MONTAGUE HOWARD RD (0903-28-073)
Items: 53
County: MONTAGUE
Length: 0.0000 MILES (0.1078 MILES)
Highway: HOWARD RD
District: WICHITA FALLS
Control Number: 0903-28-073
DBE Goal: 0.0%
Project: BR 2025(998)
Guaranty: $63,000.00
Time: 199 WORKING DAYS
Engineer's Estimate: $3,059,363.99
Date: 09/02/2026 1:00 PM CDT (17 days ago)
Contract Number: 9263025
Type: BRIDGE REPLACEMENT
Project ID: A00207438
Contract Type: FEDERAL
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
AARON BLOOM
MADISON HAVERKAMP
MONTAGUE HOWARD RD (0903-28-073)
Project Name: N/A
Project: BR 2025(998)
Engineer's Estimate: $1,165,961.87
Length: 0.0000 MILES (0.1078 MILES)
Project Class: BRIDGE REPLACEMENT
Limits From: CR 194 (SIGNED HOWARD RD)
Limits To: AT NORTH FORK VILLAGE CREEK
Project Description: REPLACE BRIDGE AND APPROACHES
MONTAGUE OLD BONITA RD (0903-28-074)
Project Name: CR 265/ OLD BONITA AT BRANCH FARMERS CR
Project: BR 2026(157)
Engineer's Estimate: $622,928.32
Length: N/A
Project Class: BRIDGE REPLACEMENT
Limits From: CR 265 (SIGNED OLD BONITA RD)
Limits To: AT BRANCH FARMERS CREEK
Project Description: REPLACE BRIDGE AND APPROACHES
MONTAGUE ROCK SPRINGS SCHOOL RD (0903-28-075)
Project Name: CR 272/RCK SPGS SCHOOL RD AT BARREL SPGS
Project: BR 2026(185)
Engineer's Estimate: $564,073.42
Length: N/A
Project Class: BRIDGE REPLACEMENT
Limits From: CR 272 (SIGNED ROCK SPRINGS SCHOOL RD)
Limits To: AT BARREL SPRINGS CREEK
Project Description: REPLACE BRIDGE AND APPROACHES
MONTAGUE COUNTY ROAD 207 (0903-28-076)
Project Name: CR 363/JORDAN RD AT BRUSHY CR
Project: BR 2026(186)
Engineer's Estimate: $706,400.38
Length: N/A
Project Class: BRIDGE REPLACEMENT
Limits From: CR 363/JORDAN RD
Limits To: AT BRUSHY CR
Project Description: REPLACE BRIDGE AND APPROACHES
Bidders (6)
E
Engineer's Estimate
$3,059,363.99
$2,804,230.39
Over/Under Est:
-8.34%
-$255,133.60
$2,845,260.00
Over/Under Est:
-7%
-$214,103.99
Amt Left:
1.46%
$41,029.61
$3,179,305.73
Over/Under Est:
3.92%
$119,941.74
Amt Left:
13.38%
$375,075.34
Delta:
-11.74%
-$334,045.73
$3,510,333.92
Over/Under Est:
14.74%
$450,969.93
Amt Left:
25.18%
$706,103.53
Delta:
-10.41%
-$331,028.19
$4,158,432.70
Over/Under Est:
35.92%
$1,099,068.71
Amt Left:
48.29%
$1,354,202.31
Delta:
-18.46%
-$648,098.78
$4,529,736.50
Over/Under Est:
48.06%
$1,470,372.51
Amt Left:
61.53%
$1,725,506.11
Delta:
-8.93%
-$371,303.80
Bid Items & Bid Tabulations
53
Total
0 of 53
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $2,000.00 |