PREPARING ROW
|
STA
|
47.000
|
$2,000.000
|
$1,950.000
|
$2,000.000
|
$1,500.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
494.000
|
$20.000
|
$23.100
|
$30.000
|
$15.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
98.000
|
$300.000
|
$914.640
|
$590.000
|
$1,000.000
|
|
|
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
|
CY
|
227.000
|
$15.000
|
$28.350
|
$55.000
|
$40.000
|
|
|
BACKFILL (TY B)
|
STA
|
98.000
|
$184.000
|
$120.750
|
$140.000
|
$345.000
|
|
|
BLADING
|
STA
|
98.000
|
$200.000
|
$121.900
|
$290.000
|
$260.000
|
|
|
SPEC EXCAV WORK (HYD EXCAVATOR)
|
HR
|
32.000
|
$150.000
|
$162.750
|
$285.000
|
$250.000
|
|
|
BLOCK SODDING
|
SY
|
1,412.000
|
$5.000
|
$5.070
|
$7.350
|
$8.000
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
10,909.000
|
$0.150
|
$0.120
|
$0.150
|
$0.500
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
10,909.000
|
$0.150
|
$0.120
|
$0.150
|
$0.500
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
21,818.000
|
$0.350
|
$0.370
|
$0.400
|
$0.650
|
|
|
VEGETATIVE WATERING
|
MG
|
891.300
|
$10.000
|
$0.010
|
$34.000
|
$5.000
|
|
|
CEM TRT(PLNT MX)(CL N)(TY D)(GR 4)(10")
|
SY
|
8,728.000
|
$55.000
|
$60.000
|
$84.000
|
$96.170
|
|
|
FOG SEAL (SS-1 OR CSS-1)
|
GAL
|
349.000
|
$4.250
|
$16.040
|
$15.000
|
$40.000
|
|
|
ASPH (RC-250)
|
TON
|
10.000
|
$1,100.000
|
$2,035.500
|
$1,500.000
|
$2,882.050
|
|
|
AGGR (TY E OR L GR 5)
|
CY
|
61.000
|
$175.000
|
$227.000
|
$350.000
|
$350.000
|
|
|
AGGR(TY-PE OR TY-PL)(GR-4)(SAC-B)
|
CY
|
301.000
|
$175.000
|
$186.300
|
$210.000
|
$225.000
|
|
|
ASPH (AC-15P OR CRS-2P)
|
TON
|
73.000
|
$900.000
|
$1,116.650
|
$1,050.000
|
$1,875.000
|
|
|
CEM STABIL BKFL
|
CY
|
10.000
|
$200.000
|
$217.350
|
$220.000
|
$250.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
3.000
|
$1,000.000
|
$840.000
|
$735.000
|
$1,500.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
24.000
|
$300.000
|
$173.250
|
$210.000
|
$250.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
1,238.000
|
$50.000
|
$51.450
|
$47.000
|
$60.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
36.000
|
$80.000
|
$75.600
|
$78.000
|
$200.000
|
|
|
HEADWALL (CH - FW - 0) (DIA= 42 IN)
|
EA
|
1.000
|
$6,000.000
|
$8,400.000
|
$14,000.000
|
$10,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
1.000
|
$7,000.000
|
$6,930.000
|
$11,000.000
|
$11,000.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 24 IN)
|
EA
|
1.000
|
$7,588.000
|
$4,935.000
|
$8,500.000
|
$7,000.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 48 IN)
|
EA
|
1.000
|
$11,000.000
|
$10,132.500
|
$15,000.000
|
$14,000.000
|
|
|
SET (TY II) (15 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$510.000
|
$682.500
|
$630.000
|
$700.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
6.000
|
$800.000
|
$735.000
|
$630.000
|
$750.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
82.000
|
$600.000
|
$792.750
|
$755.000
|
$850.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
5.000
|
$750.000
|
$1,155.000
|
$1,100.000
|
$1,200.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
4.000
|
$1,450.000
|
$1,260.000
|
$1,050.000
|
$500.000
|
|
|
REMOV STR (PIPE)
|
EA
|
37.000
|
$240.000
|
$240.450
|
$210.000
|
$100.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$170,000.000
|
$100,000.000
|
$250,000.000
|
$200,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
13.000
|
$2,000.000
|
$1,055.550
|
$1,950.000
|
$2,200.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
360.000
|
$30.000
|
$20.000
|
$42.000
|
$40.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
360.000
|
$10.000
|
$3.000
|
$8.400
|
$5.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
263.000
|
$25.000
|
$10.000
|
$31.000
|
$10.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
263.000
|
$7.500
|
$3.000
|
$8.400
|
$1.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,386.000
|
$2.500
|
$3.000
|
$3.500
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,386.000
|
$1.000
|
$1.000
|
$0.800
|
$1.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
548.000
|
$140.000
|
$112.350
|
$95.000
|
$130.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,216.000
|
$50.000
|
$60.000
|
$62.000
|
$62.620
|
|
|
TURNOUTS (SURF TREAT)
|
SY
|
385.000
|
$50.000
|
$52.500
|
$66.000
|
$70.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
1,986.000
|
$30.000
|
$39.450
|
$62.000
|
$48.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
16.000
|
$175.000
|
$283.500
|
$285.000
|
$400.000
|
|
|
MAILBOX INSTALL-D (WC-POST) TY 3
|
EA
|
3.000
|
$230.000
|
$283.500
|
$285.000
|
$400.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
3.000
|
$500.000
|
$682.500
|
$685.000
|
$1,000.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
19.000
|
$360.000
|
$456.750
|
$455.000
|
$1,200.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
22.000
|
$75.000
|
$99.750
|
$100.000
|
$50.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)SRF)SRF
|
EA
|
19.000
|
$90.430
|
$110.250
|
$110.000
|
$200.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
19,636.000
|
$0.200
|
$0.530
|
$0.550
|
$0.750
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
19,636.000
|
$0.500
|
$0.530
|
$0.550
|
$0.750
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
1,966.000
|
$1.000
|
$1.750
|
$2.000
|
$2.750
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
19,636.000
|
$0.750
|
$1.310
|
$1.300
|
$1.700
|
|
|
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
|
LF
|
5,410.000
|
$0.850
|
$1.580
|
$1.600
|
$1.700
|
|
|
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
|
LF
|
8,170.000
|
$0.710
|
$1.580
|
$1.600
|
$1.700
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
30.000
|
$20.000
|
$15.750
|
$16.000
|
$50.000
|
|
PREFAB PAV MRK TY C (W) (RR XING)
|
EA
|
2.000
|
$523.000
|
$735.000
|
$735.000
|
$1,000.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
225.000
|
$5.000
|
$5.250
|
$5.250
|
$20.000
|
|
|
SP MIXES SP-D SAC-B PG70-22 (LEVEL-UP)
|
TON
|
3,334.000
|
$130.000
|
$157.660
|
$160.000
|
$162.500
|
|
|
TACK COAT
|
GAL
|
2,837.000
|
$2.000
|
$5.250
|
$4.500
|
$5.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
1.000
|
$10,000.000
|
$20,000.000
|
$18,000.000
|
$7,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
75.000
|
$100.000
|
$230.000
|
$235.000
|
$175.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
5.000
|
$45.000
|
$50.000
|
$160.000
|
$500.000
|
|
Totals: |
$1,969,884.320
|
$2,185,617.713
|
$2,671,347.450
|
$2,871,905.080
|