PREPARING ROW
|
AC
|
0.230
|
$40,000.000
|
$19,312.250
|
$160,000.000
|
$100,000.000
|
$5,000.000
|
$250,000.000
|
$35,000.000
|
|
|
PREP ROW (TREE PRUNE AND TRIM)
|
STA
|
4.000
|
$1,250.000
|
$795.150
|
$1,500.000
|
$2,500.000
|
$555.000
|
$25,000.000
|
$6,000.000
|
|
|
REMOV CONC (RIPRAP)
|
SY
|
3,321.000
|
$30.000
|
$21.100
|
$15.000
|
$15.000
|
$14.500
|
$14.000
|
$16.000
|
|
|
REMOV CONC (DRIVEWAYS)
|
SY
|
1,868.000
|
$30.000
|
$29.250
|
$15.000
|
$15.000
|
$17.400
|
$26.000
|
$14.000
|
|
|
REMOV CONC (SIDEWALK, RAMP OR SUP)
|
SY
|
858.000
|
$20.000
|
$26.550
|
$15.000
|
$15.000
|
$14.500
|
$15.000
|
$20.000
|
|
|
REMOV CONC (CURB)
|
LF
|
744.000
|
$15.000
|
$9.950
|
$5.000
|
$10.000
|
$7.200
|
$12.000
|
$9.000
|
|
|
RMV (0"-4") TRT/UNTRT BASE & ASPH PAV
|
SY
|
438.000
|
$10.000
|
$27.100
|
$15.000
|
$15.000
|
$10.000
|
$20.000
|
$15.000
|
|
|
EXCAV (ROADWAY)
|
CY
|
4,922.000
|
$29.700
|
$21.550
|
$15.000
|
$25.000
|
$53.100
|
$45.000
|
$200.000
|
|
|
SUBGR WIDEN (OC)
|
SY
|
2,770.000
|
$18.000
|
$9.900
|
$20.000
|
$10.000
|
$7.550
|
$25.000
|
$15.200
|
|
|
EMBANK (FNL)(DC)(TY B)
|
CY
|
764.000
|
$40.000
|
$50.800
|
$45.000
|
$25.000
|
$15.000
|
$60.000
|
$120.000
|
|
|
DRILL SEED (TEMP_WARM_COOL)
|
SY
|
29,141.000
|
$0.200
|
$0.250
|
$0.330
|
$0.400
|
$0.330
|
$1.000
|
$0.200
|
|
|
HYDRO MULCH SEED (PERM_URBAN_CLAY)
|
SY
|
29,141.000
|
$0.600
|
$0.850
|
$0.450
|
$0.500
|
$0.450
|
$1.000
|
$0.650
|
|
|
VEGETATIVE WATERING
|
TGL
|
488.000
|
$25.000
|
$50.900
|
$45.000
|
$25.000
|
$25.000
|
$30.000
|
$86.000
|
|
|
SOIL RET BLKT(SL_STEEP_CLAY_SHORT)
|
SY
|
2,778.000
|
$3.750
|
$6.350
|
$2.250
|
$3.000
|
$2.250
|
$2.500
|
$5.000
|
|
|
SP MIXES SP-D SAC-A PG70-28
|
TON
|
7,649.000
|
$130.000
|
$164.700
|
$186.440
|
$180.000
|
$174.000
|
$165.000
|
$250.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
|
SY
|
250.000
|
$120.000
|
$200.650
|
$206.540
|
$160.000
|
$225.000
|
$183.000
|
$200.000
|
|
|
PLANE & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
12,884.000
|
$3.000
|
$4.000
|
$5.200
|
$3.000
|
$4.800
|
$5.150
|
$5.000
|
|
|
CL A CONC (FLUME)
|
CY
|
7.000
|
$725.000
|
$855.200
|
$2,000.000
|
$800.000
|
$740.000
|
$2,700.000
|
$1,300.000
|
|
|
CL C CONC (ABUT)
|
CY
|
40.000
|
$2,000.000
|
$1,534.900
|
$1,000.000
|
$3,000.000
|
$740.000
|
$965.000
|
$1,700.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
202.000
|
$800.000
|
$506.750
|
$650.000
|
$550.000
|
$550.000
|
$740.000
|
$573.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
113.000
|
$725.000
|
$557.250
|
$650.000
|
$675.000
|
$740.000
|
$800.000
|
$801.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
33.000
|
$750.000
|
$679.800
|
$650.000
|
$550.000
|
$740.000
|
$815.000
|
$726.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
46.000
|
$725.000
|
$837.450
|
$952.700
|
$600.000
|
$740.000
|
$940.000
|
$698.000
|
|
|
RAIL (TY SSTR)
|
LF
|
375.000
|
$125.000
|
$138.450
|
$180.000
|
$110.000
|
$110.000
|
$215.000
|
$95.000
|
|
|
RAIL (HANDRAIL)(TY E)
|
LF
|
2,729.000
|
$180.000
|
$120.000
|
$85.000
|
$125.000
|
$127.000
|
$100.000
|
$96.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
