MADISON BETHEL CEMETERY RD (0917-31-036)
Items: 34
County: MADISON
Length: 0.0000 MILES (0.1377 MILES)
Highway: BETHEL CEMETERY RD
District: BRYAN
Control Number: 0917-31-036
DBE Goal: 0.0%
Project: BR 2024(157)
Guaranty: $21,000.00
Time: 105 WORKING DAYS
Engineer's Estimate: $1,040,840.10
Date: 09/03/2026 1:00 PM CDT (16 days ago) Changed
Contract Number: 9263016
Type: BRIDGE REPLACEMENT
Project ID: A00189990
Contract Type: FEDERAL
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DELMY REYES
MATT HENSARLING
MADISON BETHEL CEMETERY RD (0917-31-036)
Project Name: N/A
Project: BR 2024(157)
Engineer's Estimate: $530,140.30
Length: 0.0000 MILES (0.0659 MILES)
Project Class: BRIDGE REPLACEMENT
Limits From: ON CR 444 (BETHEL CEMETERY RD, F-CR
Limits To: AT BEDIAS CREEK
Project Description: REPLACE BRIDGE AND APPROACHES
MADISON WALDRIP RD (0917-31-037)
Project Name: CR 307 AT LARRISON CREEK
Project: BR 2B23(231)
Engineer's Estimate: $510,699.80
Length: N/A (0.0718 MILES)
Project Class: BRIDGE REPLACEMENT
Limits From: ON CR 307 (LOCAL-WALDRIP LN, F-CR 149)
Limits To: AT LARRISON CREEK
Project Description: REPLACE BRIDGE AND APPROACHES
Bidders (7)
E
Engineer's Estimate
$1,040,840.10
$1,143,373.20
Over/Under Est:
9.85%
$102,533.10
$1,146,634.77
Over/Under Est:
10.16%
$105,794.67
Amt Left:
0.29%
$3,261.57
$1,162,175.10
Over/Under Est:
11.66%
$121,335.00
Amt Left:
1.64%
$18,801.90
Delta:
-1.36%
-$15,540.33
$1,165,655.00
Over/Under Est:
11.99%
$124,814.90
Amt Left:
1.95%
$22,281.80
Delta:
-0.30%
-$3,479.90
$1,227,069.93
Over/Under Est:
17.89%
$186,229.83
Amt Left:
7.32%
$83,696.73
Delta:
-5.27%
-$61,414.93
$1,276,197.21
Over/Under Est:
22.61%
$235,357.11
Amt Left:
11.62%
$132,824.01
Delta:
-4.00%
-$49,127.28
$1,376,782.80
Over/Under Est:
32.28%
$335,942.70
Amt Left:
20.41%
$233,409.60
Delta:
-7.88%
-$100,585.59
Bid Items & Bid Tabulations
34
Total
0 of 34
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $52,000.00 |
| Total: | $57,000.00 |