MORRIS SH 11 (0222-03-065)

Items: 96

County: MORRIS
Length: 4.4960 MILES (4.1434 MILES)
Highway: SH 11
District: ATLANTA
Control Number: 0222-03-065
DBE Goal: 0.0%
Project: F 2026(874)
Guaranty: $100,000.00
Time: 227 WORKING DAYS
Engineer's Estimate: $11,759,396.31
Date: 08/05/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263011
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00196231
Contract Type: FEDERAL
Project Description: REHABILITATE EXISTING 4-LANE HIGHWAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$11,759,396.31
$10,759,104.58
Over/Under Est: -8.51% -$1,000,291.73
Over/Under Est: -1.26% -$148,016.60
Amt Left: 7.92% $852,275.13
$11,645,262.34
Over/Under Est: -0.97% -$114,133.97
Amt Left: 8.24% $886,157.76
Delta: -0.29% -$33,882.63
$12,165,388.34
Over/Under Est: 3.45% $405,992.03
Amt Left: 13.07% $1,406,283.76
Delta: -4.47% -$520,126.00
$12,349,863.86
Over/Under Est: 5.02% $590,467.55
Amt Left: 14.79% $1,590,759.28
Delta: -1.52% -$184,475.52
Over/Under Est: 9.24% $1,086,801.63
Amt Left: 19.4% $2,087,093.36
Delta: -4.02% -$496,334.08
$13,998,023.70
Over/Under Est: 19.04% $2,238,627.39
Amt Left: 30.1% $3,238,919.12
Delta: -8.97% -$1,151,825.76

Bid Items & Bid Tabulations

96 Total 0 of 96
MORRIS  |  SH 11  |  ATLANTA  |  0222-03-065  |  08/05/2026 1:00 PM CDT  |  $11,759,396.31  |  F 2026(874)  |  REHAB EXIST ROADWAY  |  227 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
H. H. HOWARD & SONS, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
EAST TEXAS BRIDGE, INC.
H. V. CAVER, INC.
RK HALL, LLC
L. S. EQUIPMENT CO., INC.
DRAKE COMPANIES LLC
PREPARING ROW
STA 159.900 $1,000.000 $2,500.000 $7,000.000 $4,400.000 $4,000.000 $4,055.100 $4,000.000 $5,500.000
REMOV CONC (MOWSTRIP)
SY 2,949.000 $11.800 $10.000 $7.000 $10.000 $19.500 $19.340 $10.000 $7.000
REMOV CONC (RIPRAP)
SY 14.000 $25.000 $40.000 $56.000 $20.000 $50.000 $73.410 $125.000 $75.000
REMOV CONC (MEDIANS)
SY 3,933.000 $46.200 $15.000 $8.000 $12.000 $20.000 $12.340 $85.000 $6.000
REMOV CONC (DRIVEWAYS)
SY 226.000 $16.000 $15.000 $30.000 $15.000 $20.000 $15.750 $25.000 $16.000
REMOV CONC (CURB)
LF 4,698.000 $9.500 $5.000 $4.500 $6.000 $5.750 $7.880 $10.000 $9.000
EMBANK (VEH)(OC)(TY A)
CY 658.000 $16.000 $20.000 $40.000 $16.000 $50.000 $63.000 $30.000 $25.000
BACKFILL (TY B)
STA 364.000 $210.000 $200.000 $150.000 $200.000 $250.000 $130.080 $200.000 $265.000
BLADING
LF 975.000 $47.000 $10.000 $1.000 $3.000 $2.500 $315.000 $25.000 $15.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 28,422.000 $0.630 $0.500 $0.570 $0.530 $0.500 $0.500 $0.500 $0.530
BOND FBR MTRX SEED (TEMP)(WARM)
SY 14,211.000 $0.640 $0.500 $0.560 $0.500 $0.470 $0.470 $0.490 $0.500
BOND FBR MTRX SEED (TEMP)(COOL)
SY 14,211.000 $0.640 $0.500 $0.560 $0.500 $0.470 $0.470 $0.490 $0.500
VEGETATIVE WATERING
TGL 2,724.000 $8.810 $1.000 $15.000 $4.000 $0.010 $39.680 $0.010 $9.000
FL BS (RDWY DEL) (TY D GR 4) (IN VEH)
CY 1,573.000 $6.000 $80.000 $94.000 $115.000 $60.000 $63.000 $155.000 $99.000
CEMENT
TON 2,426.000 $227.000 $230.000 $256.000 $245.000 $220.000 $262.500 $300.000 $270.000
CEMENT TRT (EXIST MATL & NEW BASE)(10")
SY 118,332.000 $5.000 $3.000 $2.000 $2.300 $5.500 $7.040 $4.000 $3.750