43.000
|
$450.000
|
$562.100
|
$650.000
|
$300.000
|
$436.000
|
$530.000
|
$302.000
|
|
|
INLET (COMPL)(TY S)
|
EA
|
10.000
|
$9,360.000
|
$14,725.110
|
$4,500.000
|
$5,500.000
|
$8,760.000
|
$7,900.000
|
$8,000.000
|
|
|
INLET (COMPL)(PSL)(FG)(4FTX5FT-3FTX5FT)
|
EA
|
2.000
|
$16,000.000
|
$12,265.450
|
$14,000.000
|
$9,500.000
|
$7,150.000
|
$15,000.000
|
$8,050.000
|
|
|
ADJUSTING MANHOLES
|
EA
|
10.000
|
$1,000.000
|
$1,087.260
|
$2,000.000
|
$750.000
|
$850.000
|
$750.000
|
$1,350.000
|
|
|
ADJUSTING MANHOLES (UTILITY BOX)
|
EA
|
1.000
|
$1,000.000
|
$981.710
|
$2,000.000
|
$750.000
|
$950.000
|
$1,500.000
|
$1,350.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
2.000
|
$3,000.000
|
$5,196.100
|
$5,000.000
|
$2,000.000
|
$3,800.000
|
$2,000.000
|
$5,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$650,000.000
|
$736,478.000
|
$755,000.000
|
$635,000.000
|
$818,227.000
|
$889,000.000
|
$1,100,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$20,000.000
|
$8,473.300
|
$6,000.000
|
$2,100.000
|
$7,500.000
|
$35,000.000
|
$170,000.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$16,809.450
|
$16,500.000
|
$18,500.000
|
$11,600.000
|
$14,000.000
|
$30,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
144.000
|
$200.000
|
$415.950
|
$160.000
|
$230.000
|
$150.000
|
$350.000
|
$350.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
40.000
|
$100.000
|
$105.550
|
$20.000
|
$95.000
|
$385.000
|
$100.000
|
$65.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
50.000
|
$70.000
|
$72.180
|
$77.380
|
$50.000
|
$37.500
|
$100.000
|
$75.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
50.000
|
$30.000
|
$22.900
|
$20.630
|
$25.000
|
$10.000
|
$50.000
|
$20.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$21.950
|
$47.850
|
$34.050
|
$30.000
|
$32.800
|
$50.000
|
$33.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$8.020
|
$19.250
|
$17.540
|
$15.000
|
$4.100
|
$5.000
|
$17.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,899.000
|
$6.000
|
$6.350
|
$5.310
|
$5.000
|
$2.600
|
$4.000
|
$5.150
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,899.000
|
$1.020
|
$1.600
|
$1.030
|
$1.000
|
$0.500
|
$2.000
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
3,969.000
|
$7.150
|
$8.900
|
$5.420
|
$6.000
|
$2.650
|
$7.500
|
$5.250
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
3,969.000
|
$3.350
|
$1.250
|
$1.030
|
$2.000
|
$0.500
|
$4.000
|
$1.000
|
|
|
COLORED TEXTURED CONC (4")
|
SY
|
812.000
|
$100.000
|
$62.650
|
$66.000
|
$75.000
|
$125.000
|
$80.000
|
$100.000
|
|
|
CONC CURB (TY I)
|
LF
|
60.000
|
$40.000
|
$33.650
|
$90.000
|
$50.000
|
$76.000
|
$60.000
|
$37.000
|
|
|
CONC CURB (TY F2)
|
LF
|
101.000
|
$171.770
|
$183.800
|
$250.000
|
$375.000
|
$150.000
|
$250.000
|
$385.000
|
|
|
CONC CURB (TY F3)
|
LF
|
356.000
|
$175.000
|
$216.500
|
$250.000
|
$325.000
|
$250.000
|
$340.000
|
$422.000
|
|
|
CONC CURB (TY C2)
|
LF
|
2,207.000
|
$178.670
|
$89.850
|
$200.000
|
$140.000
|
$250.000
|
$230.000
|
$200.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
2,197.000
|
$120.000
|
$102.750
|
$95.000
|
$125.000
|
