PREPARING ROW
|
STA
|
10.900
|
$7,000.000
|
$3,285.000
|
$40,000.000
|
$9,500.000
|
$46,000.000
|
$750.000
|
|
|
REMOV CONC (RIPRAP)
|
SY
|
324.000
|
$30.000
|
$24.640
|
$25.690
|
$31.500
|
$17.600
|
$55.000
|
|
|
RMV (14"-18") TRT/UNTRT BASE & ASPH PAV
|
SY
|
4,456.000
|
$20.000
|
$6.790
|
$19.850
|
$21.000
|
$16.000
|
$20.000
|
|
|
EXCAV (ROADWAY)
|
CY
|
3,877.660
|
$29.000
|
$39.600
|
$10.510
|
$10.000
|
$33.100
|
$36.000
|
|
|
EMBANK (FNL)(DC)(TY C1)
|
CY
|
4,334.930
|
$25.000
|
$17.520
|
$19.850
|
$25.000
|
$28.000
|
$60.000
|
|
|
EMBANK (FNL)(DC)(TY C2)
|
CY
|
405.880
|
$50.000
|
$59.240
|
$31.520
|
$35.000
|
$60.300
|
$65.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
4,880.000
|
$5.000
|
$1.260
|
$3.270
|
$1.250
|
$7.200
|
$6.000
|
|
|
DRILL SEED (PERM_URBAN_CLAY)
|
SY
|
4,880.000
|
$1.500
|
$0.550
|
$0.410
|
$0.750
|
$0.500
|
$0.500
|
|
|
DRILL SEED (TEMP_WARM_COOL)
|
SY
|
4,880.000
|
$1.500
|
$0.480
|
$0.880
|
$0.500
|
$0.440
|
$0.500
|
|
|
VEGETATIVE WATERING
|
TGL
|
726.000
|
$20.000
|
$60.230
|
$17.510
|
$3.000
|
$66.000
|
$33.000
|
|
|
FL BS (CMP IN PLC)(TY D GR 1-2) (10")
|
SY
|
4,652.900
|
$40.000
|
$35.040
|
$38.490
|
$33.000
|
$30.500
|
$30.000
|
|
|
LIME (COM OR QK)(SLURRY)
|
TON
|
53.600
|
$400.000
|
$365.730
|
$389.970
|
$400.000
|
$339.000
|
$370.000
|
|
|
LIME TRT (EXIST MATL)(6")
|
SY
|
4,765.900
|
$10.000
|
$11.100
|
$4.090
|
$8.000
|
$8.900
|
$16.000
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
892.800
|
$11.000
|
$10.290
|
$11.990
|
$10.000
|
$9.400
|
$9.500
|
|
|
TACK COAT
|
GAL
|
260.000
|
$5.000
|
$2.190
|
$18.040
|
$2.000
|
$2.000
|
$12.000
|
|
|
SP MIXES SP-B PG64-22
|
TON
|
1,435.600
|
$170.000
|
$170.380
|
$234.260
|
$175.000
|
$155.600
|
$155.000
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
491.000
|
$170.000
|
$230.280
|
$279.430
|
$230.000
|
$210.300
|
$202.000
|
|
|
CEM STABIL BKFL
|
CY
|
337.200
|
$250.000
|
$229.950
|
$105.080
|
$275.000
|
$168.000
|
$220.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
376.000
|
$300.000
|
$109.500
|
$211.170
|
$150.000
|
$120.000
|
$350.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
504.000
|
$325.000
|
$224.480
|
$344.980
|
$275.000
|
$236.000
|
$380.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
24.400
|
$1,500.000
|
$1,587.750
|
$1,416.250
|
$2,000.000
|
$1,370.000
|
$4,000.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
29.700
|
$1,700.000
|
$1,724.630
|
$1,778.190
|
$2,250.000
|
$1,990.000
|
$4,000.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
20.000
|
$1,600.000
|
$1,724.630
|
$1,778.190
|
$2,500.000
|
$2,010.000
|
$3,500.000
|
|
|
REINF CONC SLAB (SLAB BEAM)(HPC)
|
SF
|
8,025.000
|
$30.000
|
$26.430
|
$28.070
|
$25.000
|
$21.000
|
$45.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
61.200
|
$820.000
|
$930.750
|
$1,004.000
|
$900.000
|
$705.000
|
$1,200.000
|
|
|
RETAINING WALL (SPREAD FOOTING)
|
SF
|
2,784.000
|
$100.000
|
$109.500
|
$76.820
|
$110.000
|
$87.000
|
$300.000
|
|
|
PRESTR CONC SLAB BEAM (5SB15)
|
LF
|
1,584.000
|
$300.000
|
$198.200
|
$218.630
|
$250.000
