TARRANT US 287 (0172-09-047)

Items: 33

County: TARRANT
Length: 3.7200 MILES
Highway: US 287
District: FORT WORTH
Control Number: 0172-09-047
DBE Goal: 0.0%
Project: F 2B26(073)
Guaranty: $96,000.00
Time: 69 WORKING DAYS
Engineer's Estimate: $3,514,144.18
Date: 09/02/2026 1:00 PM CDT (17 days ago) Changed
Contract Number: 9263212
Type: RECONSTRUCT EXISTING ROADWAY
Project ID: A00220228
Contract Type: FEDERAL
Project Description: DIAMOND GRINDING AND PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$3,514,144.18
Over/Under Est: -25.35% -$890,877.31
Over/Under Est: -19.41% -$682,058.84
Amt Left: 7.96% $208,818.47
Over/Under Est: -11.19% -$393,377.39
Amt Left: 18.96% $497,499.92
Delta: -10.19% -$288,681.45
$3,858,768.13
Over/Under Est: 9.81% $344,623.95
Amt Left: 47.1% $1,235,501.26
Delta: -23.65% -$738,001.34
Over/Under Est: 20.3% $713,337.72
Amt Left: 61.15% $1,604,215.03
Delta: -9.56% -$368,713.77
Over/Under Est: 34.27% $1,204,393.57
Amt Left: 79.87% $2,095,270.88
Delta: -11.62% -$491,055.85
$5,400,452.91
Over/Under Est: 53.68% $1,886,308.73
Amt Left: 105.87% $2,777,186.04
Delta: -14.45% -$681,915.16

