TARRANT VARIOUS (0902-00-323)
Items: 79
County: TARRANT
Length: 0.0000 MILES
Highway: VARIOUS
District: FORT WORTH
Control Number: 0902-00-323
DBE Goal: 0.0%
Project: F 2026(894)
Guaranty: $28,000.00
Time: 158 WORKING DAYS
Engineer's Estimate: $1,389,510.90
Date: 08/06/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263224
Type: INSTALL TRAFFIC SIGNAL
Project ID: A00188243
Contract Type: FEDERAL
Project Description: NON-SITE SPECIFIC TRAFFIC SIGNAL INSTALLATION FY 26
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
THERESA POER
FEDERICO HERNANDEZ
MIKE FLAMING
AKM HAQUE
TARRANT VARIOUS (0902-00-323)
Project Name: N/A
Project: F 2026(894)
Engineer's Estimate: $1,389,510.90
Length: 0.0000 MILES
Project Class: TRAFFIC CONTROL DEVICES
Limits From: VARIOUS LOCATIONS
Limits To: DISTRICTWIDE FY 2026
Project Description: NON-SITE SPECIFIC TRAFFIC SIGNAL INSTALLATION FY 26
Bidders (9)
E
Engineer's Estimate
$1,389,510.90
1
Awarded
$1,054,946.50
Over/Under Est:
-24.08%
-$334,564.40
$1,138,059.40
Over/Under Est:
-18.1%
-$251,451.50
Amt Left:
7.88%
$83,112.90
$1,169,756.57
Over/Under Est:
-15.82%
-$219,754.33
Amt Left:
10.88%
$114,810.07
Delta:
-2.79%
-$31,697.17
$1,185,927.59
Over/Under Est:
-14.65%
-$203,583.31
Amt Left:
12.42%
$130,981.09
Delta:
-1.38%
-$16,171.02
$1,269,269.00
Over/Under Est:
-8.65%
-$120,241.90
Amt Left:
20.32%
$214,322.50
Delta:
-7.03%
-$83,341.41
$1,419,188.40
Over/Under Est:
2.14%
$29,677.50
Amt Left:
34.53%
$364,241.90
Delta:
-11.81%
-$149,919.40
$1,437,585.39
Over/Under Est:
3.46%
$48,074.49
Amt Left:
36.27%
$382,638.89
Delta:
-1.30%
-$18,396.99
$1,476,076.00
Over/Under Est:
6.23%
$86,565.10
Amt Left:
39.92%
$421,129.50
Delta:
-2.68%
-$38,490.61
$1,504,142.01
Over/Under Est:
8.25%
$114,631.11
Amt Left:
42.58%
$449,195.51
Delta:
-1.90%
-$28,066.01
Bid Items & Bid Tabulations
79
Total
0 of 79
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| MATERIAL FURNISHED BY THE STATE (PART) | $260,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,500.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,500.00 |
| Total: | $264,000.00 |