|
$226.000
|
$240.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
31.200
|
$750.000
|
$711.750
|
$764.750
|
$800.000
|
$833.000
|
$990.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
1,377.000
|
$210.000
|
$312.080
|
$117.090
|
$250.000
|
$252.000
|
$125.000
|
|
|
RAIL (TY SSTR)
|
LF
|
458.000
|
$90.000
|
$130.160
|
$92.240
|
$100.000
|
$79.000
|
$140.000
|
|
|
RAIL (TY SSTR)(HPC)
|
LF
|
412.000
|
$80.000
|
$105.550
|
$145.950
|
$120.000
|
$78.000
|
$165.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
116.700
|
$200.000
|
$291.270
|
$216.000
|
$210.000
|
$228.000
|
$330.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
910.000
|
$100.000
|
$116.630
|
$44.320
|
$60.000
|
$64.500
|
$85.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
626.000
|
$135.000
|
$170.210
|
$63.690
|
$95.000
|
$77.000
|
$120.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$1,500.000
|
$821.250
|
$762.810
|
$750.000
|
$1,188.000
|
$800.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
2.000
|
$2,000.000
|
$2,080.500
|
$1,181.180
|
$2,000.000
|
$1,513.000
|
$1,100.000
|
|
|
REMOV STR (SET)
|
EA
|
4.000
|
$600.000
|
$328.500
|
$389.190
|
$800.000
|
$622.000
|
$1,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,010.000
|
$35.000
|
$21.900
|
$7.780
|
$35.000
|
$18.700
|
$10.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$75,000.000
|
$44,114.270
|
$76,226.490
|
$75,000.000
|
$550,000.000
|
$48,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$400,000.000
|
$400,000.000
|
$450,000.000
|
$450,000.000
|
$550,000.000
|
$400,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$12,000.000
|
$2,269.300
|
$5,254.020
|
$15,000.000
|
$78,000.000
|
$12,000.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$14,000.000
|
$10,731.000
|
$8,172.920
|
$8,000.000
|
$12,260.000
|
$16,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
20.000
|
$250.000
|
$384.880
|
$875.670
|
$250.000
|
$346.000
|
$260.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
60.000
|
$70.000
|
$106.090
|
$107.270
|
$100.000
|
$81.000
|
$80.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
210.000
|
$45.000
|
$36.140
|
$58.380
|
$52.680
|
$49.000
|
$48.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
40.000
|
$60.000
|
$71.180
|
$116.760
|
$69.880
|
$105.000
|
$100.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
250.000
|
$15.000
|
$16.430
|
$23.350
|
$25.160
|
$25.000
|
$21.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
340.000
|
$30.000
|
$38.330
|
$75.890
|
$37.630
|
$35.000
|
$40.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
340.000
|
$10.000
|
$16.430
|
$35.030
|
$16.130
|
$15.000
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,605.000
|
$5.000
|
$3.560
|
$5.840
|
$3.490
|
$3.250
|
$3.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,605.000
|
$1.500
|
$1.310
|
$2.340
|
$1.290
|
$1.200
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
40.000
|
$10.000
|
$7.670
|
$35.030
|
$7.530
|
$7.000
|
$15.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
40.000
|
$3.000
|
$2.190
|
$11.680
