CL C CONC (RAIL FOUNDATION)
|
CY
|
337.000
|
$1,300.000
|
$1,286.490
|
$966.000
|
$1,600.000
|
$2,000.000
|
|
|
PENETRATING CONCRETE SURFACE TREATMENT
|
SY
|
2,138.000
|
$30.000
|
$13.960
|
$5.950
|
$12.000
|
$10.000
|
|
|
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
|
SF
|
146.000
|
$250.000
|
$90.070
|
$100.000
|
$300.000
|
$500.000
|
|
|
CONC STR REPAIR(DECK REP(PART DEPTH))
|
SF
|
56.000
|
$400.000
|
$166.000
|
$150.000
|
$300.000
|
$650.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
191.000
|
$300.000
|
$330.670
|
$150.000
|
$300.000
|
$500.000
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL7)
|
LF
|
3,574.000
|
$50.000
|
$50.580
|
$35.000
|
$75.000
|
$10.000
|
|
|
RESIZING AND SEALING JOINTS
|
LF
|
422.000
|
$60.000
|
$115.080
|
$55.000
|
$100.000
|
$100.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$347,132.410
|
$419,545.000
|
$440,000.000
|
$440,000.000
|
$480,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
13.000
|
$20,000.000
|
$16,292.180
|
$84,000.000
|
$5,000.000
|
$10,000.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,310.000
|
$3.130
|
$3.500
|
$3.500
|
$6.000
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,310.000
|
$1.370
|
$1.000
|
$1.000
|
$2.000
|
$2.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
722.000
|
$8.000
|
$5.000
|
$5.000
|
$15.000
|
$18.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
722.000
|
$4.000
|
$1.250
|
$1.250
|
$5.000
|
$9.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
930.000
|
$125.000
|
$116.420
|
$88.000
|
$125.000
|
$100.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
6,320.000
|
$25.000
|
$29.910
|
$25.000
|
$30.000
|
$20.000
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 1)
|
LF
|
60.000
|
$37.000
|
$307.640
|
$27.000
|
$100.000
|
$30.000
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 2)
|
LF
|
20.000
|
$40.000
|
$857.920
|
$27.000
|
$100.000
|
$30.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
930.000
|
$35.000
|
$41.420
|
$15.000
|
$50.000
|
$20.000
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (42 )
|
LF
|
5,800.000
|
$200.000
|
$178.750
|
$165.000
|
$280.000
|
$225.000
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (54 )
|
LF
|
325.000
|
$250.000
|
$298.000
|
$201.000
|
$360.000
|
$300.000
|
|
|
PERM CTB (SGL SLOPE)(TY 1)(TRANSITION)
|
LF
|
60.000
|
$450.000
|
$435.870
|
$135.000
|
$360.000
|
$300.000
|
|
|
PERM CTB (TRAN SSCB TO T501)(MOD)
|
LF
|
200.000
|
$450.000
|
$345.110
|
$121.000
|
$360.000
|
$300.000
|
|
|
PERM CTB (TRAN SSCB TO C201)
|
LF
|
40.000
|
$450.000
|
$515.550
|
$121.000
|
$350.000
|
$300.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
19.000
|
$2,300.000
|
$2,784.430
|
$1,875.000
|
$1,200.000
|
$1,850.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
4,215.000
|
$4.000
|
$6.040
|
$3.000
|
$5.000
|
$3.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
12.000
|
$150.000
|
$655.210
|
$150.000
|
$300.000
|
$500.000
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
4.000
|
$145.000
|
$1,422.500
|
$125.000
|
$300.000
|
$500.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
19.000
|
$3,000.000
|
$3,784.430
|
$2,875.000
|
$1,200.000
|
$3,500.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
20.000
|
$300.000
|
$683.370
|
$250.000
|
$350.000
|
$1,500.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
18.000
|
$2,325.580
|
$1,521.010
|
$1,407.260
|
$1,800.000
|
$6,500.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
4.000
|
$914.240
|
$1,548.890
|
$1,870.340
|
$1,000.000
|
$2,500.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)
|
EA
|
1.000
|
$46,170.200
|
$42,897.060
