REMOVING CONC (RIPRAP)
|
SY
|
360.000
|
$20.000
|
$14.660
|
$42.000
|
$50.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
1,650.000
|
$7.500
|
$18.320
|
$21.000
|
$97.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
100.000
|
$100.000
|
$26.760
|
$52.500
|
$97.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
2,500.000
|
$0.100
|
$0.390
|
$7.350
|
$97.000
|
|
|
PLANE ASPH CONC PAV(0" TO 6")
|
SY
|
1,520.000
|
$10.000
|
$24.520
|
$25.200
|
$31.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
180.000
|
$20.000
|
$6.110
|
$21.000
|
$30.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
16.000
|
$200.000
|
$433.210
|
$210.000
|
$296.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
50.000
|
$500.000
|
$536.540
|
$735.000
|
$675.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
56.000
|
$80.000
|
$73.810
|
$210.000
|
$341.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
16.000
|
$100.000
|
$109.860
|
$315.000
|
$341.000
|
|
|
INLET(COMPL)(DROP)(TY 1)(1 GRATE)
|
EA
|
3.000
|
$5,000.000
|
$7,707.930
|
$6,300.000
|
$6,500.000
|
|
|
INLET(COMPL)(DROP)(TY 1 )(2 GRATE)
|
EA
|
3.000
|
$6,000.000
|
$11,688.590
|
$6,825.000
|
$8,500.000
|
|
|
INLET(COMPL)(DROP)(TY 1)(3 GRATE)
|
EA
|
3.000
|
$7,000.000
|
$14,794.650
|
$7,350.000
|
$12,000.000
|
|
|
INLET (COMPL)(MEDIAN)
|
EA
|
9.000
|
$8,000.000
|
$8,282.140
|
$11,550.000
|
$14,800.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$210,000.000
|
$200,831.200
|
$275,000.000
|
$210,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
6.000
|
$7,500.000
|
$8,450.660
|
$33,333.330
|
$41,000.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
300.000
|
$25.000
|
$25.420
|
$21.000
|
$15.550
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
300.000
|
$10.000
|
$12.870
|
$10.500
|
$11.200
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
600.000
|
$5.000
|
$3.920
|
$1.520
|
$1.550
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
600.000
|
$1.000
|
$0.930
|
$0.110
|
$0.850
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
600.000
|
$8.000
|
$7.860
|
$3.780
|
$4.500
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
600.000
|
$2.000
|
$2.190
|
$1.050
|
$0.600
|
|
|
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
|
LF
|
11,730.000
|
$16.000
|
$7.360
|
$10.500
|
$17.000
|
|
|
PORT CTB (STKPL)(SGL SLP)(TY 1)
|
LF
|
11,730.000
|
$16.000
|
$7.360
|
$10.500
|
$17.000
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (54 )
|
LF
|
2,845.000
|
$100.000
|
$101.450
|
$168.000
|
$158.000
|
|
|
PERM CTB (SGL SLOPE) (TY 3) (54 )
|
LF
|
80.000
|
$400.000
|
$346.570
|
$420.000
|
$411.000
|
|
|
PERM CTB (SGL SLOPE) (TY 4) (54 )
|
LF
|
70.000
|
$200.000
|
$346.570
|
$630.000
|
$426.000
|
|
|
PERM CTB (TRAN SSCB TO CTB) (MOD)
|
LF
|
20.000
|
$250.000
|
$249.530
|
$630.000
|
$426.000
|
|
|
PERM CTB (SGL SLOPE) (RETAINING WALL)
|
LF
|
20.000
|
$500.000
|
$623.830
|
$630.000
|
$899.000
|
|
|
PERM CTB (TRAN SSCB TO PARAPET)
