REMOVING CONC (DRIVEWAYS)
|
SY
|
535.000
|
$25.000
|
$24.450
|
$12.950
|
$8.300
|
$25.000
|
$16.950
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
4,703.000
|
$6.000
|
$5.750
|
$15.000
|
$6.900
|
$5.000
|
$6.860
|
|
|
REMOVING STAB BASE & ASPH PAV (7"-12")
|
SY
|
17,550.000
|
$10.000
|
$3.800
|
$7.000
|
$6.200
|
$6.000
|
$4.280
|
|
|
REMOVING STAB BASE AND ASPH PAV (7")
|
SY
|
275.000
|
$3.500
|
$6.650
|
$8.000
|
$10.900
|
$25.000
|
$11.460
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
115.000
|
$15.000
|
$75.000
|
$5.000
|
$51.000
|
$30.000
|
$43.770
|
|
|
BACKFILL (TY B)
|
STA
|
34.610
|
$200.000
|
$230.000
|
$100.000
|
$275.000
|
$200.000
|
$679.960
|
|
|
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
|
AC
|
1.660
|
$15,000.000
|
$2,000.000
|
$1,865.000
|
$2,500.000
|
$3,530.000
|
$2,051.500
|
|
|
DRILL SEEDING (TEMP)(WARM OR COOL)
|
AC
|
1.660
|
$5,000.000
|
$1,020.000
|
$964.000
|
$1,300.000
|
$2,670.000
|
$1,060.400
|
|
|
VEGETATIVE WATERING
|
MG
|
135.000
|
$20.000
|
$50.000
|
$10.000
|
$85.000
|
$22.500
|
$44.800
|
|
|
FL BS (CMP IN PLC)(TY A OR B GR 4)(9")
|
SY
|
17,550.000
|
$20.000
|
$10.750
|
$18.500
|
$14.500
|
$14.000
|
$23.520
|
|
|
LIME (QUICKLIME (DRY))
|
TON
|
232.000
|
$250.000
|
$193.000
|
$178.440
|
$215.000
|
$200.000
|
$214.500
|
|
|
FLY ASH (CLASS CS)
|
TON
|
618.000
|
$150.000
|
$83.300
|
$78.950
|
$96.000
|
$85.000
|
$99.000
|
|
|
LFA TREAT SUBGRADE (12")
|
SY
|
18,084.000
|
$6.000
|
$4.300
|
$3.500
|
$4.700
|
$4.000
|
$5.280
|
|
|
CEMENT
|
TON
|
131.000
|
$300.000
|
$150.750
|
$160.670
|
$210.000
|
$150.000
|
$201.340
|
|
|
PRIME COAT (CSS-1H)
|
GAL
|
5,265.000
|
$3.000
|
$3.050
|
$2.500
|
$3.800
|
$2.750
|
$4.980
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
8,775.000
|
$4.000
|
$2.900
|
$3.000
|
$3.500
|
$3.000
|
$4.170
|
|
|
AGGR(TY-A GR-4 SAC-B)
|
CY
|
160.000
|
$200.000
|
$158.000
|
$155.600
|
$165.000
|
$110.000
|
$181.060
|
|
|
D-GR HMA TY B SAC-B PG (64-22)
|
TON
|
2,631.000
|
$110.000
|
$99.400
|
$89.480
|
$126.000
|
$130.000
|
$129.280
|
|
|
SUPERPAVE MIXTURES SP-D SAC-A PG70-28
|
TON
|
6,416.000
|
$120.000
|
$103.000
|
$107.660
|
$136.000
|
$150.000
|
$139.060
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
6,431.000
|
$2.500
|
$4.350
|
$2.330
|
$5.050
|
$5.000
|
$2.410
|
|
|
PLANE ASPH CONC PAV (6")
|
SY
|
15,679.000
|
$5.000
|
$5.000
|
$3.500
|
$4.400
|
$5.000
|
$2.830
|
|
|
CL A CONC (MISC)
|
CY
|
22.000
|
$550.000
|
$369.000
|
$600.000
|
$470.000
|
$700.000
|
$606.090
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
1.750
|
$525.000
|
$342.600
|
$100.000
|
$440.000
|
$600.000
|
$1,171.770
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
20.000
|
$525.000
|
$339.400
|
$100.000
|
$435.000
|
$600.000
|
$709.350
|
|
|
RAIL (HANDRAIL)(TY E)
|
LF
|
50.000
|
$150.000
|
$220.000
|
$106.500
|
$150.000
|
$110.000
|
$230.090
|
|
|
CONC BOX CULV (7 FT X 3 FT)
|
LF
|
76.000
|
$550.000
|
$454.000
|
$435.000
|
$545.000
|
$375.000
|
$984.330
|
|
|
WINGWALL (FW - 0) (HW=4 FT)
|
EA
|
2.000
|
$7,500.000
|
$8,020.000
|
$7,500.000
|
$10,250.000
|
$10,000.000
|
$12,750.310
|
|
|
ADJUSTING MANHOLES
|
EA
|
1.000
|
$1,500.000
|
$1,550.000
|
$1,500.000
|
$1,300.000
|
$3,500.000
|
$3,917.120
|
|
|
ADJUSTING INLETS
|
EA
|
11.000
|
$4,000.000
|
$4,150.000
|
$10,450.000
|
$4,900.000
|
$3,500.000
|
$9,192.340
|
|
|
REMOV STR (HEADWALL)
|
EA
|
2.000
|
$2,000.000
|
$2,240.000
|
$4,000.000
|
$6,400.000
|
$3,000.000
|
$9,394.370
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$326,550.000
|
$290,000.000
|
$300,000.000
|
$327,800.000
|
$345,000.000
|
$361,294.540
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
10.000
|
$8,000.000
|
$13,000.000
|
$16,100.000
|
$3,650.000
|
$11,000.000
|
$2,976.880
|
|
|
CONSTRUCTION PERIMETER FENCE
|
LF
|
531.000
|
$5.000
|
$6.650
|
$0.650
|
$5.400
|
$5.000
|
$5.500
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
777.000
|