|
$2.150
|
$2.000
|
$1.200
|
|
|
CONSTRUCTING DETOURS
|
SY
|
1,855.000
|
$150.000
|
$159.210
|
$210.160
|
$262.000
|
$163.000
|
$250.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
1,635.000
|
$60.000
|
$82.130
|
$82.700
|
$25.000
|
$26.000
|
$80.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
1,350.000
|
$13.000
|
$28.470
|
$12.650
|
$10.000
|
$10.000
|
$20.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
1,635.000
|
$15.000
|
$21.900
|
$12.650
|
$12.500
|
$14.500
|
$20.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
145.700
|
$80.000
|
$87.600
|
$134.270
|
$110.000
|
$69.800
|
$200.000
|
|
|
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
|
LF
|
758.000
|
$1.000
|
$11.210
|
$11.960
|
$11.000
|
$3.320
|
$13.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
287.500
|
$30.000
|
$26.830
|
$26.270
|
$24.190
|
$22.500
|
$30.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
2.000
|
$2,400.000
|
$1,914.060
|
$2,101.610
|
$2,863.780
|
$2,426.000
|
$2,100.000
|
|
|
SHORT RADIUS (28")
|
LF
|
59.000
|
$80.000
|
$382.700
|
$27.440
|
$25.260
|
$23.500
|
$400.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,600.000
|
$1,500.150
|
$1,401.070
|
$1,290.000
|
$1,200.000
|
$1,800.000
|
|
|
MTL BM GD FEN TRANS (NON - SYM)
|
EA
|
2.000
|
$725.000
|
$672.330
|
$700.540
|
$645.000
|
$600.000
|
$1,200.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
201.000
|
$7.500
|
$6.570
|
$3.210
|
$2.960
|
$2.750
|
$12.000
|
|
|
CABLE BARRIER SYSTEM (INSTALL)(TL-3)
|
LF
|
1,510.000
|
$30.000
|
$50.460
|
$40.860
|
$49.540
|
$50.000
|
$25.000
|
|
|
CABLE BARRIER TERM SEC (INSTL)(TL-3)
|
EA
|
2.000
|
$1,550.000
|
$2,441.850
|
$6,421.580
|
$2,397.250
|
$3,500.000
|
$1,800.000
|
|
|
CABLE BARRIER (REMOVE)
|
LF
|
1,510.000
|
$6.000
|
$19.960
|
$5.840
|
$19.600
|
$9.400
|
$6.000
|
|
|
CABLE BARRIER TERMINAL SECTION (REMOVE)
|
EA
|
2.000
|
$600.000
|
$1,314.000
|
$875.670
|
$1,290.000
|
$1,000.000
|
$600.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$3,300.000
|
$3,461.300
|
$3,359.650
|
$3,093.320
|
$2,877.500
|
$3,300.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$450.000
|
$328.500
|
$291.890
|
$268.750
|
$250.000
|
$320.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
4.000
|
$2,200.000
|
$3,504.000
|
$1,167.560
|
$1,500.000
|
$1,000.000
|
$1,200.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
5.000
|
$1,500.000
|
$2,737.500
|
$992.430
|
$1,000.000
|
$850.000
|
$1,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
5.000
|
$11,500.000
|
$10,840.500
|
$10,185.790
|
$10,000.000
|
$6,974.000
|
$10,000.000
|
|
|
PIPE UNDERDRAINS (TY 8) (6")
|
LF
|
462.000
|
$50.000
|
$60.900
|
$23.350
|
$36.750
|
$64.000
|
$80.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
|
EA
|
3.000
|
$70.000
|
$24.090
|
$23.350
|
$21.500
|
$20.000
|
$50.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB
|
EA
|
3.000
|
$70.000
|
$24.090
|
$29.190
|
$21.500
|
$20.000
|
$50.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
3.000
|
$100.000
|
$29.570
|
$379.460
|
$26.880
|
$25.000
|
$50.000
|
|
|
