PREPARING ROW
|
STA
|
16.000
|
$6,000.000
|
$5,000.000
|
$6,670.000
|
$4,901.470
|
$19,287.500
|
$22,419.710
|
|
|
REMOVING CONC (PAV)
|
SY
|
874.000
|
$20.000
|
$15.000
|
$5.000
|
$19.110
|
$30.780
|
$21.740
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
1,097.000
|
$6.400
|
$15.000
|
$5.000
|
$23.740
|
$17.100
|
$9.310
|
|
|
REMOVING STAB BASE AND ASPH PAV (2"-6")
|
SY
|
89.000
|
$6.500
|
$15.000
|
$20.000
|
$11.260
|
$75.240
|
$42.090
|
|
|
REMOVING STAB BASE & ASPH PV(10 TO 16")
|
SY
|
3,148.000
|
$3.000
|
$5.000
|
$7.750
|
$10.820
|
$6.840
|
$18.400
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
1,712.000
|
$12.000
|
$12.000
|
$16.000
|
$22.700
|
$23.940
|
$22.770
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
2,126.000
|
$25.000
|
$12.000
|
$18.000
|
$18.810
|
$23.940
|
$21.140
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
3,588.000
|
$12.000
|
$25.000
|
$36.000
|
$14.580
|
$17.100
|
$33.810
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
6,099.000
|
$2.000
|
$3.500
|
$8.000
|
$2.880
|
$2.520
|
$3.450
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
6,099.000
|
$0.350
|
$1.045
|
$0.250
|
$0.320
|
$0.250
|
$0.300
|
|
|
VEGETATIVE WATERING
|
MG
|
95.200
|
$24.000
|
$40.000
|
$97.000
|
$63.210
|
$41.030
|
$20.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
6,099.000
|
$0.980
|
$2.290
|
$1.850
|
$1.160
|
$1.850
|
$1.100
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
1,387.000
|
$46.000
|
$45.000
|
$65.500
|
$91.260
|
$71.670
|
$100.430
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
890.000
|
$4.100
|
$4.830
|
$4.500
|
$5.080
|
$8.910
|
$4.700
|
|
|
CEM STABIL BKFL
|
CY
|
201.000
|
$77.000
|
$140.000
|
$188.250
|
$240.720
|
$175.000
|
$150.500
|
|
|
TEMPORARY SPL SHORING
|
SF
|
7,319.000
|
$26.000
|
$20.000
|
$19.450
|
$32.440
|
$20.000
|
$80.000
|
|
|
DRILLED SHAFT (36IN)(SRC)
|
LF
|
1,360.000
|
$250.000
|
$365.000
|
$339.000
|
$382.170
|
$310.000
|
$400.000
|
|
|
CL C CONC (ABUT)(SRC)
|
CY
|
64.200
|
$1,300.000
|
$1,211.000
|
$1,000.000
|
$1,375.900
|
$1,400.000
|
$1,635.980
|
|
|
CL C CONC (CAP)
|
CY
|
85.200
|
$2,000.000
|
$1,680.000
|
$1,200.000
|
$1,711.620
|
$1,800.000
|
$1,998.490
|
|
|
CL C CONC (COLUMN)
|
CY
|
87.500
|
$1,600.000
|
$1,344.000
|
$1,400.000
|
$1,385.460
|
$1,150.000
|
$1,226.580
|
|
|
REINF CONC SLAB
|
SF
|
24,380.000
|
$18.000
|
$23.000
|
$23.310
|
$29.130
|
$25.000
|
$23.750
|
|
|
APPROACH SLAB
|
CY
|
83.800
|
$400.000
|
$735.000
|
$775.000
|
$801.900
|
$650.000
|
$738.830
|
|
|
RETAINING WALL (TEMP WALL)
|
SF
|
948.000
|
$20.000
|
$25.000
|
$35.000
|
$53.720
|
$20.000
|
$37.370
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
3,165.060
|
$130.000
|
$195.000
|
$238.400
|
$262.420
|
$190.000
|
$175.990
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
78.000
|
$580.000
|
$450.000
|
$650.000
|
$802.150
|
$845.710
|
$739.530
|
|
|
RAIL (TY T223)
|
LF
|
1,108.000
|
$80.000
|
$75.000
|
$100.000
|
$102.480
|
$150.000
|
$114.520
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
|
LF
|
138.000
|
$130.000
|
$150.000
|
$150.000
|
$169.060
|
$140.000
|
$154.640
|
|
|
GABIONS (GALV)
|
CY
|
2,152.000
|
$280.000
|
$165.000
|
$245.000
|
$202.970
|
$355.070
|
$200.000
|
|
|
REMOV STR (BRIDGE 500 - 999 FT LENGTH)
|
EA
|
1.000
|
$250,000.000
|
$150,000.000
|
$71,450.000
|
$113,803.570
|
$130,000.000
|
$200,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$415,000.000
|
$350,000.000
|
$460,000.000
|
$472,857.560
|
$550,000.000
|
$554,887.910
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
18.000
|
$13,000.000
|
$2,800.000
|
$4,000.000
|
$3,222.010
|
$6,000.000
|
$2,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
110.000
|
$37.000
|
$48.840
|
$37.300
|
$37.030
|
$37.300
|
$35.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
110.000
|
$9.300
|
$27.500
|
$8.900
|
$10.580
|
$8.900
|
$10.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$23.000
|
$43.850
|
$18.150
|
$23.280
|
$18.150
|
$22.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$4.000
|
$19.800
|
$6.000
|
$2.120
|
$6.000
|
$2.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,596.000
|
$3.000
|
$4.980
|
$3.650
|
$2.800
|
$3.650
|
$2.860
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,596.000
|
$0.570
|
$0.660
|
$0.500
|
$1.060
|
$0.500
|
$1.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
388.000
|
$47.000
|
$50.000
|
$25.000
