MCLENNAN VARIOUS (0909-00-101)
Items: 38
County: MCLENNAN
Length: 0.0000 MILES
Highway: VARIOUS
District: WACO
Control Number: 0909-00-101
DBE Goal: 0.0%
Project: C 909-00-101
Guaranty: $55,000.00
Time: 270 WORKING DAYS
Engineer's Estimate: $2,769,436.00
Date: 04/04/2025 1:00 PM CDT (1 year ago)
Contract Number: 4253218
Type: BRIDGE MAINTENANCE
Project ID: A00212191
Project Description: BRIDGE REPAIRS AND STEEL PAINTING IN BELL, BOSQUE, HAMILTON, HILL, FALLS, AND LIMESTONE COUNTIES.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SEE PLANS OR PROPOSAL BOOK
MCLENNAN VARIOUS (0909-00-101)
Project Name: N/A
Project: C 909-00-101
Length: 0.0000 MILES
Project Class: CONSTRUCTION
Limits From: VARIOUS
Limits To: VARIOUS
Project Description: BRIDGE REPAIRS AND STEEL PAINTING IN BELL, BOSQUE, HAMILTON, HILL, FALLS, AND LIMESTONE COUNTIES.
Informational
Bidders (12)
E
Engineer's Estimate
$2,769,436.00
1
Awarded
$3,067,458.00
Over/Under Est:
10.76%
$298,022.00
$3,122,086.00
Over/Under Est:
12.73%
$352,650.00
Amt Left:
1.78%
$54,628.00
$3,495,942.00
Over/Under Est:
26.23%
$726,506.00
Amt Left:
13.97%
$428,484.00
Delta:
-11.97%
-$373,856.00
$3,624,444.75
Over/Under Est:
30.87%
$855,008.75
Amt Left:
18.16%
$556,986.75
Delta:
-3.68%
-$128,502.75
$3,837,008.68
Over/Under Est:
38.55%
$1,067,572.68
Amt Left:
25.09%
$769,550.68
Delta:
-5.86%
-$212,563.93
$3,933,993.00
Over/Under Est:
42.05%
$1,164,557.00
Amt Left:
28.25%
$866,535.00
Delta:
-2.53%
-$96,984.32
$3,936,710.25
Over/Under Est:
42.15%
$1,167,274.25
Amt Left:
28.34%
$869,252.25
Delta:
-0.07%
-$2,717.25
$3,974,304.50
Over/Under Est:
43.51%
$1,204,868.50
Amt Left:
29.56%
$906,846.50
Delta:
-0.95%
-$37,594.25
$4,146,890.00
Over/Under Est:
49.74%
$1,377,454.00
Amt Left:
35.19%
$1,079,432.00
Delta:
-4.34%
-$172,585.50
$4,171,045.00
Over/Under Est:
50.61%
$1,401,609.00
Amt Left:
35.98%
$1,103,587.00
Delta:
-0.58%
-$24,155.00
$4,417,431.00
Over/Under Est:
59.51%
$1,647,995.00
Amt Left:
44.01%
$1,349,973.00
Delta:
-5.91%
-$246,386.00
$4,540,778.00
Over/Under Est:
63.96%
$1,771,342.00
Amt Left:
48.03%
$1,473,320.00
Delta:
-2.79%
-$123,347.00
Bid Items & Bid Tabulations
38
Total
0 of 38
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $20,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| Total: | $30,000.00 |