NUECES VA (0916-00-234)
Items: 8
County: NUECES
Length: N/A
Highway: VA
District: CORPUS CHRISTI
Control Number: 0916-00-234
DBE Goal: N/A
Project: C 916-00-234
Guaranty: N/A
Time: 102 WORKING DAYS
Engineer's Estimate: $2,044,415.66
Date: 07/01/2021 (5 years ago)
Contract Number: N/A
Type: UPGRADE SIGNAL CABINET AND INTERCONNECTION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Pay Estimates:
Documents
1 files available
Bidders (10)
E
Engineer's Estimate
$2,044,415.66
1
Awarded
$1,718,070.00
Over/Under Est:
-15.96%
-$326,345.66
$1,828,775.00
Over/Under Est:
-10.55%
-$215,640.66
Amt Left:
6.44%
$110,705.00
$1,841,612.00
Over/Under Est:
-9.92%
-$202,803.66
Amt Left:
7.19%
$123,542.00
Delta:
-0.70%
-$12,837.00
$1,903,926.60
Over/Under Est:
-6.87%
-$140,489.06
Amt Left:
10.82%
$185,856.60
Delta:
-3.38%
-$62,314.60
$1,943,699.00
Over/Under Est:
-4.93%
-$100,716.66
Amt Left:
13.13%
$225,629.00
Delta:
-2.09%
-$39,772.40
$1,974,685.00
Over/Under Est:
-3.41%
-$69,730.66
Amt Left:
14.94%
$256,615.00
Delta:
-1.59%
-$30,986.00
$2,084,610.00
Over/Under Est:
1.97%
$40,194.34
Amt Left:
21.33%
$366,540.00
Delta:
-5.57%
-$109,925.00
$2,175,691.04
Over/Under Est:
6.42%
$131,275.38
Amt Left:
26.64%
$457,621.04
Delta:
-4.37%
-$91,081.04
$2,219,120.00
Over/Under Est:
8.55%
$174,704.34
Amt Left:
29.16%
$501,050.00
Delta:
-2.00%
-$43,428.96
$2,400,531.42
Over/Under Est:
17.42%
$356,115.76
Amt Left:
39.72%
$682,461.42
Delta:
-8.17%
-$181,411.42
Bid Items & Bid Tabulations
8
Total
0 of 8