$105.000
|
$110.000
|
$97.000
|
|
|
CONC SIDEWALKS (5")
|
SY
|
16,069.000
|
$94.000
|
$58.280
|
$66.000
|
$75.000
|
$85.000
|
$80.000
|
$80.000
|
|
|
CURB RAMPS (TY 2)
|
SY
|
92.000
|
$120.000
|
$210.800
|
$125.000
|
$165.000
|
$135.000
|
$215.000
|
$166.000
|
|
|
CURB RAMPS (TY 5)
|
SY
|
44.000
|
$250.000
|
$229.400
|
$125.000
|
$165.000
|
$135.000
|
$215.000
|
$140.000
|
|
|
CURB RAMPS (TY 7)
|
SY
|
370.000
|
$250.000
|
$155.550
|
$125.000
|
$165.000
|
$135.000
|
$165.000
|
$147.000
|
|
|
CURB RAMPS (TY 10)
|
SY
|
21.000
|
$300.000
|
$497.800
|
$125.000
|
$165.000
|
$135.000
|
$270.000
|
$160.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
825.000
|
$35.750
|
$36.800
|
$41.470
|
$35.000
|
$32.000
|
$40.000
|
$30.000
|
|
|
MTL BEAM GD FEN TRANS (TL2)
|
EA
|
2.000
|
$3,075.000
|
$1,581.250
|
$1,793.320
|
$1,500.000
|
$1,380.000
|
$1,720.000
|
$1,400.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
3.000
|
$1,068.710
|
$1,523.750
|
$1,793.310
|
$1,500.000
|
$1,330.000
|
$1,720.000
|
$1,350.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,300.000
|
$6.000
|
$3.450
|
$2.240
|
$3.000
|
$3.000
|
$3.000
|
$2.500
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
3.000
|
$250.000
|
$345.000
|
$560.410
|
$300.000
|
$300.000
|
$540.000
|
$150.000
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
3.000
|
$250.000
|
$345.000
|
$560.410
|
$300.000
|
$300.000
|
$540.000
|
$150.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
3.000
|
$3,800.000
|
$3,795.000
|
$4,483.290
|
$3,300.000
|
$3,300.000
|
$4,300.000
|
$3,325.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
75.000
|
$25.000
|
$23.000
|
$26.710
|
$20.000
|
$31.300
|
$35.000
|
$31.250
|
|
|
CONDT (PVC) (SCH 40) (3")
|
LF
|
5.000
|
$100.000
|
$28.250
|
$33.390
|
$25.000
|
$50.000
|
$55.000
|
$50.000
|
|
|
CONDUIT (PREPARE)
|
LF
|
410.000
|
$3.630
|
$9.200
|
$10.680
|
$8.000
|
$4.750
|
$5.000
|
$4.750
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
80.000
|
$5.000
|
$3.450
|
$4.010
|
$3.000
|
$6.500
|
$7.000
|
$6.500
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
9.000
|
$950.000
|
$914.250
|
$895.000
|
$800.000
|
$595.000
|
$960.000
|
$795.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
7.000
|
$1,100.000
|
$1,106.300
|
$1,070.000
|
$850.000
|
$745.000
|
$1,150.000
|
$962.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
19.000
|
$1,050.000
|
$1,114.350
|
$1,125.000
|
$850.000
|
$750.000
|
$1,200.000
|
$969.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$1,238.400
|
$1,628.400
|
$1,500.000
|
$1,000.000
|
$1,150.000
|
$1,610.000
|
$1,416.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
3.000
|
$720.000
|
$886.650
|
$920.000
|
$650.000
|
$618.000
|
$990.000
|
$771.000
|
|
|
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
|
EA
|
8.000
|
$550.000
|
$162.150
|
$250.000
|
$400.000
|
$345.000
|
$270.000
|
$141.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
31.000
|
$110.000
|
$127.350
|
$150.000
|
$100.000
|
$92.000
|
$160.000
|
$150.000
|
|
|
INSTL OM SM RD SIGN (1-OM-PW)Y
|
EA
|
29.000
|
$10.000
|
$14.950
|
$25.000
|
$20.000
|
$50.000
|
$27.000
|
$13.000
