REMOVING CONC (DRIVEWAYS)
|
SY
|
287.000
|
$13.500
|
$25.000
|
$20.000
|
$20.000
|
$10.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
2,084.000
|
$8.500
|
$10.000
|
$4.000
|
$7.500
|
$9.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
162.000
|
$11.000
|
$15.000
|
$15.000
|
$29.970
|
$27.000
|
|
|
BLADING
|
HR
|
80.000
|
$150.000
|
$60.000
|
$100.000
|
$85.500
|
$140.000
|
|
|
ASPH (AC-15P)
|
GAL
|
15,531.000
|
$3.000
|
$2.500
|
$2.250
|
$2.570
|
$2.500
|
|
|
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
|
CY
|
374.000
|
$75.000
|
$70.000
|
$75.000
|
$69.030
|
$110.000
|
|
|
D-GR HMA (SQ) TY-D PG 70-22(LEVEL-UP)
|
TON
|
6,180.000
|
$80.000
|
$70.000
|
$70.000
|
$67.590
|
$79.000
|
|
|
SUPERPAVE MIXTURES SP-C SAC-A PG76-22
|
TON
|
61,777.000
|
$75.000
|
$64.500
|
$65.000
|
$73.530
|
$75.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
13,610.000
|
$35.000
|
$25.600
|
$38.000
|
$24.730
|
$33.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
40,151.000
|
$1.500
|
$1.100
|
$0.750
|
$1.430
|
$1.500
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
46,532.000
|
$1.500
|
$1.100
|
$1.000
|
$1.430
|
$1.400
|
|
|
FLOWABLE BACKFILL
|
CY
|
27.000
|
$130.000
|
$185.000
|
$285.000
|
$183.750
|
$180.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
189.000
|
$425.000
|
$540.000
|
$335.000
|
$540.740
|
$390.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
148.000
|
$400.000
|
$441.000
|
$330.000
|
$440.990
|
$415.000
|
|
|
RETROFIT RAIL (TY T631)
|
LF
|
400.000
|
$80.000
|
$64.000
|
$65.000
|
$193.860
|
$62.000
|
|
|
RC PIPE (ARCH)(CL IV)(DES 3)
|
LF
|
43.000
|
$100.000
|
$289.000
|
$150.000
|
$288.740
|
$200.000
|
|
|
RC PIPE (ARCH)(CL IV)(DES 4)
|
LF
|
19.000
|
$200.000
|
$436.000
|
$210.000
|
$435.740
|
$250.000
|
|
|
RC PIPE (ARCH)(CL V)(DES 2)
|
LF
|
90.000
|
$200.000
|
$341.000
|
$200.000
|
$341.240
|
$200.000
|
|
|
RC PIPE (ARCH)(CL V)(DES 3)
|
LF
|
14.000
|
$200.000
|
$368.000
|
$240.000
|
$367.490
|
$210.000
|
|
|
SET (TY II) (DES 2) (RCP) (6: 1) (P)
|
EA
|
8.000
|
$1,000.000
|
$2,889.000
|
$1,300.000
|
$2,887.430
|
$2,500.000
|
|
|
SET (TY II) (DES 3) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,000.000
|
$3,150.000
|
$1,400.000
|
$3,149.920
|
$2,600.000
|
|
|
SET (TY II) (DES 4) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,200.000
|
$3,413.000
|
$3,000.000
|
$3,412.420
|
$3,700.000
|
|
|
SET (TY II) (DES 5) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,200.000
|
$3,938.000
|
$4,400.000
|
$3,937.400
|
$4,500.000
|
|
|
REMOV STR (DRIVEWAY CULVERT)
|
EA
|
3.000
|
$500.000
|
$1,575.000
|
$470.000
|
$1,574.960
|
$750.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$616,321.460
|
$400,000.000
|
$491,969.240
|
$515,181.120
|
$407,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
5.000
|
$3,500.000
|
$7,000.000
|
$5,000.000
|
$2,163.430
|
$2,500.000
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
185.000
|
$110.000
|
$100.000
|
$150.000
|
$79.800
|
$200.000
|
|
|
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
|
LF
|
1,260.000
|
$45.000
|
$40.000
|
$65.000
|
$20.000
|
$34.000
|
|
|
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
|
LF
|
6,300.000
|
$16.000
|
$15.000
|
$13.500
|
$20.000
|
$15.000
|
|
|
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
|
LF
|
1,260.000
|
$30.000
|
$20.000
|
$15.500
|
$20.000
|
$16.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
306.000
|
$90.000
|
$84.000
|
$60.000
|
$84.000
|
$81.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
9,734.000
|
$18.000
|
$23.400
|
$16.000
|
$18.750
|
$16.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
263.500
|
$80.000
|
$80.000
|
$60.000
|
$47.000
|
$57.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,450.000
|
$1,688.000
|
$1,500.000
|
$1,885.000
|
$1,500.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
34.000
|
$1,020.000
|
$916.000
|
$870.000
|
$850.000
|
$900.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
9,735.000
|
$2.250
|
$0.900
|
$1.000
|
$1.000
|
$1.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
36.000
|
$180.000
|
$84.000
|
$200.000
|
$150.000
|
$200.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
40.000
|
$2,150.000
|
$2,490.000
|
$1,900.000
|
$2,160.000
|
$1,900.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
36.000
|
$225.000
|
$80.000
|
$200.000
|
$270.000
|
$200.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
4.000
|
$10,000.000
|
$8,000.000
|
$8,500.000
|
$7,100.000
|
$7,775.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
22.000
|
$1,800.000
|
$910.000
|
$1,000.000
|
$1,185.000
|
$880.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
4.000
|
$800.000
|
$105.000
|
$500.000
|
$890.000
|
$100.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
7,586.000
|
$1.150
|
$1.250
|
$1.000
|
$1.580
|
$1.500
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
14,471.000
|
$1.000
|
$1.250
|
$1.000
|
$1.580
|
$1.500
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
7,430.000
|
$0.750
|
$0.660
|
$0.630
|
$0.630
|
$0.650
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
5,103.000
|
$5.250
|
$5.250
|
$5.000
|
$5.000
|
$5.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
136.000
|
$110.000
|
$87.000
|
$83.000
|
$83.000
|
$85.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
39.000
|
$125.000
|
$96.000
|
$91.000
|
$91.000
|
$92.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
25,278.000
|
$0.330
|
$0.300
|
$0.280
|
$0.280
|
$0.300
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
156,118.000
|
$0.280
|
$0.300
|
$0.280
|
$0.280
|
$0.300
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
27,238.000
|
$0.300
|
$0.300
|
$0.280
|
$0.280
|
$0.300
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
125,860.000
|
$0.300
|
$0.300
|
$0.280
|
$0.280
|
$0.300
|
|
REFL PAV MRKR TY I-C
|
EA
|
1,268.000
|
$3.250
|
$2.950
|
$2.800
|
$2.800
|
$3.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
2,946.000
|
$3.250
|
$2.950
|
$2.800
|
$2.800
|
$3.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$9,800.000
|
$8,000.000
|
$10,000.000
|
$7,575.490
|
$7,000.000
|
|
Totals: |
$7,611,638.040
|
$6,593,233.700
|
$6,666,666.660
|
$7,240,274.350
|
$7,278,006.500
|