PRIME COAT & BLOTTER (MC-30)
GAL 11,833.000 $8.000 $6.000 $6.800 $5.500 $7.700 $8.140 $8.000 $5.250
ASPH (AC-20-5TR)
GAL 42,600.000 $3.250 $6.000 $6.500 $4.500 $6.600 $6.560 $6.000 $4.750
AGGR (TY-PB, GR-4)(SAC-A)
CY 845.000 $64.400 $200.000 $248.000 $205.000 $187.090 $115.500 $190.000 $215.000
SP MIXES SP-C PG70-22
TON 19,525.000 $140.000 $125.680 $134.000 $135.000 $127.000 $128.260 $128.820 $157.000
SP MIXES SP-C SAC-A PG76-22
TON 27,088.000 $145.000 $126.880 $136.000 $137.000 $129.000 $129.480 $129.420 $159.000
TACK COAT
GAL 24,111.000 $4.100 $6.000 $4.000 $4.750 $6.100 $4.740 $7.000 $5.250
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 4,000.000 $29.080 $40.000 $38.000 $45.000 $38.330 $38.030 $50.000 $53.000
PLANE ASPH CONC PAV(0" TO 3")
SY 5,266.000 $3.880 $5.000 $2.000 $6.850 $4.250 $6.230 $6.500 $7.000
PLANE ASPH CONC PAV(2")
SY 114,400.000 $2.600 $2.700 $1.750 $2.650 $1.600 $2.730 $4.000 $5.500
PLANE ASPH CONC PAV (0.5")
SY 73,468.000 $2.000 $1.500 $1.350 $1.670 $1.200 $1.820 $3.250 $4.750
RIPRAP (MOW STRIP)(4 IN)
CY 336.000 $400.000 $615.000 $514.000 $595.000 $500.000 $735.000 $660.000 $610.000
CLEANING AND SEALING EXISTING JOINTS
LF 400.000 $50.000 $60.000 $45.000 $45.000 $38.000 $47.250 $75.000 $49.500
CLEANING EXISTING JOINTS
LF 100.000 $40.000 $55.000 $37.000 $37.000 $25.000 $50.400 $75.000 $49.500
RC PIPE (CL III)(18 IN)
LF 192.000 $52.940 $85.000 $82.000 $57.000 $48.000 $68.250 $55.000 $60.000
RC PIPE (CL III)(24 IN)
LF 52.000 $62.660 $200.000 $109.000 $77.000 $81.000 $94.500 $80.000 $110.000
RC PIPE (CL III)(36 IN)
LF 4.000 $164.480 $250.000 $220.000 $150.000 $130.000 $204.750 $125.000 $300.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 21.000 $728.050 $850.000 $1,000.000 $875.000 $795.000 $892.500 $950.000 $1,125.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 6.000 $1,953.570 $1,000.000 $1,450.000 $1,325.000 $1,225.000 $1,575.000 $1,200.000 $1,600.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 1.000 $6,573.180 $10,000.000 $5,700.000 $6,000.000 $6,446.250 $7,875.000 $7,500.000 $5,920.000
ADJUSTING INLETS
EA 4.000 $1,761.000 $3,000.000 $1,980.000 $2,000.000 $7,500.000 $2,100.000 $1,000.000 $1,500.000
REMOV STR (SET)
EA 1.000 $203.000 $100.000 $900.000 $400.000 $500.000 $210.000 $400.000 $475.000
REMOV STR (PIPE)
LF 124.000 $17.060 $10.000 $22.000 $12.000 $20.000 $10.500 $20.000 $13.000
MOBILIZATION
LS 1.000 $1,069,000.000 $400,000.000 $550,000.000 $670,000.000 $1,200,000.000 $493,994.550 $1,000,000.000 $1,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $5,000.000 $10,000.000 $3,000.000 $11,000.000 $11,000.000 $22,158.750 $13,500.000 $6,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $6,000.000 $15,000.000 $6,600.000 $14,000.000 $13,000.000 $5,334.540 $10,000.000 $19,250.000
TMA (STATIONARY)
DAY 227.000 $85.000 $100.000 $200.000 $200.000 $200.000 $432.550 $250.000 $198.000
TMA (MOBILE OPERATION)
DAY 8.000 $255.000 $500.000 $300.000 $200.000 $250.000 $796.850 $250.000 $300.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 100.000 $44.840 $40.000 $64.000 $37.000 $35.000 $35.700 $37.000 $38.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $5.080 $10.000 $22.000 $7.000 $8.000 $7.350 $7.000 $8.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,600.000 $3.670 $5.000 $4.400 $4.000 $3.600 $3.680 $3.650 $3.850
