PREPARING ROW
|
STA
|
77.000
|
$1,000.000
|
$500.000
|
$240.000
|
$1,129.620
|
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
5,267.000
|
$5.500
|
$25.000
|
$11.040
|
$20.990
|
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY A)
|
CY
|
2,338.000
|
$21.000
|
$25.000
|
$52.430
|
$24.610
|
|
|
|
BACKFILL (TY A)
|
STA
|
73.000
|
$144.000
|
$275.000
|
$263.000
|
$433.600
|
|
|
|
BLADING
|
HR
|
80.000
|
$85.000
|
$100.000
|
$180.000
|
$239.520
|
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
SY
|
424.000
|
$0.190
|
$2.500
|
$1.150
|
$1.510
|
|
|
|
VEGETATIVE WATERING
|
MG
|
1.000
|
$10.000
|
$160.000
|
$1,017.500
|
$2,589.960
|
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2) (6")
|
SY
|
24,971.000
|
$16.000
|
$16.000
|
$14.790
|
$19.370
|
|
|
|
PRIME COAT (SS-1H)
|
GAL
|
4,995.000
|
$4.500
|
$5.000
|
$4.770
|
$6.740
|
|
|
|
ASPH (AC-10)
|
GAL
|
9,989.000
|
$2.150
|
$4.500
|
$4.510
|
$5.410
|
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
228.000
|
$90.000
|
$200.000
|
$175.000
|
$324.080
|
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
10,594.000
|
$3.000
|
$2.000
|
$2.400
|
$5.090
|
|
|
|
STRUCT EXCAV (PIPE)
|
CY
|
85.000
|
$7.500
|
$1.000
|
$18.000
|
$80.420
|
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
76.000
|
$400.000
|
$700.000
|
$632.500
|
$1,189.080
|
|
|
|
CMP (GAL STL BIT COAT 36 IN)
|
LF
|
144.000
|
$5.000
|
$145.000
|
$126.500
|
$212.600
|
|
|
|
SET (PIPE RUNNER ASSEMBLY)
|
EA
|
16.000
|
$2,100.000
|
$1,675.000
|
$2,875.000
|
$3,424.120
|
|
|
|
SET (TY II) (36 IN) (CMP) (4: 1) (C)
|
EA
|
2.000
|
$3,500.000
|
$11,500.000
|
$4,025.000
|
$3,996.510
|
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$200,000.000
|
$225,000.000
|
$613,195.000
|
$530,897.050
|
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
6.000
|
$12,000.000
|
$7,500.000
|
$20,070.000
|
$8,922.640
|
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
110.000
|
$40.000
|
$70.000
|
$12.000
|
$40.080
|
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
110.000
|
$10.000
|
$24.000
|
$6.000
|
$10.930
|
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,954.000
|
$3.000
|
$2.500
|
$3.450
|
$4.210
|
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,954.000
|
$1.000
|
$1.250
|
$1.150
|
$2.290
|
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
6,990.000
|
$30.000
|
$68.000
|
$71.000
|
$92.880
|
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
6,990.000
|
$5.000
|
$2.000
|
$7.200
|
$10.530
|
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
6,990.000
|
$7.500
|
$8.000
|
$15.600
|
$15.670
|
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
6,400.000
|
$0.200
|
$0.350
|
$0.400
|
$0.800
|
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
6,400.000
|
$0.200
|
$0.350
|
$0.400
|
$0.800
|
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,749.000
|
$28.000
|
$35.000
|
$29.900
|
$35.490
|
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
1.000
|
$1,500.000
|
$1,800.000
|
$1,610.000
|
$1,681.160
|
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
1.000
|
$3,200.000
|
$4,500.000
|
$3,852.500
|
$3,047.360
|
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,250.000
|
$750.000
|
$1,800.000
|
$1,214.580
|
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$800.000
|
$750.000
|
$1,800.000
|
$1,214.580
|
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$8,000.000
|
$9,000.000
|
$7,787.500
|
$9,177.480
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
95.000
|
$550.000
|
$630.000
|
$655.500
|
$733.330
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
6.000
|
$600.000
|
$715.000
|
$747.500
|
$1,239.030
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
12.000
|
$950.000
|
$660.000
|
$690.000
|
$1,499.510
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U-EXAL)
|
EA
|
2.000
|
$900.000
|
$965.000
|
$1,006.250
|
$1,187.080
|
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
88.000
|
$120.000
|
$85.000
|
$86.250
|
$157.290
|
|
|
|
INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI)
|
EA
|
140.000
|
$60.000
|
$61.000
|
$63.250
|
$111.240
|
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
96.000
|
$75.000
|
$72.000
|
$74.750
|
$95.310
|
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
96.000
|
$20.000
|
$39.000
|
$40.250
|
$45.810
|
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
36,500.000
|
$0.750
|
$1.000
|
$1.130
|
$1.300
|
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
36,566.000
|
$0.750
|
$1.000
|
$1.130
|
$1.360
|
|
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
603.000
|
$1.000
|
$1.500
|
$1.730
|
$2.490
|
|
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
4.000
|
$125.000
|
$180.000
|
$207.000
|
$1,088.540
|
|
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
23,200.000
|
$0.500
|
$0.550
|
$0.630
|
$1.000
|
|
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
2,172.000
|
$0.800
|
$0.800
|
$0.900
|
$1.180
|
|
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
23,200.000
|
$0.300
|
$0.550
|
$0.630
|
$0.890
|
|
|
|
REFL PAV MRKR TY I-C
|
EA
|
109.000
|
$3.250
|
$4.000
|
$4.600
|
$9.850
|
|
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
290.000
|
$2.800
|
$4.000
|
$4.600
|
$6.100
|
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
112,326.000
|
$0.500
|
$0.750
|
$0.630
|
$0.610
|
|
|
|
SP MIXES SP-C SAC-A PG70-22
|
TON
|
4,121.000
|
$130.000
|
$140.000
|
$203.800
|
$234.140
|
|
|
|
TACK COAT
|
GAL
|
3,746.000
|
$4.000
|
$5.500
|
$4.170
|
$8.700
|
|
|
|
TMA (STATIONARY)
|
DAY
|
120.000
|
$180.000
|
$275.000
|
$300.000
|
$597.080
|
|
1
|
|
PTB (FUR & INST)(STEEL)
|
LF
|
6,990.000
|
$30.000
|
$0.000
|
$0.000
|
$0.000
|
|
1
|
|
PTB (MOVE)(STEEL)
|
LF
|
6,990.000
|
$5.000
|
$0.000
|
$0.000
|
$0.000
|
|
1
|
|
PTB (STKPL)(STEEL)
|
LF
|
6,990.000
|
$7.500
|
$0.000
|
$0.000
|
$0.000
|
|
Totals: |
$2,499,389.760
|
$2,763,014.600
|
$3,529,839.320
|
$4,164,663.780
|