PREPARING ROW
|
STA
|
9.000
|
$20,000.000
|
$2,971.000
|
$20,000.000
|
$6,000.000
|
$10,000.000
|
|
|
REMOVING STAB BASE AND ASPH PAV(8")
|
SY
|
1,721.000
|
$3.750
|
$8.300
|
$13.000
|
$20.000
|
$27.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
755.000
|
$13.000
|
$11.250
|
$25.000
|
$30.000
|
$70.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
1,162.000
|
$15.000
|
$30.600
|
$32.000
|
$30.000
|
$70.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
715.000
|
$20.000
|
$7.000
|
$26.000
|
$30.000
|
$70.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
3,450.000
|
$1.350
|
$4.480
|
$3.900
|
$4.000
|
$1.500
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
3,450.000
|
$0.500
|
$0.820
|
$1.000
|
$1.000
|
$1.000
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
1,726.000
|
$0.400
|
$0.820
|
$1.200
|
$1.000
|
$1.000
|
|
|
CELL FBR MLCH SEED(TEMP)(COOL)
|
SY
|
1,726.000
|
$0.400
|
$0.820
|
$1.200
|
$1.000
|
$1.000
|
|
|
VEGETATIVE WATERING
|
MG
|
69.000
|
$13.600
|
$42.000
|
$20.000
|
$1.000
|
$125.000
|
|
|
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
|
SY
|
2,854.000
|
$15.000
|
$19.750
|
$29.000
|
$45.000
|
$35.000
|
|
|
CEMENT
|
TON
|
33.000
|
$225.000
|
$300.000
|
$275.000
|
$300.000
|
$300.000
|
|
|
CEMENT TREAT(EXIST MATL)(8")
|
SY
|
3,010.000
|
$2.500
|
$5.760
|
$6.000
|
$15.000
|
$10.000
|
|
|
ASPH (AC-10-2TR)
|
GAL
|
282.000
|
$6.500
|
$27.200
|
$17.000
|
$25.000
|
$45.000
|
|
|
ASPH (RC-250)
|
GAL
|
713.000
|
$6.000
|
$12.000
|
$13.500
|
$25.000
|
$23.000
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
6.000
|
$100.000
|
$1,050.000
|
$1,700.000
|
$2,500.000
|
$4,500.000
|
|
|
AGGR (TY-B GR-5 OR TY-L GR-5)
|
CY
|
21.000
|
$130.000
|
$361.000
|
$900.000
|
$800.000
|
$2,500.000
|
|
|
CEM STABIL BKFL
|
CY
|
193.000
|
$100.000
|
$106.000
|
$200.000
|
$250.000
|
$315.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,238.000
|
$25.000
|
$98.000
|
$70.000
|
$70.000
|
$41.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
124.000
|
$125.000
|
$106.000
|
$116.000
|
$215.000
|
$300.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
952.000
|
$260.000
|
$352.000
|
$310.000
|
$325.000
|
$500.000
|
|
|
CL C CONC (ABUT)
|
CY
|
63.800
|
$1,300.000
|
$1,150.000
|
$1,800.000
|
$2,200.000
|
$1,400.000
|
|
|
CL C CONC (CAP)
|
CY
|
40.200
|
$1,800.000
|
$1,400.000
|
$2,200.000
|
$2,500.000
|
$1,600.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
36.000
|
$1,800.000
|
$880.000
|
$1,400.000
|
$2,500.000
|
$1,600.000
|
|
|
REINF CONC SLAB
|
SF
|
5,980.000
|
$21.000
|
$36.000
|
$40.000
|
$50.000
|
$25.000
|
|
|
APPROACH SLAB
|
CY
|
66.000
|
$600.000
|
$1,048.000
|
$880.000
|
$1,000.000
|
$1,000.000
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
771.000
|
$200.000
|
$280.000
|
$247.000
|
$385.000
|
$300.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
44.000
|
$550.000
|
$545.000
|
$710.000
|
$700.000
|
$600.000
|
|
|
RAIL (TY T223)
|
LF
|
340.000
|
$170.000
|
$132.000
|
$180.000
|
$180.000
|
$185.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
92.000
|
$125.000
|
$239.000
|
$220.000
|
$200.000
|
$250.000
|
|
|
GABIONS (GALV)
|
CY
|
231.000
|
$320.000
|
$244.000
|
$550.000
|
$275.000
|
$600.000
|
|
|
GABION MATTRESSES (GALV)(12 IN)
|
SY
|
2,028.000
|
$110.000
|
$146.000
|
$120.000
|
$85.000
|
$80.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$100,000.000
|
$54,950.000
|
$60,000.000
|
$95,000.000
|
$115,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$201,119.230
|
$246,000.000
|
$280,000.000
|
$285,000.000
|
$361,740.110
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$7,500.000
|
$2,740.000
|
$6,000.000
|
$10,000.000
|
$10,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
45.000
|
$35.000
|
$54.950
|
$50.000
|
$1.000
|
$44.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
45.000
|
$10.000
|
$22.000
|
$10.000
|
$1.000
|
$10.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
444.000
|
$28.000
|
$38.000
|
$20.000
|
$1.000
|
$44.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
444.000
|
$7.000
|
$16.400
|
$8.000
|
$1.000
|
$9.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,238.000
