TARRANT SS 347 (0081-01-053)

Items: 57

County: TARRANT
Length: 0.0830 MILES
Highway: SS 347
District: FORT WORTH
Control Number: 0081-01-053
DBE Goal: 0.0%
Project: BR 2025(243)
Guaranty: $34,000.00
Time: 240 WORKING DAYS
Engineer's Estimate: $1,581,478.34
Date: 08/06/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263231
Type: REHABILITATE BRIDGE
Project ID: A00193283
Contract Type: FEDERAL
Project Description: PARTIAL TO FULL DECK REPLACEMENT AND, NEW RAILS.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 2 files available
Bidders (2)
E
Engineer's Estimate
$1,581,478.34
$2,868,396.85
Over/Under Est: 81.37% $1,286,918.51
$4,002,558.75
Over/Under Est: 153.09% $2,421,080.41
Amt Left: 39.54% $1,134,161.90

Bid Items & Bid Tabulations

57 Total 0 of 57
TARRANT  |  SS 347  |  FORT WORTH  |  0081-01-053  |  08/06/2026 1:00 PM CDT  |  $1,581,478.34  |  BR 2025(243)  |  REHAB BRIDGE  |  240 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
IBCTX, LLC
PREPARING ROW
STA 4.000 $3,878.000 $45,000.000 $25,000.000
REMOV CONC (APPR SLAB)
SY 167.000 $31.000 $45.500 $100.000
RMV (0"-4") TRT/UNTRT BASE & ASPH PAV
SY 167.000 $31.000 $11.500 $31.000
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 423.000 $8.500 $9.000 $31.000
SP MIXES SP-C SAC-A PG70-28
TON 105.000 $152.000 $310.000 $382.000
TACK COAT
GAL 122.000 $3.000 $17.000 $13.000
CL C CONC (RAIL FOUNDATION)
CY 5.000 $554.000 $982.000 $1,320.000
REINF CONC SLAB (HPC)
SF 9,373.000 $28.000 $38.800 $60.000
APPROACH SLAB (HPC)
CY 60.000 $780.000 $678.000 $1,200.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 609.000 $12.490 $9.200 $19.000
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 34.000 $184.000 $100.500 $184.000
RIPRAP (MOW STRIP)(4 IN)
CY 52.000 $722.000 $658.000 $790.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 79.000 $44.000 $75.000 $67.000
STR STEEL (MISCELLANEOUS BRIDGE)
LB 520.000 $11.750 $20.000 $82.000
STR STEEL (SHEAR CONNECTOR)
LB 2,897.000 $5.790 $6.500 $25.000
CLEAN & PAINT EXIST STR (SYSTEM III-B)
LS 2.000 $90,000.000 $300,000.000 $400,000.000
RAIL (TY SSTR)(MOD)
LF 482.800 $97.230 $120.000 $165.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 141.000 $218.000 $227.000 $300.000
REMOV STR (BRIDGE SLAB)
EA 1.000 $78,000.000 $410,000.000 $450,000.000
REMOV STR (ABUTMENT)
EA 2.000 $6,750.000 $2,400.000 $15,000.000
REMOVE STR (RAIL)
LF 400.000 $34.360 $44.000 $80.000
ADJUST STL SHOES
EA 7.000 $4,674.000 $17,000.000 $3,850.000
MOBILIZATION
LS 1.000 $185,000.000 $280,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $21,000.000 $25,000.000 $40,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 11.000 $10,000.000 $9,000.000 $30,000.000
TMA (STATIONARY)
DAY 278.000 $251.000 $287.000 $240.000
TMA (MOBILE OPERATION)
HR 48.000 $200.000 $62.000 $100.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 310.000 $5.500 $6.000 $20.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 310.000 $1.400 $1.250 $10.000
MTL W-BEAM GD FEN (TIM POST)
LF 950.000 $25.960 $23.000 $28.000
MTL BM GD FEN TRANS (NON - SYM)
EA 1.000 $592.370 $1,200.000 $1,400.000
MTL THRIE-BEAM GD FEN (TIM POST)
EA 3.000 $2,094.000 $1,800.000 $2,100.000
REMOVE METAL BEAM GUARD FENCE
LF 975.000 $2.650 $3.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $194.000 $150.000 $200.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $310.000 $200.000 $250.000
RM MTL BM GD FEN TRANS (T101)
EA 3.000 $199.000 $100.000 $150.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,177.000 $3,500.000 $4,200.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GF2
EA 9.000 $26.000 $25.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 2.000 $11.000 $20.000 $25.000
INSTL DEL ASSM (D-SY)SZ 1(YFLX)GF2
EA 4.000 $29.000 $25.000 $30.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB
EA 3.000 $21.000 $20.000 $25.000
RE PM TY II (W) 6" (BRK)
LF 4,935.000 $0.230 $1.500 $2.000
RE PM TY II (W) 6" (SLD)
LF 368.000 $0.160 $1.300 $2.000
RE PM TY II (W) 8" (SLD)
LF 112.000 $0.400 $3.000 $4.000
RE PM TY II (W) 12" (SLD)
LF 220.000 $1.940 $6.000 $7.000
RE PM TY II (Y) 6" (SLD)
LF 372.000 $0.160 $1.300 $2.000
PAVEMENT SLER 6"
LF 5,675.000 $0.200 $0.100 $0.250
PAVEMENT SLER 8"
LF 112.000 $0.270 $0.200 $0.250
PAVEMENT SLER 12"
LF 220.000 $1.750 $1.000 $2.000
PAV SURF PREP FOR MRK (6")
LF 5,675.000 $0.210 $1.150 $2.000
PAV SURF PREP FOR MRK (8")
LF 112.000 $0.270 $2.000 $3.000
PAV SURF PREP FOR MRK (12")
LF 220.000 $0.500 $3.000 $4.000
CONCRETE RAIL REPAIR (MISC)
LF 5.000 $365.000 $500.000 $738.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 28.000 $66.000 $75.000 $103.000
CNC CRACK REPAIR (DISCRETE)(SURF SEAL)
LF 52.000 $33.630 $75.000 $83.000
REP STL BRIDGE MBR (STRAIGHTEN MEMB)
EA 8.000 $4,266.000 $6,600.000 $15,000.000
REP STL BRIDGE MBR (WELD REPAIR)
EA 2.000 $7,195.000 $1,650.000 $3,500.000
Totals: $1,581,478.344 $2,868,396.850 $4,002,558.750
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $15,000.00