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,600.000 $0.970 $1.000 $1.100 $0.500 $0.600 $0.530 $0.500 $0.550
CONC CURB & GUTTER (TY II)
LF 140.000 $38.000 $70.000 $49.000 $38.000 $23.000 $42.000 $110.000 $58.000
DRIVEWAYS (CONC)
SY 226.000 $110.000 $100.000 $155.000 $110.000 $141.000 $105.000 $125.000 $105.000
DRIVEWAYS (ACP)
SY 3,895.000 $45.000 $60.000 $45.000 $35.000 $100.000 $42.670 $50.000 $35.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 45,066.000 $0.340 $0.300 $0.300 $0.280 $0.250 $0.260 $0.320 $0.280
MTL W-BEAM GD FEN (TIM POST)
LF 6,225.000 $30.000 $22.000 $24.200 $23.500 $22.000 $23.100 $25.000 $24.000
MTL W-BEAM GD FEN (STEEL POST)
LF 75.000 $32.000 $91.000 $91.000 $90.000 $83.000 $87.150 $90.000 $99.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $1,180.500 $1,330.000 $1,350.000 $1,325.000 $1,230.000 $1,291.500 $1,500.000 $1,460.000
MTL THRIE-BEAM GD FEN (TIM POST)
EA 12.000 $1,403.000 $1,650.000 $1,760.000 $1,800.000 $1,600.000 $1,575.000 $1,800.000 $1,790.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 12.000 $831.000 $585.000 $715.000 $700.000 $650.000 $682.500 $750.000 $635.000
REMOVE METAL BEAM GUARD FENCE
LF 6,175.000 $2.960 $3.000 $1.650 $1.650 $1.500 $1.580 $3.000 $2.200
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 10.000 $158.500 $160.000 $165.000 $165.000 $150.000 $157.500 $175.000 $165.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 10.000 $234.940 $155.000 $165.000 $165.000 $750.000 $733.760 $175.000 $165.000
GUARDRAIL END TREATMENT (INSTALL)
EA 28.000 $3,800.000 $3,200.000 $3,325.000 $3,250.000 $3,020.000 $3,171.000 $3,250.000 $3,410.000
GUARDRAIL END TREATMENT (REMOVE)
EA 18.000 $148.600 $220.000 $165.000 $165.000 $150.000 $157.500 $175.000 $220.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 17.000 $275.000 $340.000 $220.000 $215.000 $220.000 $231.000 $245.000 $365.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 2.000 $293.330 $400.000 $245.000 $240.000 $240.000 $252.000 $280.000 $405.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $1,075.000 $800.000 $750.000 $730.000 $750.000 $787.500 $805.000 $810.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 12.000 $851.820 $875.000 $800.000 $780.000 $800.000 $840.000 $875.000 $935.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $1,047.220 $1,300.000 $1,100.000 $1,100.000 $990.000 $1,039.500 $1,050.000 $1,350.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 20.000 $777.830 $1,100.000 $1,320.000 $1,300.000 $990.000 $1,039.500 $1,050.000 $1,200.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 65.000 $427.140 $550.000 $475.000 $465.000 $450.000 $472.500 $475.000 $530.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 13.000 $542.750 $550.000 $540.000 $525.000 $500.000 $525.000 $525.000 $550.000
REMOVE SM RD SN SUP&AM