|
$35,100.000
|
$41,000.000
|
$30,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
4.000
|
$10,000.000
|
$11,574.720
|
$11,747.040
|
$10,000.000
|
$30,000.000
|
|
|
REPLACE EXISTING ALUMINUM SIGNS(TY O)
|
SF
|
2,132.000
|
$60.000
|
$36.870
|
$40.000
|
$30.000
|
$40.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
2.000
|
$2,300.000
|
$3,125.420
|
$2,500.000
|
$500.000
|
$5,000.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
|
EA
|
4.000
|
$2,500.000
|
$2,812.710
|
$2,500.000
|
$500.000
|
$5,000.000
|
|
|
IN SM RD SN SUP&AM (RAIL MOUNT)
|
EA
|
46.000
|
$1,800.000
|
$4,785.890
|
$3,500.000
|
$200.000
|
$4,500.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
5.000
|
$450.000
|
$480.170
|
$150.000
|
$200.000
|
$50.000
|
|
|
REMOVE BRDG MNT CLEARANCE SIGN ASSM
|
EA
|
6.000
|
$500.000
|
$1,075.140
|
$750.000
|
$1,500.000
|
$1,500.000
|
|
|
REMOVE SIGN WALKWAY
|
EA
|
3.000
|
$3,000.000
|
$3,275.140
|
$3,500.000
|
$2,000.000
|
$1,500.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
348.000
|
$30.000
|
$14.650
|
$20.000
|
$12.000
|
$100.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
350.000
|
$30.000
|
$14.610
|
$20.000
|
$12.000
|
$100.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
190.000
|
$7.000
|
$11.840
|
$10.000
|
$12.000
|
$6.000
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
23,797.000
|
$1.000
|
$0.530
|
$1.000
|
$1.250
|
$2.000
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
1,630.000
|
$1.410
|
$1.450
|
$1.200
|
$1.500
|
$2.000
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
64.000
|
$1.670
|
$15.200
|
$3.000
|
$3.500
|
$2.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
23,797.000
|
$0.500
|
$0.080
|
$0.500
|
$1.000
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
1,630.000
|
$0.890
|
$0.600
|
$0.850
|
$1.200
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
244.000
|
$3.000
|
$3.760
|
$1.000
|
$1.200
|
$1.000
|
|
|
CNC CRACK REPAIR (DISCRETE)(INJECT)
|
LF
|
10.000
|
$200.000
|
$156.870
|
$150.000
|
$550.000
|
$1,000.000
|
|
|
BRIDGE JOINT REPAIR (SEJ)
|
LF
|
226.000
|
$207.500
|
$214.600
|
$74.000
|
$150.000
|
$200.000
|
|
|
CONCRETE BEAM REPAIR (CFRP)
|
EA
|
3.000
|
$20,000.000
|
$22,486.720
|
$13,800.000
|
$25,000.000
|
$25,000.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
6.000
|
$15,000.000
|
$20,896.780
|
$25,000.000
|
$10,000.000
|
$16,500.000
|
|
MULTIPOLYMER PAV MRK (W)(6")(SLD)
|
LF
|
10,007.000
|
$1.500
|
$0.930
|
$1.380
|
$1.500
|
$2.000
|
|
MULTIPOLYMER PAV MRK (W)(6")(BRK)
|
LF
|
1,910.000
|
$1.500
|
$1.530
|
$1.650
|
$2.000
|
$2.000
|
|
MULTIPOLYMER PAV MRK (W)(8")(SLD)
|
LF
|
1,630.000
|
$2.000
|
$2.060
|
$2.720
|
$3.000
|
$6.000
|
|
MULTIPOLYMER PAV MRK (W)(12")(SLD)
|
LF
|
244.000
|
$8.000
|
$10.630
|
$7.980
|
$9.000
|
$6.000
|
|
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
|
LF
|
9,970.000
|
$1.500
|
$0.930
|
$1.350
|
$1.500
|
$3.000
|
|
MULTIPOLYMER PAV MRK (BLK)(6")(BRK)
|
LF
|
1,910.000
|
$2.000
|
$1.930
|
$2.200
|
$2.500
|
$3.000
|
|
|
TMA (STATIONARY)
|
DAY
|
353.000
|
$288.520
|
$333.160
|
$384.000
|
$250.000
|
$250.000
|
|
|
INSTL LINEAR DELIN SYS(LDS)(6")(Y)(CTB)
|
EA
|
1,274.000
|
$55.000
|
$60.410
|
$60.500
|
$55.000
|
$100.000
|
|
|
INSTL LINEAR DELIN SYS(LDS)(6")(W)(CTB)
|
EA
|
228.000
|
$55.000
|
$64.180
|
$60.500
|
$55.000
|
$100.000
|
|
|
INSTL LIN DELIN SYS(LDS)(1.5")(Y)(GF)
|
EA
|
30.000
|
$55.000
|
$86.230
|
$50.000
|
$55.000
|
$100.000
|
|
|
INSTL LIN DELIN SYS(LDS)(1.5")(W)(GF)
|
EA
|
15.000
|
$55.000
|
$86.230
|
$50.000
|
$55.000
|
$100.000
|
|
Totals: |
$4,117,662.450
|
$4,195,452.120
|
$4,432,794.180
|
$4,482,409.550
|
$4,804,260.000
|