|
$3.200
|
$5.220
|
$5.000
|
$1.000
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,238.000
|
$0.800
|
$1.000
|
$1.400
|
$1.000
|
$1.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
8.000
|
$5,000.000
|
$3,650.000
|
$4,000.000
|
$4,000.000
|
$8,600.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
630.000
|
$50.000
|
$18.450
|
$30.000
|
$80.000
|
$130.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
630.000
|
$12.000
|
$10.000
|
$6.000
|
$40.000
|
$15.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
630.000
|
$11.000
|
$18.450
|
$21.000
|
$40.000
|
$17.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
77.000
|
$50.000
|
$78.000
|
$90.000
|
$80.000
|
$240.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
412.500
|
$30.000
|
$27.470
|
$26.000
|
$25.000
|
$28.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,400.000
|
$2,214.000
|
$2,500.000
|
$1,800.000
|
$2,100.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
950.000
|
$3.000
|
$2.200
|
$2.000
|
$2.500
|
$6.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,300.000
|
$3,130.000
|
$3,000.000
|
$3,200.000
|
$3,500.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$280.000
|
$220.000
|
$200.000
|
$500.000
|
$500.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,400.000
|
$900.000
|
$1,000.000
|
$3,000.000
|
$2,000.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$930.000
|
$900.000
|
$500.000
|
$2,000.000
|
$900.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$9,300.000
|
$3,000.000
|
$10,000.000
|
$20,000.000
|
$10,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
2.000
|
$1,030.000
|
$1,065.000
|
$1,000.000
|
$1,200.000
|
$3,000.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
2.000
|
$110.000
|
$165.000
|
$125.000
|
$500.000
|
$300.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
4.000
|
$30.000
|
$38.400
|
$24.000
|
$30.000
|
$22.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
|
EA
|
8.000
|
$35.000
|
$36.000
|
$33.000
|
$30.000
|
$38.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
180.000
|
$5.000
|
$6.870
|
$6.500
|
$15.000
|
$17.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
3,618.000
|
$1.000
|
$1.000
|
$1.000
|
$2.000
|
$3.000
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
24.000
|
$10.000
|
$12.000
|
$11.000
|
$15.000
|
$17.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
7,200.000
|
$0.900
|
$1.000
|
$1.000
|
$2.000
|
$3.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
450.000
|
$1.000
|
$1.000
|
$2.000
|
$5.000
|
$2.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
7,880.000
|
$0.150
|
$0.250
|
$0.240
|
$1.000
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
2,000.000
|
$0.400
|
$1.000
|
$0.900
|
$2.000
|
$3.000
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
200.000
|
$0.400
|
$1.320
|
$1.200
|
$2.000
|
$3.000
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
9,000.000
|
$0.400
|
$1.000
|
$0.900
|
$2.000
|
$2.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
116.000
|
$3.850
|
$7.000
|
$6.000
|
$10.000
|
$10.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
9,733.000
|
$0.400
|
$1.000
|
$0.900
|
$1.500
|
$2.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
7,880.000
|
$0.050
|
$0.180
|
$0.170
|
$0.750
|
$1.000
|
|
|
SP MIXES SP-C SAC-A PG64-22
|
TON
|
318.000
|
$110.000
|
$137.600
|
$200.000
|
$275.000
|
$385.000
|
|
|
SP MIXES SP-C SAC-B PG64-22
|
TON
|
318.000
|
$115.000
|
$123.000
|
$200.000
|
$275.000
|
$381.000
|
|
|
BONDING COURSE
|
GAL
|
574.000
|
$5.000
|
$7.000
|
$6.000
|
$10.000
|
$23.000
|
|
|
INSTALL BRIDGE IDENTIFICATION NUMBERS
|
EA
|
2.000
|
$450.000
|
$800.000
|
$300.000
|
$1,000.000
|
$650.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$13,800.000
|
$10,000.000
|
$25,000.000
|
$56,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
4.000
|
$190.000
|
$570.000
|
$300.000
|
$200.000
|
$470.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
12.000
|
$280.000
|
$900.000
|
$300.000
|
$200.000
|
$1,000.000
|
|
Totals: |
$2,207,236.480
|
$2,461,069.875
|
$2,851,073.600
|
$3,243,873.000
|
$3,625,511.110
|