TARRANT SH 121 (0363-03-061)

Items: 64

County: TARRANT
Length: 3.7000 MILES (0.0306 MILES)
Highway: SH 121
District: FORT WORTH
Control Number: 0363-03-061
DBE Goal: 0.0%
Project: F 2026(985)
Guaranty: $58,000.00
Time: 40 WORKING DAYS
Engineer's Estimate: $2,924,978.47
Date: 08/06/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263225
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00220224
Contract Type: FEDERAL
Project Description: MILL & OVERLAY, BASE REPAIR, MBFG, CURB & GUTTER, PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 2 files available
Bidders (5)
E
Engineer's Estimate
$2,924,978.47
$3,202,525.20
Over/Under Est: 9.49% $277,546.73
Over/Under Est: 11.34% $331,812.54
Amt Left: 1.69% $54,265.81
Over/Under Est: 14.4% $421,252.33
Amt Left: 4.49% $143,705.60
Delta: -2.75% -$89,439.79
Over/Under Est: 16.26% $475,534.03
Amt Left: 6.18% $197,987.30
Delta: -1.62% -$54,281.70
$3,535,170.70
Over/Under Est: 20.86% $610,192.23
Amt Left: 10.39% $332,645.50
Delta: -3.96% -$134,658.20

Bid Items & Bid Tabulations

64 Total 0 of 64
TARRANT  |  SH 121  |  FORT WORTH  |  0363-03-061  |  08/06/2026 1:00 PM CDT  |  $2,924,978.47  |  F 2026(985)  |  REHAB EXIST ROADWAY  |  40 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOUTSCO PAVING COMPANY, LLC
AUSTIN BRIDGE & ROAD SERVICES, LP
TEXAS MATERIALS GROUP, INC.
PEACHTREE CONSTRUCTION, LTD.
JAGOE-PUBLIC COMPANY
PREPARING ROW
STA 10.000 $2,000.000 $300.000 $885.000 $1.000 $925.000 $950.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 2,500.000 $12.500 $7.000 $10.000 $13.000 $16.500 $18.000
BACKFILL (TY A OR B)
STA 25.000 $152.000 $150.000 $330.790 $400.000 $550.000 $1,570.000
ASPH (AC-20-5TR)
GAL 29,464.000 $3.680 $5.000 $3.530 $3.150 $4.200 $4.550
AGGR (TY-B, GR-4)(SAC-B)
CY 670.000 $155.000 $250.000 $330.000 $220.000 $155.000 $195.000
SP MIXES SP-C SAC-A PG70-28
TON 12,706.000 $126.000 $142.000 $137.600 $145.000 $140.000 $125.000
SP MIXES SP-D PG64-22 (LEVEL-UP)
TON 1,271.000 $115.000 $130.000 $100.500 $145.000 $145.000 $115.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 2,210.000 $72.000 $75.500 $81.550 $72.000 $88.000 $80.000
PLANE ASPH CONC PAV (2" TO 4 1/2")
SY 73,660.000 $2.400 $1.500 $2.000 $2.000 $3.600 $3.750
RIPRAP (MOW STRIP)(4 IN)
CY 75.000 $680.000 $650.000 $707.050 $700.000 $725.000 $1,200.000
ADJUSTING MANHOLES
EA 5.000 $2,250.000 $2,500.000 $2,500.000 $2,000.000 $2,100.000 $2,000.000
MOBILIZATION
LS 1.000 $200,000.000 $150,000.000 $358,247.010 $225,000.000 $225,000.000 $392,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $12,500.000 $50,000.000 $12,414.270 $30,000.000 $30,000.000 $40,250.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $5,000.000 $5,000.000 $3,288.600 $11,000.000 $7,500.000 $20,000.000
TMA (STATIONARY)
DAY 80.000 $108.000 $1.000 $1.050 $1.000 $90.000 $220.000
TMA (MOBILE OPERATION)
DAY 10.000 $175.000 $1.000 $1.050 $1.000 $225.000 $270.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,100.000 $4.000 $0.100 $3.750 $5.000 $4.750 $3.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,100.000 $2.000 $0.100 $1.100 $2.000 $1.950 $1.250
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 500.000 $4.000 $0.100 $5.500 $8.000 $4.550 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 500.000 $2.000 $0.100 $1.250 $2.000 $1.850 $1.250
CONC CURB & GUTTER (TY II)
LF 2,500.000 $45.000 $23.900 $23.900 $60.000 $37.000 $50.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,100.000 $22.000 $25.000 $25.000 $25.000 $26.500 $26.000
SHORT RADIUS (28")
LF 300.000 $34.000 $26.000 $26.000 $26.000 $27.500 $27.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,150.000 $1,200.000 $1,200.000 $1,200.000 $1,250.000 $1,200.000
REMOVE METAL BEAM GUARD FENCE
