PREPARING ROW
|
STA
|
82.000
|
$1,500.000
|
$609.760
|
$1,200.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
81.770
|
$800.000
|
$197.290
|
$950.000
|
|
|
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
|
CY
|
323.000
|
$30.000
|
$25.000
|
$38.000
|
|
|
BACKFILL (TY B)
|
STA
|
81.770
|
$175.000
|
$203.330
|
$155.000
|
|
|
BLADING
|
STA
|
81.770
|
$200.000
|
$90.650
|
$260.000
|
|
|
SPEC EXCAV WORK (HYD EXCAVATOR)
|
HR
|
6.000
|
$150.000
|
$171.600
|
$250.000
|
|
|
BLOCK SODDING
|
SY
|
153.000
|
$8.000
|
$15.000
|
$10.500
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
9,038.000
|
$0.330
|
$0.160
|
$0.150
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
9,038.000
|
$0.310
|
$0.150
|
$0.150
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
18,077.000
|
$0.500
|
$0.370
|
$0.400
|
|
|
VEGETATIVE WATERING
|
MG
|
726.300
|
$10.000
|
$0.010
|
$10.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
19.000
|
$1.000
|
$10.580
|
$26.000
|
|
|
CEM TRT(PLNT MX)(CL N)(TY D)(GR 4)(10")
|
SY
|
9,086.000
|
$60.000
|
$75.390
|
$90.000
|
|
|
FOG SEAL (SS-1 OR CSS-1)
|
GAL
|
363.000
|
$16.000
|
$17.500
|
$16.000
|
|
|
ASPH (RC-250)
|
TON
|
9.650
|
$1,700.000
|
$1,367.120
|
$1,750.000
|
|
|
AGGR (TY E OR L, PE OR PL GR 4)
|
CY
|
81.000
|
$400.000
|
$196.810
|
$280.000
|
|
|
AGGR (TY E OR L GR 5)
|
CY
|
63.000
|
$400.000
|
$252.780
|
$460.000
|
|
|
ASPH (AC-15P OR CRS-2P)
|
TON
|
64.820
|
$1,250.000
|
$1,039.980
|
$1,000.000
|
|
|
AGGR (TY E OR L, PE OR PL GR 4) (SAC-A)
|
CY
|
188.000
|
$250.000
|
$177.490
|
$200.000
|
|
|
CEM STABIL BKFL
|
CY
|
30.140
|
$250.000
|
$275.000
|
$210.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
20.000
|
$150.000
|
$176.000
|
$265.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
1.000
|
$1,300.000
|
$1,199.000
|
$2,100.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
19.000
|
$200.000
|
$247.500
|
$265.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
108.000
|
$70.000
|
$82.500
|
$63.000
|
|
|
HEADWALL (CH - FW - 0) (DIA= 30 IN)
|
EA
|
1.000
|
$8,500.000
|
$9,900.000
|
$4,700.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
1.000
|
$5,500.000
|
$6,600.000
|
$5,800.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 54 IN)
|
EA
|
1.000
|
$15,000.000
|
$19,844.000
|
$16,800.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
5.000
|
$700.000
|
$935.000
|
$945.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$800.000
|
$935.000
|
$1,050.000
|
|
|
REMOV STR (PIPE)
|
EA
|
2.000
|
$300.000
|
$330.000
|
$1,600.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$150,000.000
|
$136,600.000
|
$275,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$2,000.000
|
$1,402.500
|
$2,100.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
160.000
|
$50.000
|
$33.000
|
$40.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
160.000
|
$10.000
|
$9.000
|
$10.500
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 2)
|
SY
|
181.000
|
$25.000
|
$15.000
|
$68.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
181.000
|
$8.500
|
$5.000
|
$12.600
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
3,357.000
|
$3.500
|
$3.000
|
$3.100
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
3,357.000
|
$1.000
|
$1.000
|
$1.100
|
|
|
INTERSECTIONS (ACP)
|
SY
|
335.000
|
$125.000
|
$87.110
|
$90.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
2.000
|
$650.000
|
$814.000
|
$665.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
16.000
|
$450.000
|
$508.200
|
$450.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
18.000
|
$90.000
|
$115.500
|
$135.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
|
EA
|
9.000
|
$160.000
|
$138.600
|
$110.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
887.000
|
$0.500
|
$1.100
|
$1.050
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
12,824.000
|
$0.500
|
$1.100
|
$1.050
|
|
|
WK ZN PAV MRK REMOV (Y)4"(BRK)
|
LF
|
402.000
|
$1.100
|
$1.500
|
$1.300
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
2,935.000
|
$0.750
|
$1.500
|
$1.300
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
922.000
|
$1.000
|
$1.500
|
$1.900
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
16,131.000
|
$1.000
|
$1.870
|
$1.800
|
|
|
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
|
LF
|
887.000
|
$1.000
|
$3.300
|
$3.150
|
|
|
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
|
LF
|
12,824.000
|
$1.000
|
$2.200
|
$2.100
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
17.000
|
$9.000
|
$38.500
|
$37.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
211.000
|
$3.000
|
$11.000
|
$10.500
|
|
|
SP MIXES SP-D PG64-22 (LEVEL-UP)
|
TON
|
2,466.000
|
$160.000
|
$172.900
|
$161.000
|
|
|
BONDING COURSE
|
GAL
|
1,272.000
|
$5.000
|
$5.500
|
$5.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
1.000
|
$10,000.000
|
$10,000.000
|
$15,000.000
|
|
|
PREFORMED CENTERLINE RUMBLE STRIP
|
LF
|
29.000
|
$4.000
|
$33.000
|
$31.500
|
|
|
TMA (STATIONARY)
|
DAY
|
70.000
|
$250.000
|
$100.000
|
$235.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
6.000
|
$420.000
|
$50.000
|
$1.000
|
|
Totals: |
$1,787,801.520
|
$1,771,724.562
|
$2,191,119.350
|