INSTL OM ASSM (OM-3L)(TWT)GND
|
EA
|
1.000
|
$300.000
|
$240.900
|
$379.460
|
$349.380
|
$325.000
|
$140.000
|
|
|
INSTL OM ASSM (OM-3R)(TWT)GND
|
EA
|
1.000
|
$300.000
|
$240.900
|
$350.270
|
$349.380
|
$325.000
|
$140.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
2,483.000
|
$2.000
|
$4.380
|
$1.480
|
$3.230
|
$0.930
|
$1.100
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
14.000
|
$20.000
|
$27.380
|
$8.890
|
$14.190
|
$7.000
|
$8.000
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
1,925.000
|
$2.500
|
$4.380
|
$1.480
|
$3.230
|
$0.930
|
$1.100
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
64.000
|
$1.500
|
$5.380
|
$2.040
|
$5.380
|
$3.000
|
$3.500
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
15.000
|
$12.000
|
$10.950
|
$12.240
|
$26.880
|
$7.000
|
$8.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
2.000
|
$185.000
|
$273.750
|
$220.380
|
$537.500
|
$185.000
|
$210.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
2.000
|
$215.000
|
$383.250
|
$254.740
|
$752.500
|
$200.000
|
$230.000
|
|
|
PAVEMENT SLER 6"
|
LF
|
2,591.000
|
$0.500
|
$1.100
|
$0.670
|
$2.150
|
$1.800
|
$2.000
|
|
|
PAVEMENT SLER 8"
|
LF
|
64.000
|
$1.000
|
$1.640
|
$0.960
|
$4.300
|
$1.900
|
$2.000
|
|
|
PAVEMENT SLER 24"
|
LF
|
15.000
|
$3.000
|
$3.290
|
$4.920
|
$21.500
|
$2.750
|
$3.000
|
|
|
PAVEMENT SLER (ARROW)
|
EA
|
2.000
|
$50.000
|
$164.250
|
$64.720
|
$215.000
|
$90.000
|
$100.000
|
|
|
PAVEMENT SLER (WORD)
|
EA
|
2.000
|
$50.000
|
$219.000
|
$64.470
|
$322.500
|
$98.000
|
$110.000
|
|
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
|
LF
|
270.000
|
$1.500
|
$2.190
|
$5.840
|
$5.380
|
$2.000
|
$2.300
|
|
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
|
LF
|
1,090.000
|
$1.500
|
$2.190
|
$2.290
|
$5.380
|
$2.000
|
$2.300
|
|
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
|
LF
|
1,231.000
|
$1.500
|
$2.190
|
$2.210
|
$5.380
|
$2.000
|
$2.300
|
|
|
MOBILE RETROREFLECTIVITY DATA COLLECT
|
MI
|
1,960.000
|
$1.000
|
$1.200
|
$2.340
|
$1.000
|
$1.000
|
$19.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
20.000
|
$7.000
|
$27.380
|
$10.440
|
$12.900
|
$9.000
|
$10.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
2,591.000
|
$0.500
|
$1.100
|
$0.500
|
$1.080
|
$0.520
|
$0.600
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
64.000
|
$0.500
|
$1.640
|
$2.320
|
$1.610
|
$0.630
|
$0.700
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
15.000
|
$2.500
|
$3.290
|
$3.220
|
$3.230
|
$1.000
|
$1.200
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
2.000
|
$40.000
|
$82.130
|
$42.090
|
$107.500
|
$55.000
|
$65.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
2.000
|
$40.000
|
$109.500
|
$48.200
|
$161.250
|
$75.000
|
$85.000
|
|
|
PAV SURF PREP FOR MRK (RPM)
|
EA
|
20.000
|
$7.000
|
$5.480
|
$1.620
|
$2.150
|
$2.000
|
$2.300
|
|
|
FULL - WIDTH MOWING
|
CYC
|
2.000
|
$4,500.000
|
$4,380.000
|
$5,837.800
|
$3,150.000
|
$2,500.000
|
$2,000.000
|
|
Totals: |
$4,506,815.690
|
$4,442,318.950
|
$4,571,198.270
|
$4,585,356.195
|
$5,589,711.790
|
$5,621,448.760
|