000
|
$12,000.000
|
$13,426.350
|
$13,694.540
|
$12,000.000
|
$12,300.000
|
|
|
WINGWALL (PW - 1) (HW=7 FT)
|
EA
|
2.000
|
$20,000.000
|
$26,600.000
|
$26,000.000
|
$25,000.000
|
$27,000.000
|
$28,000.000
|
$31,536.300
|
$27,099.970
|
$28,000.000
|
$29,000.000
|
|
|
WINGWALL (SW - 0) (HW=12 FT)
|
EA
|
1.000
|
$30,000.000
|
$33,100.000
|
$66,000.000
|
$20,000.000
|
$33,500.000
|
$35,000.000
|
$39,248.650
|
$43,286.750
|
$35,000.000
|
$36,000.000
|
|
|
HEADWALL (CH - PW - 0)(DIA=36 IN)(MOD)
|
EA
|
1.000
|
$18,000.000
|
$500.000
|
$10,000.000
|
$5,000.000
|
$9,300.000
|
$1,000.000
|
$10,913.260
|
$13,981.620
|
$9,500.000
|
$10,000.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
18.000
|
$3,000.000
|
$5,270.000
|
$1,750.000
|
$5,000.000
|
$2,000.000
|
$5,500.000
|
$6,244.810
|
$2,350.540
|
$3,500.000
|
$5,800.000
|
|
|
REMOV STR (SET)
|
EA
|
10.000
|
$500.000
|
$343.000
|
$500.000
|
$350.000
|
$350.000
|
$360.000
|
$406.220
|
$649.240
|
$360.000
|
$372.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
8.000
|
$1,500.000
|
$501.000
|
$1,500.000
|
$530.000
|
$500.000
|
$530.000
|
$594.170
|
$1,510.540
|
$525.000
|
$545.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
8.000
|
$1,800.000
|
$685.000
|
$1,500.000
|
$700.000
|
$700.000
|
$725.000
|
$812.430
|
$1,060.680
|
$720.000
|
$745.000
|
|
|
REMOV STR (RAILROAD CROSSING)
|
EA
|
1.000
|
$10,000.000
|
$19,000.000
|
$25,000.000
|
$4,000.000
|
$35,000.000
|
$18,000.000
|
$28,894.960
|
$3,942.190
|
$20,000.000
|
$24,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$463,000.000
|
$405,000.000
|
$304,000.000
|
$548,500.000
|
$590,000.000
|
$597,500.000
|
$132,105.340
|
$587,463.080
|
$640,000.000
|
$550,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
14.000
|
$8,500.000
|
$2,500.000
|
$2,500.000
|
$3,000.000
|
$8,000.000
|
$2,700.000
|
$10,883.090
|
$12,367.640
|
$6,300.000
|
$1,200.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
560.000
|
$28.000
|
$23.700
|
$30.000
|
$28.140
|
$23.000
|
$35.000
|
$27.280
|
$30.750
|
$30.000
|
$33.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
560.000
|
$12.000
|
$6.900
|
$11.500
|
$11.260
|
$6.500
|
$17.500
|
$7.880
|
$8.180
|
$12.000
|
$16.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
224.000
|
$29.000
|
$10.000
|
$25.000
|
$22.590
|
$9.500
|
$17.000
|
$11.520
|
$24.300
|
$24.000
|
$20.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
224.000
|
$10.000
|
$5.000
|
$8.000
|
$8.000
|
$4.750
|
$13.500
|
$5.760
|
$9.410
|
$8.500
|
$12.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
34,940.000
|
$2.300
|
$1.950
|
$3.000
|
$1.920
|
$2.500
|
$2.350
|
$2.240
|
$3.390
|
$2.000
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
34,940.000
|
$0.500
|
$0.210
|
$0.500
|
$0.400
|
$0.200
|
$0.350
|
$0.240
|
$0.510
|
$0.420
|
$1.100
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
280.000
|
$45.000
|
$24.900
|
$70.000
|
$36.550
|
$80.000
|
$48.000
|
$113.260
|
$36.100
|
$60.000
|
$35.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
110.000
|
$10.000
|
$33.300
|
$25.000
|
$37.830
|
$65.000
|
$30.000
|
$97.010
|
$5.370
|
$30.000
