EMBANKMENT (FINAL)(ORD COMP)(TY A)
|
CY
|
87.000
|
$25.000
|
$30.000
|
$100.000
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
51,867.000
|
$3.000
|
$4.300
|
$3.300
|
|
|
AGGR (MULTI OPTION)
|
CY
|
1,347.000
|
$25.000
|
$220.000
|
$118.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
|
SY
|
28,445.000
|
$26.000
|
$44.000
|
$48.000
|
|
|
PLANE ASPH CONC PAV (3")
|
SY
|
148,192.000
|
$1.500
|
$2.200
|
$3.600
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
48.000
|
$500.000
|
$580.000
|
$710.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
42.000
|
$520.000
|
$570.000
|
$632.000
|
|
|
ADJUSTING INLETS
|
EA
|
1.000
|
$4,500.000
|
$2,200.000
|
$2,770.000
|
|
|
ADJUSTING INLET (CAP)
|
EA
|
1.000
|
$2,500.000
|
$3,100.000
|
$2,770.000
|
|
|
REMOVE STR (RAIL)
|
LF
|
120.000
|
$500.000
|
$170.000
|
$134.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$544,171.000
|
$297,570.000
|
$392,500.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
4.000
|
$30,000.000
|
$42,000.000
|
$74,800.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
948.000
|
$4.000
|
$6.200
|
$6.100
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
948.000
|
$1.000
|
$3.800
|
$1.450
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
600.000
|
$30.000
|
$18.250
|
$21.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
600.000
|
$8.000
|
$15.750
|
$18.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
400.000
|
$25.000
|
$34.000
|
$28.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
3.000
|
$1,350.000
|
$2,200.000
|
$1,500.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
570.000
|
$5.000
|
$5.900
|
$2.200
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
3.000
|
$2,750.000
|
$4,100.000
|
$2,740.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
1.000
|
$1,000.000
|
$3,000.000
|
$831.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
1.000
|
$24,000.000
|
$34,100.000
|
$38,200.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
1.000
|
$8,000.000
|
$11,700.000
|
$8,310.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$650.000
|
$460.000
|
$554.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
13,480.000
|
$0.400
|
$0.300
|
$0.300
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
25,427.000
|
$0.350
|
$0.300
|
$0.300
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
13,959.000
|
$2.000
|
$0.700
|
$0.650
|
|
|
WK ZN PAV MRK NON-REMOV (W)12"(LNDP)
|
LF
|
1,623.000
|
$2.750
|
$2.300
|
$2.200
|
|
|
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
|
LF
|
1,200.000
|
$2.000
|
$2.100
|
$2.050
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
24,821.000
|
$0.350
|
$0.300
|
$0.300
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-C-R
|
EA
|
7,709.000
|
$4.500
|
$3.700
|
$3.600
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
5,474.000
|
$0.450
|
$2.300
|
$1.400
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
7,709.000
|
$0.700
|
$0.750
|
$0.750
|
|
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
|
LF
|
1,623.000
|
$3.000
|
$2.100
|
$2.050
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
1,200.000
|
$3.000
|
$2.100
|
$2.050
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
13,474.000
|
$0.320
|
$0.500
|
$0.500
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
25,427.000
|
$0.220
|
$0.500
|
$0.450
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
24,821.000
|
$0.220
|
$0.500
|
$0.450
|
|
PREFAB PAV MRK TY C (W) (12") (SLD)
|
LF
|
1,200.000
|
$5.000
|
$10.250
|
$10.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
14.000
|
$175.000
|
$230.000
|
$222.000
|
|
PREFAB PAV MRK TY C (W) (DBL ARROW)
|
EA
|
3.000
|
$400.000
|
$460.000
|
$443.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
14.000
|
$225.000
|
$260.000
|
$244.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
7,914.000
|
$2.800
|
$3.800
|
$3.600
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
3,478.000
|
$0.500
|
$1.200
|
$0.550
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
250.000
|
$2.000
|
$2.500
|
$1.650
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
3.000
|
$60.000
|
$250.000
|
$72.000
|
|
|
ELIM EXT PAV MRK & MRKS (DBL ARROW)
|
EA
|
1.000
|
$100.000
|
$360.000
|
$94.000
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
3.000
|
$45.000
|
$260.000
|
$83.000
|
|
|
DRAIN INLET CLEANING
|
EA
|
10.000
|
$185.000
|
$3,100.000
|
$837.000
|
|
|
RAISING AND UNDERSEALING CONCRETE SLAB
|
LB
|
3,750.000
|
$64.000
|
$10.000
|
$21.000
|
|
|
D-GR HMA TY-B SAC-B PG70-22
|
TON
|
20,376.000
|
$110.000
|
$130.000
|
$140.000
|
|
|
TACK COAT
|
GAL
|
11,411.000
|
$3.500
|
$3.700
|
$3.600
|
|
|
TBWC (MEMBRANE)
|
GAL
|
32,364.000
|
$3.500
|
$4.900
|
$3.600
|
|
|
TBWC PG76-22 SAC-A TY C
|
TON
|
8,091.000
|
$164.000
|
$200.000
|
$199.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
160.000
|
$65.000
|
$140.000
|
$71.000
|
|
|
TMA (STATIONARY)
|
DAY
|
212.000
|
$65.000
|
$340.000
|
$10.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
90.000
|
$80.000
|
$590.000
|
$10.000
|
|
Totals: |
$6,173,145.090
|
$7,618,726.750
|
$7,998,851.350
|