Bid Items & Bid Tabulations

33 Total 0 of 33
TARRANT  |  US 287  |  FORT WORTH  |  0172-09-047  |  09/02/2026 1:00 PM CDT  |  $3,514,144.18  |  F 2B26(073)  |  RECON EXIST ROADWAY  |  69 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
O. TREVINO CONSTRUCTION, LLC
FOUTSCO PAVING COMPANY, LLC
SELECT MAINTENANCE, L.L.C.
DIAMOND SURFACE, INC.
EMERY SAPP & SON'S INC.
ED BELL CONSTRUCTION COMPANY
CDM HOLDINGS
PLANE & TEXT ASPH CONC PAV(0" TO 2")
SY 9,788.000 $1.610 $10.100 $10.000 $8.500 $11.880 $11.000 $10.000 $11.000
FULL - DEPTH REPAIR CRCP (8")
CY 1,301.300 $1,000.000 $862.000 $500.000 $1,000.000 $1,386.250 $1,420.000 $1,450.000 $1,500.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 9,788.000 $9.900 $6.850 $18.000 $6.000 $6.570 $18.000 $7.000 $8.000
MOBILIZATION
LS 1.000 $408,755.650 $200,000.000 $280,000.000 $300,000.000 $755,115.000 $775,000.000 $1,000,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $40,000.000 $10,000.000 $118,000.000 $48,000.000 $3,750.000 $45,000.000 $73,500.000 $75,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $2,344.000 $7,750.000 $10,000.000 $32,000.000 $11,875.000 $8,500.000 $10,000.000 $25,100.000
TMA (STATIONARY)
DAY 3.000 $180.000 $750.000 $750.000 $3,850.000 $1,000.000 $300.000 $750.000 $300.000
TMA (MOBILE OPERATION)
DAY 101.000 $141.500 $490.000 $1.000 $500.000 $1,125.000 $320.000 $750.000 $300.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 10,512.000 $1.150 $1.000 $1.000 $0.300 $1.230 $1.100 $0.320 $0.300
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 41,672.000 $1.180 $0.920 $0.900 $0.200 $1.130 $1.100 $0.220 $0.200
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 39,246.000 $1.130 $0.920 $0.900 $0.200 $1.130 $1.100 $0.220 $0.200
RE PM TY III (W)(6")(SLD)
LF 41,672.000 $0.750 $0.670 $0.660 $0.900 $0.830 $0.900 $0.970 $0.900
RE PM TY III (W)(6")(BRK)
LF 10,512.000 $0.800 $0.740 $0.100 $0.900 $0.900 $0.900 $0.970 $0.900
RE PM TY III (W)(8")(SLD)
LF 10,327.000 $1.050 $1.120 $1.100 $1.150 $1.380 $1.250 $1.240 $1.150
RE PM TY III (W)(12")(SLD)
LF 2,557.000 $3.420 $4.350 $4.250 $4.000 $5.320 $5.000 $4.300 $4.000
RE PM TY III (W)(12")(DOT)
LF 529.000 $3.320 $2.050 $2.000 $4.000 $2.500 $2.500 $4.300 $4.000
RE PM TY III (Y)(6")(SLD)
LF 39,246.000 $0.740 $0.670 $0.660 $0.900 $0.830 $0.800 $0.970 $0.900
RE PM TY III (W)(ARROW)
EA 1.000 $226.970 $180.000 $176.000 $250.000 $220.000 $225.000 $268.750 $250.000
RE PM TY III (W)(WORD)
EA 3.000 $240.660 $213.000 $209.000 $275.000 $261.250 $260.000 $295.630 $275.000
PAVEMENT SLER 6"
LF 91,430.000 $0.150 $0.150 $0.150 $0.250 $0.190 $0.180 $0.270 $0.250
PAVEMENT SLER 8"
LF 10,327.000 $0.230 $0.220 $0.220 $0.350 $0.270 $0.250 $0.380 $0.350
PAVEMENT SLER 12"
LF 3,086.000 $0.570 $0.400 $0.390 $0.500 $0.490 $0.450 $0.540 $0.500
PAVEMENT SLER (ARROW)
EA 1.000 $36.120 $7.410 $7.250 $30.000 $9.060 $9.000 $32.250 $30.000
PAVEMENT SLER (WORD)
EA 3.000 $37.710 $9.250 $9.050 $40.000 $11.310 $11.000 $43.000 $40.000
REFL PAV MRKR TY II-C-R
EA 158.000 $4.140 $4.190 $4.100 $7.500 $5.130 $5.000 $8.060 $7.500
PAV SURF PREP FOR MRK (6")
LF 91,430.000 $0.060 $0.050 $0.050 $0.030 $0.060 $0.100 $0.030 $0.030
PAV SURF PREP FOR MRK (8")
LF 10,327.000 $0.110 $0.110 $0.110 $0.030 $0.140 $0.200 $0.030 $0.030
PAV SURF PREP FOR MRK (12")
LF 3,086.000 $0.280 $0.420 $0.410 $0.500 $0.520 $0.500 $0.540 $0.500
PAV SURF PREP FOR MRK (ARROW)
EA 1.000 $14.870 $20.450 $20.000 $20.000 $25.000 $25.000 $21.500 $20.000
PAV SURF PREP FOR MRK (WORD)
EA 3.000 $15.810 $27.610 $27.000 $30.000 $33.750 $35.000 $32.250 $30.000
SPALLING REPAIR (HYDRAULIC CEMENT)
CF 100.000 $305.000 $282.000 $350.000 $250.000 $381.250 $355.000 $250.000 $175.000
CONTINUOUS GRINDING-CONCRETE PAVEMENT
SY 106,444.000 $6.000 $4.650 $5.000 $4.550 $4.250 $4.500 $6.000 $10.000
CONTINUOUS GROOVING-CONCRETE PAVEMENT
SY 96,656.000 $6.000 $3.090 $2.700 $3.530 $2.350 $3.000 $3.750 $11.000
Totals: $3,514,144.180 $2,623,266.870 $2,832,085.340 $3,120,766.790 $3,858,768.125 $4,227,481.900 $4,718,537.750 $5,400,452.910
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $39,161.69
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $78,323.37
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $117,485.06
Total: $234,970.12