|
$102.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
280.000
|
$10.000
|
$24.700
|
$16.000
|
$36.430
|
$40.000
|
$20.000
|
$69.250
|
$8.280
|
$35.000
|
$35.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
533.000
|
$48.000
|
$37.700
|
$48.000
|
$39.420
|
$30.000
|
$38.000
|
$35.640
|
$48.950
|
$26.000
|
$24.000
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
430.000
|
$22.000
|
$32.400
|
$24.000
|
$39.420
|
$24.000
|
$34.000
|
$57.130
|
$18.420
|
$23.000
|
$22.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
3,408.000
|
$20.000
|
$22.200
|
$21.000
|
$21.000
|
$22.000
|
$22.000
|
$25.460
|
$22.260
|
$22.000
|
$28.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
3.000
|
$950.000
|
$1,190.000
|
$1,250.000
|
$1,124.230
|
$1,150.000
|
$1,315.000
|
$1,363.230
|
$1,174.930
|
$1,200.000
|
$1,100.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
5,817.000
|
$1.000
|
$1.600
|
$2.500
|
$1.500
|
$1.550
|
$2.150
|
$1.820
|
$1.550
|
$1.600
|
$1.700
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
24.000
|
$225.000
|
$216.000
|
$190.000
|
$204.860
|
$215.000
|
$200.000
|
$248.410
|
$123.680
|
$220.000
|
$280.000
|
|
|
GDRAIL END TRT(INST)(WOOD POST)(TY I)
|
EA
|
16.000
|
$2,400.000
|
$2,860.000
|
$2,500.000
|
$2,707.430
|
$2,750.000
|
$2,650.000
|
$3,282.990
|
$2,288.010
|
$2,900.000
|
$3,100.000
|
|
|
PIPE UNDERDRAINS (TY 6) (6")
|
LF
|
687.000
|
$8.000
|
$6.700
|
$25.000
|
$27.170
|
$15.000
|
$21.000
|
$36.380
|
$14.410
|
$14.720
|
$28.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
1.000
|
$400.000
|
$206.000
|
$200.000
|
$195.000
|
$200.000
|
$210.000
|
$236.460
|
$432.870
|
$210.000
|
$272.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
18.000
|
$525.000
|
$505.000
|
$500.000
|
$478.640
|
$490.000
|
$520.000
|
$580.390
|
$559.360
|
$520.000
|
$682.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
12.000
|
$550.000
|
$609.000
|
$600.000
|
$577.690
|
$600.000
|
$625.000
|
$700.500
|
$714.230
|
$625.000
|
$876.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
2.000
|
$800.000
|
$858.000
|
$850.000
|
$813.880
|
$840.000
|
$880.000
|
$986.900
|
$1,004.250
|
$880.000
|
$1,100.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
31.000
|
$100.000
|
$90.600
|
$90.000
|
$85.930
|
$90.000
|
$90.000
|
$104.200
|
$92.760
|
$92.000
|
$167.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
8.000
|
$20.000
|
$12.200
|
$12.000
|
$11.590
|
$12.000
|
$12.600
|
$14.060
|
$19.170
|
$12.500
|
$17.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
16.000
|
$40.000
|
$57.900
|
$57.000
|
$54.900
|
$57.000
|
$59.500
|
$66.570
|
$43.290
|
$58.000
|
$72.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
153.000
|
$25.000
|
$18.200
|
$17.500
|
$17.250
|
$18.000
|
$18.750
|
$54.870
|
$20.340
|
$18.000
|
$31.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,668.000
|
$0.850
|
$1.670
|
$1.100
|
$1.450
|
$1.250
|
$1.000
|
$2.220
|
$0.930
|
$1.300
|
$0.900
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
1,820.000
|
$0.850
|
$1.670
|
$1.100
|
$1.450
|
$1.250
|
$1.000
|
$2.180
|
$0.930
|
$1.300
|
$0.900