|
$24.040
|
$49.500
|
$22.930
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
18.000
|
$4,800.000
|
$3,000.000
|
$2,100.000
|
$2,327.660
|
$2,834.380
|
$216.500
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
1,530.000
|
$30.000
|
$18.000
|
$24.000
|
$105.850
|
$60.000
|
$83.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
1,280.000
|
$4.000
|
$15.000
|
$9.500
|
$5.340
|
$3.500
|
$3.740
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
1,530.000
|
$4.100
|
$16.000
|
$20.000
|
$21.910
|
$25.000
|
$11.060
|
|
|
DRIVEWAYS (ACP)(TYPE 1)
|
SY
|
82.000
|
$54.000
|
$85.000
|
$100.000
|
$30.940
|
$27.000
|
$98.680
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
1,881.000
|
$0.230
|
$3.000
|
$3.660
|
$3.170
|
$5.260
|
$3.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,175.000
|
$35.000
|
$32.720
|
$29.750
|
$34.490
|
$30.160
|
$32.800
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,600.000
|
$2,884.450
|
$3,222.000
|
$3,013.210
|
$2,659.080
|
$2,486.000
|
|
|
SHORT RADIUS
|
LF
|
25.000
|
$820.000
|
$37.780
|
$34.350
|
$73.530
|
$34.830
|
$69.500
|
|
|
DRIVEWAY TERMINAL ANCHOR SECTION
|
EA
|
1.000
|
$1,200.000
|
$866.840
|
$788.000
|
$1,428.340
|
$799.110
|
$1,350.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,462.500
|
$4.200
|
$4.400
|
$4.000
|
$2.120
|
$4.060
|
$2.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
4.000
|
$250.000
|
$281.020
|
$255.500
|
$370.310
|
$259.060
|
$350.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
3.000
|
$3,300.000
|
$3,525.300
|
$3,205.000
|
$3,232.270
|
$3,249.850
|
$3,055.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,000.000
|
$440.000
|
$550.000
|
$1,322.540
|
$1,295.290
|
$1,250.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$1,000.000
|
$440.000
|
$300.000
|
$370.310
|
$761.300
|
$8,410.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$8,900.000
|
$7,700.000
|
$10,000.000
|
$8,898.010
|
$9,014.910
|
$28.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
6.000
|
$570.000
|
$830.500
|
$755.000
|
$798.810
|
$669.800
|
$755.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
4.000
|
$120.000
|
$137.500
|
$125.000
|
$132.250
|
$116.830
|
$125.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
10.000
|
$27.000
|
$30.800
|
$28.000
|
$29.630
|
$26.120
|
$28.000
|
|
|
INSTL OM ASSM (OM-3R)(TWT)GND
|
EA
|
2.000
|
$350.000
|
$324.500
|
$295.000
|
$312.120
|
$338.100
|
$295.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
54.000
|
$27.000
|
$41.800
|
$38.000
|
$40.210
|
$34.400
|
$38.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
6,060.000
|
$0.630
|
$1.650
|
$1.500
|
$1.590
|
$1.500
|
$1.500
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
24.000
|
$7.500
|
$22.000
|
$20.000
|
$21.160
|
$20.000
|
$20.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
3,021.000
|
$0.450
|
$0.710
|
$0.650
|
$0.690
|
$0.650
|
$0.650
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
3,020.000
|
$0.400
|
$0.710
|
$0.650
|
$0.690
|
$0.650
|
$0.650
|
|
REFL PAV MRKR TY I-C
|
EA
|
18.000
|
$9.600
|
$11.000
|
$10.000
|
$10.580
|
$10.000
|
$10.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
37.000
|
$6.600
|
$11.000
|
$10.000
|
$10.580
|
$10.000
|
$10.000
|
|
|
FULL - WIDTH MOWING
|
CYC
|
6.000
|
$2,700.000
|
$1,500.000
|
$2,000.000
|
$1,626.580
|
$3,950.780
|
$800.000
|
|
|
LITTER REMOVAL
|
CYC
|
17.000
|
$1,700.000
|
$900.000
|
$700.000
|
$841.410
|
$1,565.610
|
$591.770
|
|
|
D-GR HMA TY-C PG70-22 (EXEMPT)
|
TON
|
633.000
|
$170.000
|
$153.180
|
$145.000
|
$176.690
|
$133.200
|
$127.260
|
|
|
SP MIXES SP-C SAC-B PG70-22 (EXEMPT)
|
TON
|
498.000
|
$170.000
|
$161.250
|
$155.000
|
$158.700
|
$133.200
|
$116.130
|
|
|
BONDING COURSE
|
GAL
|
654.000
|
$6.100
|
$6.450
|
$6.000
|
$5.290
|
$5.260
|
$3.550
|
|
|
INSTALL BRIDGE IDENTIFICATION NUMBERS
|
EA
|
2.000
|
$270.000
|
$400.000
|
$450.000
|
$168.280
|
$521.870
|
$200.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$11,000.000
|
$10,500.000
|
$9,700.000
|
$14,936.990
|
$20,000.000
|
$11,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
544.000
|
$280.000
|
$50.000
|
$70.000
|
$74.680
|
$250.000
|
$150.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
32.000
|
$81.000
|
$200.000
|
$50.000
|
$101.770
|
$70.000
|
$100.000
|
|
Totals: |
$4,562,659.070
|
$4,254,249.675
|
$4,695,446.614
|
$5,240,204.631
|
$5,438,169.886
|
$5,604,928.407
|