LF 1,400.000 $2.620 $2.500 $2.500 $2.500 $2.600 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $205.000 $150.000 $150.000 $150.000 $160.000 $150.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,000.000 $3,000.000 $3,000.000 $3,000.000 $3,200.000 $3,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $235.110 $250.000 $250.000 $250.000 $260.000 $260.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 4,200.000 $0.200 $0.300 $0.370 $0.300 $0.320 $0.400
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 21,700.000 $0.200 $0.260 $0.370 $0.260 $0.280 $0.400
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,950.000 $1.000 $0.480 $0.600 $0.480 $0.500 $0.600
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 50.000 $1.100 $2.000 $3.000 $2.000 $2.150 $3.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 480.000 $2.400 $4.000 $5.000 $4.000 $4.250 $5.000
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 4.000 $40.000 $55.000 $100.000 $55.000 $59.000 $100.000
WK ZN PAV MRK NON-REMOV (W)(DBL ARW)
EA 4.000 $100.000 $80.000 $125.000 $80.000 $85.000 $130.000
WK ZN PAV MRK NON-REMOV (W)(UTURN ARW)
EA 5.000 $95.000 $80.000 $125.000 $80.000 $85.000 $130.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 8.000 $40.000 $58.000 $100.000 $58.000 $62.000 $100.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 22,110.000 $0.200 $0.260 $0.370 $0.260 $0.280 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 524.000 $0.730 $1.000 $0.500 $3.000 $10.000 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,000.000 $0.950 $0.880 $0.910 $0.880 $0.950 $0.900
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 50.000 $3.370 $3.000 $3.650 $3.000 $3.200 $3.750
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 480.000 $6.660 $6.900 $6.550 $6.900 $7.400 $7.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 4.000 $159.000 $155.000 $127.000 $155.000 $165.000 $130.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 4.000 $241.610 $190.000 $181.000 $190.000 $200.000 $190.000
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 5.000 $300.000 $190.000 $185.000 $190.000 $200.000 $190.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 8.000 $175.000 $155.000 $153.000 $155.000 $165.000 $160.000
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
EA 4.000 $620.000 $1,100.000 $900.000 $1,100.000 $1,175.000 $900.000
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
EA 4.000 $780.000 $1,600.000 $900.000 $1,600.000 $1,700.000 $900.000
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 4,200.000 $0.500 $0.560 $0.700 $1.000 $0.600 $0.700
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 21,700.000 $0.550 $0.560 $0.700 $0.560 $0.600 $0.700
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 22,110.000 $0.480 $0.560 $0.700 $0.560 $0.600 $0.700
PAVEMENT SLER 6"
LF 48,010.000 $0.100 $0.200 $0.100 $0.200 $0.210 $0.100
PAVEMENT SLER 8"
LF 1,000.000 $0.120 $0.220 $0.150 $0.220 $0.240 $0.150
PAVEMENT SLER 12"
LF 50.000 $5.000 $0.500 $0.500 $0.500 $0.550 $0.500
PAVEMENT SLER 24"
LF 480.000 $0.400 $0.750 $0.700 $0.750 $0.800 $0.700
PAVEMENT SLER (ARROW)
EA 4.000 $28.000 $10.000 $15.000 $10.000 $10.500 $15.000
PAVEMENT SLER (WORD)
EA 8.000 $28.000 $10.000 $18.000 $10.000 $10.500 $19.000
PAVEMENT SLER (DBL ARROW)
EA 4.000 $62.000 $15.000 $15.000 $15.000 $16.000 $15.000
PAVEMENT SLER (UTURN ARROW)
EA 5.000 $35.000 $15.000 $18.000 $15.000 $16.000 $19.000
PAVEMENT SLER (ENTR GORE)
EA 4.000 $120.000 $200.000 $30.000 $200.000 $215.000 $31.000
PAVEMENT SLER (EXIT GORE)
EA 4.000 $140.000 $400.000 $30.000 $400.000 $425.000 $31.000
REFL PAV MRKR TY I-C
EA 55.000 $3.890 $4.000 $3.500 $4.000 $4.300 $3.500
REFL PAV MRKR TY II-A-A
EA 221.000 $5.000 $4.000 $3.500 $4.000 $4.300 $3.500
REFL PAV MRKR TY II-C-R
EA 230.000 $6.150 $4.000 $3.500 $4.000 $4.300 $3.500
Totals: $2,924,978.470 $3,202,525.200 $3,256,791.010 $3,346,230.800 $3,400,512.500 $3,535,170.700
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $25,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
Total: $55,000.00