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
680.000
|
$1.050
|
$0.540
|
$0.550
|
$0.540
|
$0.540
|
$0.550
|
$0.620
|
$0.620
|
$1.050
|
$0.600
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
15.000
|
$15.000
|
$30.600
|
$30.000
|
$30.730
|
$30.540
|
$31.500
|
$35.160
|
$24.740
|
$16.000
|
$32.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
4.000
|
$115.000
|
$190.000
|
$200.000
|
$190.470
|
$189.000
|
$195.000
|
$218.270
|
$371.030
|
$165.000
|
$200.000
|
|
REFL PAV MRK TY II (W) 4" (BRK)
|
LF
|
2,500.000
|
$0.170
|
$0.110
|
$0.150
|
$0.140
|
$0.110
|
$0.110
|
$0.120
|
$0.160
|
$0.130
|
$0.100
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
36,630.000
|
$0.170
|
$0.110
|
$0.150
|
$0.140
|
$0.110
|
$0.110
|
$0.120
|
$0.160
|
$0.130
|
$0.100
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
36,360.000
|
$0.170
|
$0.120
|
$0.150
|
$0.150
|
$0.120
|
$0.120
|
$0.130
|
$0.160
|
$0.130
|
$0.100
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
2,500.000
|
$0.360
|
$0.540
|
$0.550
|
$0.540
|
$0.540
|
$0.550
|
$0.620
|
$0.620
|
$0.540
|
$0.600
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
|
LF
|
36,630.000
|
$0.600
|
$0.550
|
$0.550
|
$0.550
|
$0.550
|
$0.570
|
$0.630
|
$0.720
|
$0.620
|
$0.600
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
36,360.000
|
$0.600
|
$0.550
|
$0.550
|
$0.550
|
$0.550
|
$0.570
|
$0.630
|
$0.720
|
$0.650
|
$0.600
|
|
REFL PAV MRKR TY I-C
|
EA
|
126.000
|
$4.000
|
$4.200
|
$4.500
|
$4.250
|
$4.200
|
$4.350
|
$4.850
|
$6.180
|
$3.850
|
$4.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
898.000
|
$4.000
|
$2.900
|
$3.000
|
$2.910
|
$2.900
|
$2.950
|
$3.330
|
$6.180
|
$3.850
|
$3.100
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
4.000
|
$22.000
|
$4.200
|
$2.000
|
$1.070
|
$1.000
|
$1.000
|
$1.210
|
$123.680
|
$59.000
|
$1.100
|
|
|
D-GR HMA TY-C PG76-22
|
TON
|
12,230.000
|
$82.000
|
$79.100
|
$81.000
|
$80.190
|
$81.000
|
$71.500
|
$101.970
|
$93.990
|
$78.000
|
$85.000
|
|
|
D-GR HMA TY-C PG76-22 (LEVEL-UP)
|
TON
|
237.000
|
$110.000
|
$111.000
|
$104.000
|
$100.350
|
$125.000
|
$112.000
|
$137.900
|
$117.490
|
$110.000
|
$106.000
|
|
|
TACK COAT
|
GAL
|
3,433.000
|
$3.250
|
$4.750
|
$2.750
|
$3.060
|
$4.000
|
$3.000
|
$5.710
|
$4.890
|
$4.250
|
$5.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$7,500.000
|
$539.000
|
$2,000.000
|
$7,000.000
|
$5,000.000
|
$10,000.000
|
$7,119.510
|
$6,183.820
|
$25,000.000
|
$7,800.000
|
|
|
TMA (STATIONARY)
|
DAY
|
200.000
|
$175.000
|
$35.000
|
$125.000
|
$220.000
|
$175.000
|
$140.000
|
$243.490
|
$185.510
|
$210.000
|
$85.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
80.000
|
$55.000
|
$10.000
|
$55.000
|
$100.000
|
$60.000
|
$40.000
|
$48.850
|
$123.680
|
$150.000
|
$167.000
|
|
|
REML & DISPL DRIFTWOOD & DEBRIS
|
LS
|
1.000
|
$10,000.000
|
$5,270.000
|
$5,000.000
|
$16,650.000
|
$9,500.000
|
$6,500.000
|
$8,404.950
|
$2,559.300
|
$3,900.000
|
$3,700.000
|
|
Totals: |
$5,808,873.950
|
$5,448,731.920
|
$5,694,944.150
|
$5,706,980.930
|
$5,866,111.270
|
$5,972,442.240
|
$6,065,154.710
|
$6,092,095.420
|
$6,483,485.330
|
$7,163,082.600
|