EA 99.000 $110.000 $150.000 $110.000 $110.000 $100.000 $105.000 $105.000 $115.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 91.000 $14.600 $45.000 $43.000 $45.000 $39.000 $40.950 $45.000 $44.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 103.000 $31.300 $45.000 $44.000 $45.000 $40.000 $42.000 $45.000 $44.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 103.000 $18.370 $15.000 $16.500 $16.500 $10.000 $10.500 $12.000 $42.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 11,850.000 $0.300 $0.270 $0.390 $0.270 $0.350 $0.260 $0.400 $0.280
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 47,306.000 $0.320 $0.270 $0.280 $0.270 $0.250 $0.260 $0.320 $0.280
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 11,850.000 $0.360 $0.270 $0.380 $0.270 $0.350 $0.260 $0.400 $0.280
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 47,306.000 $0.310 $0.270 $0.280 $0.270 $0.250 $0.260 $0.320 $0.280
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 11,850.000 $1.190 $1.250 $1.500 $2.250 $3.000 $2.310 $1.500 $1.300
WK ZN PAV MRK REMOV (Y)6"(BRK)
LF 11,850.000 $0.550 $1.250 $1.500 $2.250 $3.000 $2.240 $1.500 $1.300
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,183.000 $1.500 $5.000 $1.500 $1.500 $1.000 $1.770 $2.000 $1.300
WK ZN PAV MRK SHT TERM RMV (Y)(6")
LF 2,365.000 $1.500 $1.000 $1.500 $1.500 $3.000 $2.240 $5.000 $1.300
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 316.000 $6.330 $7.550 $5.800 $8.000 $5.250 $7.880 $5.750 $8.250
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 48,184.000 $1.000 $1.050 $0.630 $1.100 $0.570 $1.050 $0.650 $1.100
ALL-WTHER PM TY I (W)6"(BRK)(100MIL)
LF 12,610.000 $0.800 $1.050 $0.700 $1.100 $0.630 $1.050 $0.700 $1.100
ALL-WTHER PM TY I (W)6"(DOT)(100MIL)
LF 1,340.000 $1.000 $2.500 $0.700 $2.150 $0.650 $2.100 $0.700 $2.200
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 48,184.000 $1.490 $1.100 $0.630 $1.100 $0.570 $1.050 $0.650 $1.100
ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)
LF 5,390.000 $1.060 $1.100 $0.700 $1.100 $0.630 $1.050 $0.700 $1.100
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 13,416.000 $3.000 $3.700 $3.500 $3.850 $3.200 $3.780 $3.500 $4.000
PREFAB PM TY C (W)(ARROW)
EA 26.000 $215.000 $225.000 $230.000 $230.000 $210.000 $225.750 $240.000 $235.000
PREFAB PM TY C (W)(WORD)
EA 12.000 $245.000 $255.000 $270.000 $265.000 $245.000 $257.250 $275.000 $270.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 153.000 $48.560 $60.000 $55.000 $60.000 $50.000 $57.750 $55.000 $60.000
REFL PAV MRKR TY I-C
EA 266.000 $5.000 $6.000 $5.800 $5.350 $5.250 $5.250 $5.750 $5.500
REFL PAV MRKR TY II-A-A
EA 422.000 $5.100 $6.000 $5.800 $5.350 $5.250 $5.250 $5.750 $5.500
REFL PAV MRKR TY II-C-R
EA 352.000 $5.000 $6.000 $5.800 $5.350 $5.250 $5.250 $5.750 $5.500
TRAFFIC BUTTON TY Y
EA 26.000 $5.000 $5.000 $4.350 $4.300 $3.950 $4.200 $4.050 $4.500
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 8.000 $500.000 $500.000 $330.000 $235.000 $1,800.000 $525.000 $1,200.000 $200.000
Totals: $11,759,396.310 $10,759,104.580 $11,611,379.710 $11,645,262.340 $12,165,388.340 $12,349,863.860 $12,846,197.940 $13,998,023.700
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $104,782.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $20,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $52,390.00
Total: $177,172.00