PREPARING ROW
|
STA
|
12.000
|
$20,000.000
|
$22,000.000
|
$2,500.000
|
$1,647.730
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
1,357.000
|
$20.000
|
$38.500
|
$100.000
|
$52.800
|
|
|
BLADING
|
HR
|
90.000
|
$280.000
|
$450.000
|
$250.000
|
$274.490
|
|
|
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
|
SY
|
2,574.000
|
$1.000
|
$1.150
|
$2.000
|
$1.200
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
2,574.000
|
$1.000
|
$0.900
|
$1.500
|
$0.960
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-28
|
TON
|
30,835.000
|
$148.000
|
$187.000
|
$150.000
|
$240.110
|
|
|
TACK COAT
|
GAL
|
29,152.000
|
$5.000
|
$6.400
|
$4.000
|
$9.180
|
|
|
PLANE ASPH CONC PAV (2 1/2")
|
SY
|
224,252.000
|
$4.000
|
$3.100
|
$3.000
|
$4.200
|
|
|
CURB (TYPE I)
|
LF
|
1,275.000
|
$30.000
|
$22.450
|
$30.000
|
$52.800
|
|
|
FULL-DPTH REP(BR APPROACH SLAB)(9"-13")
|
SY
|
115.000
|
$500.000
|
$1,840.000
|
$1,000.000
|
$1,980.000
|
|
|
CUT & RESTORING PAV
|
SY
|
689.000
|
$300.000
|
$91.000
|
$200.000
|
$264.000
|
|
|
CONC STR REPR(RAPID DECK REP(FULL DPT))
|
SF
|
1,038.000
|
$250.000
|
$190.000
|
$100.000
|
$204.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
2,810.000
|
$600.000
|
$445.000
|
$1,000.000
|
$792.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
471.000
|
$600.000
|
$545.000
|
$1,100.000
|
$792.000
|
|
|
RIPRAP (MOW STRIP)(5 IN)
|
CY
|
37.000
|
$600.000
|
$550.000
|
$1,100.000
|
$990.000
|
|
|
JOINT SEALANT
|
LF
|
716.000
|
$75.000
|
$151.500
|
$100.000
|
$163.200
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
88.000
|
$150.000
|
$330.000
|
$310.000
|
$569.600
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
344.000
|
$175.000
|
$385.000
|
$320.000
|
$330.000
|
|
|
INLET (COMPL)(PSL)(FG)(3FTX5FT-3FTX5FT)
|
EA
|
45.000
|
$5,200.000
|
$8,950.000
|
$15,000.000
|
$12,540.000
|
|
|
INLET (COMPL)(TY H)
|
EA
|
18.000
|
$7,200.000
|
$6,900.000
|
$10,000.000
|
$7,920.000
|
|
|
ADJUSTING INLETS
|
EA
|
1.000
|
$2,000.000
|
$3,600.000
|
$15,000.000
|
$6,600.000
|
|
|
ADJUSTING INLET (CAP)
|
EA
|
85.000
|
$3,300.000
|
$3,600.000
|
$5,000.000
|
$4,620.000
|
|
|
REMOV STR (PIPE)
|
LF
|
196.000
|
$20.000
|
$245.000
|
$100.000
|
$33.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$950,000.000
|
$1,290,000.000
|
$1,400,000.000
|
$1,682,476.260
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$20,000.000
|
$66,000.000
|
$120,000.000
|
$71,537.800
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
480.000
|
$35.000
|
$45.500
|
$50.000
|
$90.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
480.000
|
$6.000
|
$8.000
|
$15.000
|
$18.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
171.000
|
$6.000
|
$10.000
|
$4.500
|
$6.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
171.000
|
$2.000
|
$5.000
|
$1.000
|
$1.200
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
2,825.000
|
$5.000
|
$8.100
|
$5.000
|
$2.940
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
250.000
|
$6.500
|
$15.000
|
$5.500
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
3,075.000
|
$2.000
|
$5.000
|
$1.000
|
$1.200
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (42 )
|
LF
|
509.000
|
$150.000
|
$154.000
|
$150.000
|
$165.240
|
|
|
PERM CTB (SGL SLOPE) (TY 3) (42 )
|
LF
|
28.000
|
$200.000
|
$230.000
|
$210.000
|
$249.360
|
|
|
PERM CTB (SSCB)(TY 1)(MOD)
|
LF
|
80.000
|
$225.000
|
$180.000
|
$165.000
|
$191.840
|
|
|
PERM CTB (SGL SLOPE)(TY 1)(TRANSITION)
|
LF
|
28.000
|
$300.000
|
$235.000
|
$250.000
|
$251.280
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
8,109.000
|
$30.000
|
$40.650
|
$31.000
|
$43.800
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
21.000
|
$1,900.000
|
$3,065.000
|
$2,175.000
|
$3,300.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
17.000
|
$1,600.000
|
$1,800.000
|
$1,475.000
|
$1,950.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
8,638.000
|
$5.000
|
$3.650
|
$2.000
|
$3.900
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
16.000
|
$330.000
|
$365.000
|
$350.000
|
$390.000
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
2.000
|
$450.000
|
$365.000
|
$350.000
|
$390.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
19.000
|
$315.000
|
$365.000
|
$350.000
|
$390.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
24.000
|
$3,000.000
|
$4,100.000
|
$3,079.000
|
$4,410.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
23.000
|
$500.000
|
$365.000
|
$350.000
|
$390.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
12.000
|
$20.000
|
$20.000
|
$32.000
|
$21.600
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
36.000
|
$25.000
|
$15.000
|
$10.000
|
$12.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
54.000
|
$40.000
|
$40.000
|
$39.000
|
$42.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
14.000
|
$30.000
|
$39.000
|
$40.000
|
$42.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
22.000
|
$35.000
|
$39.000
|
$39.000
|
$42.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
84.000
|
$150.000
|
$165.000
|
$150.000
|
$180.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
15,540.000
|
$1.500
|
$1.300
|
$1.000
|
$1.530
|
|
REFL PAV MRK TY I (W)4"(DOT)(090MIL)
|
LF
|
582.000
|
$1.500
|
$1.100
|
$1.000
|
$1.200
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
14,074.000
|
$1.500
|
$1.050
|
$0.920
|
$1.100
|
|
REFL PAV MRK TY I (W)12"(LNDP)(090MIL)
|
LF
|
156.000
|
$3.000
|
$3.350
|
$3.000
|
$3.600
|
|
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
|
LF
|
4,515.000
|
$3.000
|
$2.800
|
$2.500
|
$3.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
|
LF
|
32,310.000
|
$0.500
|
$0.500
|
$0.460
|
$0.550
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
73,543.000
|
$0.500
|
$0.500
|
$0.460
|
$0.550
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
76,365.000
|
$0.500
|
$0.600
|
$0.510
|
$0.610
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$15,000.000
|
$24,000.000
|
$15,500.000
|
$11,081.580
|
|
|
TMA (STATIONARY)
|
DAY
|
145.000
|
$300.000
|
$542.030
|
$710.000
|
$470.820
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
210.000
|
$90.000
|
$85.700
|
$95.000
|
$125.790
|
|
Totals: |
$11,234,135.000
|
$13,120,890.350
|
$14,176,711.610
|
$16,824,762.670
|