$5.000
|
$11.900
|
$3.720
|
$7.300
|
$5.000
|
$4.090
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
777.000
|
$2.000
|
$1.550
|
$0.600
|
$3.800
|
$1.000
|
$0.660
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
3,857.000
|
$22.500
|
$20.550
|
$27.500
|
$26.200
|
$20.000
|
$37.800
|
|
|
TURNOUTS (ACP)
|
SY
|
921.000
|
$80.000
|
$73.350
|
$100.000
|
$94.000
|
$70.000
|
$71.070
|
|
|
CONC SIDEWALKS (4")
|
SY
|
1,280.000
|
$75.000
|
$74.150
|
$50.000
|
$73.000
|
$60.000
|
$74.050
|
|
|
CURB RAMPS (TY 7)
|
SY
|
48.000
|
$150.000
|
$125.000
|
$48.000
|
$155.000
|
$120.000
|
$168.900
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
5.000
|
$800.000
|
$620.000
|
$700.000
|
$620.000
|
$550.000
|
$1,457.500
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$1,000.000
|
$695.000
|
$700.000
|
$516.000
|
$500.000
|
$1,512.500
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
7.000
|
$125.000
|
$125.000
|
$100.000
|
$72.000
|
$50.000
|
$165.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
2.000
|
$125.000
|
$230.000
|
$500.000
|
$152.000
|
$140.000
|
$220.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
2.000
|
$15.000
|
$27.000
|
$500.000
|
$63.000
|
$16.000
|
$22.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
110.000
|
$0.500
|
$0.540
|
$0.510
|
$0.700
|
$0.510
|
$0.560
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
6,515.000
|
$0.500
|
$0.540
|
$0.510
|
$0.700
|
$0.510
|
$0.560
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
80.000
|
$0.500
|
$0.540
|
$0.510
|
$0.700
|
$0.510
|
$0.560
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
12,537.000
|
$0.500
|
$0.540
|
$0.510
|
$0.700
|
$0.510
|
$0.560
|
|
|
WK ZN PAV MRK REMOV (REFL) TY I-C
|
EA
|
300.000
|
$5.000
|
$4.220
|
$4.000
|
$5.400
|
$4.000
|
$4.400
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
213.000
|
$6.000
|
$4.220
|
$4.000
|
$5.400
|
$4.000
|
$4.400
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY W
|
EA
|
243.000
|
$5.000
|
$3.160
|
$3.000
|
$4.000
|
$3.000
|
$3.300
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
|
EA
|
419.000
|
$5.000
|
$3.160
|
$3.000
|
$4.000
|
$3.000
|
$3.300
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,195.000
|
$1.000
|
$1.200
|
$0.550
|
$1.000
|
$1.000
|
$0.970
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
4,612.000
|
$1.000
|
$1.250
|
$0.550
|
$1.000
|
$1.000
|
$0.970
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
345.000
|
$0.750
|
$0.530
|
$0.500
|
$0.700
|
$0.500
|
$0.550
|
|
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
|
LF
|
660.000
|
$2.000
|
$2.110
|
$2.000
|
$2.700
|
$2.000
|
$2.200
|
|
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
|
LF
|
155.000
|
$5.500
|
$6.320
|
$6.000
|
$8.000
|
$6.000
|
$6.600
|
|
REFL PAV MRK TY I (W)(ARROW)(090MIL)
|
EA
|
7.000
|
$150.000
|
$158.120
|
$150.000
|
$202.000
|
$150.000
|
$165.000
|
|
REFL PAV MRK TY I (W)(WORD)(090MIL)
|
EA
|
4.000
|
$225.000
|
$210.830
|
$200.000
|
$269.000
|
$200.000
|
$220.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
|
LF
|
5,920.000
|
$0.350
|
$0.260
|
$0.250
|
$0.350
|
$0.250
|
$0.280
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
4,020.000
|
$0.350
|
$0.260
|
$0.250
|
$0.350
|
$0.250
|
$0.280
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
18,995.000
|
$0.350
|
$0.260
|
$0.250
|
$0.350
|
$0.250
|
$0.280
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
7,338.000
|
$1.000
|
$1.210
|
$1.150
|
$1.500
|
$1.150
|
$1.270
|
|
|
EMULSION
|
GAL
|
118,168.000
|
$3.500
|
$3.100
|
$2.520
|
$3.700
|
$3.500
|
$3.810
|
|
|
EMUL TRTMNT(MX EXST MTRL & NEW BASE) 9"
|
SY
|
17,550.000
|
$8.000
|
$7.300
|
$4.500
|
$2.300
|
$7.700
|
$8.090
|
|
|
GEOGRID BASE REINFORCEMENT (TY II)
|
SY
|
17,550.000
|
$2.250
|
$1.750
|
$2.000
|
$2.200
|
$2.000
|
$1.390
|
|
Totals: |
$3,608,422.250
|
$2,999,163.700
|
$3,151,055.880
|
$3,435,092.350
|
$3,527,541.620
|
$3,837,493.817
|