|
|
|
INSTL OM SM RD SIGN (1-OM-PW)R
|
EA
|
7.000
|
$10.000
|
$14.950
|
$25.000
|
$20.000
|
$50.000
|
$27.000
|
$13.000
|
|
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
|
LF
|
425.000
|
$1.240
|
$2.300
|
$1.000
|
$2.000
|
$2.000
|
$1.300
|
$1.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
1,612.000
|
$0.900
|
$1.250
|
$0.880
|
$1.100
|
$1.100
|
$1.300
|
$0.880
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
1,118.000
|
$7.410
|
$8.350
|
$6.770
|
$7.250
|
$7.250
|
$13.000
|
$6.770
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
19.000
|
$150.000
|
$215.050
|
$170.000
|
$187.000
|
$187.000
|
$245.000
|
$170.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
2.000
|
$150.000
|
$218.500
|
$175.000
|
$190.000
|
$190.000
|
$350.000
|
$175.000
|
|
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
|
LF
|
3,481.000
|
$0.550
|
$0.750
|
$0.570
|
$0.650
|
$0.650
|
$1.100
|
$0.570
|
|
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
|
LF
|
3,559.000
|
$0.550
|
$0.850
|
$0.570
|
$0.750
|
$0.750
|
$1.100
|
$0.570
|
|
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
|
LF
|
16,080.000
|
$0.400
|
$0.750
|
$0.550
|
$0.650
|
$0.650
|
$1.100
|
$0.550
|
|
RECESSED REFL PAV MRKR TY I-C
|
EA
|
431.000
|
$40.000
|
$46.300
|
$10.000
|
$40.250
|
$40.300
|
$55.000
|
$10.000
|
|
RECESSED REFL PAV MRKR TY II-A-A
|
EA
|
484.000
|
$40.000
|
$46.300
|
$10.000
|
$40.250
|
$40.300
|
$55.000
|
$10.000
|
|
|
INSTALL HWY TRF SIG (UPGRADE)
|
EA
|
1.000
|
$8,555.930
|
$11,500.000
|
$13,354.580
|
$10,000.000
|
$8,350.000
|
$9,000.000
|
$8,350.000
|
|
|
TRF SIG CBL (TY A)(10 AWG)(2 CONDR)
|
LF
|
1,050.000
|
$3.500
|
$4.050
|
$4.670
|
$3.500
|
$10.600
|
$11.500
|
$10.550
|
|
|
PEDESTRIAN PUSH BUTTON POLE
|
EA
|
6.000
|
$2,000.000
|
$5,175.000
|
$6,009.560
|
$4,500.000
|
$4,500.000
|
$4,825.000
|
$4,500.000
|
|
|
PED DETECT PUSH BUTTON (APS)
|
EA
|
8.000
|
$1,013.850
|
$1,380.000
|
$1,602.550
|
$1,200.000
|
$1,430.000
|
$1,525.000
|
$1,425.000
|
|
|
PED DETECTOR CONTROLLER UNIT
|
EA
|
1.000
|
$3,844.340
|
$1,840.000
|
$2,136.730
|
$1,600.000
|
$4,750.000
|
$5,100.000
|
$4,750.000
|
|
|
POST AND CABLE FENCE (NEW INSTALLATION)
|
LF
|
981.000
|
$19.000
|
$38.200
|
$28.020
|
$30.000
|
$25.000
|
$27.000
|
$25.000
|
|
|
POST AND CABLE FENCE (NEW CONC ANCHOR)
|
EA
|
8.000
|
$600.000
|
$254.700
|
$616.450
|
$550.000
|
$550.000
|
$590.000
|
$550.000
|
|
|
TIED-CONCRETE BLOCK EROSION CONTROL MAT
|
SF
|
5,990.000
|
$8.000
|
$12.000
|
$10.500
|
$10.000
|
$9.900
|
$6.300
|
$30.000
|
|
|
UNDERSEAL COURSE
|
GAL
|
15,302.000
|
$6.500
|
$8.350
|
$5.580
|
$8.000
|
$7.800
|
$5.000
|
$7.300
|
|
|
PREFAB CANTILEVER PED SYSTEM
|
SF
|
8,643.000
|
$162.000
|
$200.000
|
$192.000
|
$220.000
|
$207.000
|
$212.000
|
$250.000
|
|
|
FIXED BOLLARDS
|
EA
|
8.000
|
$1,200.000
|
$1,213.600
|
$800.000
|
$1,000.000
|
$1,100.000
|
$1,100.000
|
$2,700.000
|
|
|
GROUND BOX (PREPARE)
|
EA
|
4.000
|
$540.490
|
$747.500
|
$868.050
|
$650.000
|
$1,200.000
|
$1,300.000
|
$1,200.000
|
|
Totals: |
$7,802,744.750
|
$7,487,324.298
|
$7,598,853.110
|
$7,872,239.250
|
$8,330,254.230
|
$8,892,413.200
|
$11,756,266.520
|