|
LF
|
20.000
|
$300.000
|
$256.460
|
$630.000
|
$899.000
|
|
|
PERM CTB (SGL SLOPE) (TY 1) SPECIAL
|
LF
|
1,432.000
|
$200.000
|
$120.780
|
$168.000
|
$298.000
|
|
|
PERM CTB (SGL SLOPE) (TY 3) SPECIAL
|
LF
|
50.000
|
$400.000
|
$222.830
|
$420.000
|
$411.000
|
|
|
PERM CTB (SGL SLOPE) (TY 4) SPECIAL
|
LF
|
70.000
|
$200.000
|
$257.110
|
$630.000
|
$426.000
|
|
|
PERM CTB (SGL SLOPE)(TY 1)(TRANSITION)
|
LF
|
275.000
|
$250.000
|
$188.550
|
$630.000
|
$513.500
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
6,875.000
|
$5.000
|
$4.070
|
$6.300
|
$3.350
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
2.000
|
$1,000.000
|
$289.830
|
$630.000
|
$280.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
6.000
|
$500.000
|
$281.460
|
$630.000
|
$280.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
3.000
|
$12,000.000
|
$12,789.440
|
$15,750.000
|
$14,000.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
20.000
|
$2,500.000
|
$1,698.290
|
$4,200.000
|
$7,500.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
3.000
|
$2,000.000
|
$2,247.450
|
$1,155.000
|
$2,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
1.000
|
$40,000.000
|
$28,289.690
|
$21,000.000
|
$36,300.000
|
|
|
REMOVE RD IL ASM (SHOE-BASE)
|
EA
|
7.000
|
$600.000
|
$1,062.600
|
$575.000
|
$310.000
|
|
|
REMOVE RD IL ASM (TRANS-BASE)
|
EA
|
9.000
|
$1,100.000
|
$1,381.380
|
$915.000
|
$310.000
|
|
|
IN RD IL (TY SP) 48S-8-8 (400W EQ) LED
|
EA
|
7.000
|
$5,000.000
|
$8,072.480
|
$7,350.000
|
$5,000.000
|
|
|
IN RD IL (TY SP) 48S-10 (400W EQ) LED
|
EA
|
8.000
|
$4,000.000
|
$5,747.840
|
$7,350.000
|
$4,100.000
|
|
|
IN RD IL (TY SA) 50T-8-8 (400W EQ) LED
|
EA
|
2.000
|
$4,200.000
|
$7,307.410
|
$7,350.000
|
$4,500.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
3,710.000
|
$15.000
|
$14.600
|
$15.750
|
$12.150
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
3,865.000
|
$2.000
|
$2.400
|
$1.570
|
$1.350
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
7,730.000
|
$3.000
|
$2.600
|
$1.570
|
$1.450
|
|
|
GROUND BOX TY C (162911)W/APRON
|
EA
|
2.000
|
$1,500.000
|
$1,873.640
|
$1,365.000
|
$1,900.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
119.000
|
$30.000
|
$23.980
|
$18.580
|
$16.000
|
|
|
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
|
AC
|
0.300
|
$3,000.000
|
$15,530.290
|
$84,000.000
|
$8,000.000
|
|
|
STORM SEWER CLEANING (ALL SIZES)
|
LF
|
1,359.000
|
$50.000
|
$30.650
|
$63.000
|
$12.000
|
|
|
STORM SEWER CLEAN (BOX CULV)(ALL SIZES)
|
LF
|
172.000
|
$50.000
|
$61.300
|
$126.000
|
$12.000
|
|
|
DRAIN INLET CLEANING (BY LOCATION)
|
EA
|
11.000
|
$500.000
|
$674.340
|
$1,155.000
|
$600.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
236.000
|
$100.000
|
$147.300
|
$157.500
|
$170.000
|
|
|
TMA (STATIONARY)
|
EA
|
8.000
|
$10,000.000
|
$34,525.380
|
$7,500.000
|
$22,000.000
|
|
Totals: |
$2,140,580.000
|
$2,096,043.237
|
$2,810,025.150
|
$3,454,391.500
|