PREPARING ROW
|
STA
|
16.000
|
$4,000.000
|
$1,000.000
|
$33,750.000
|
$18,900.000
|
$4,550.000
|
|
|
REMOV CONC (DRIVEWAYS)
|
SY
|
831.000
|
$35.000
|
$40.000
|
$16.000
|
$23.000
|
$20.000
|
|
|
REMOV CONC (SIDEWALK, RAMP OR SUP)
|
SY
|
63.000
|
$50.000
|
$30.000
|
$14.000
|
$76.000
|
$26.000
|
|
|
REMOV CONC (CURB & GUTTER)
|
LF
|
1,302.000
|
$15.000
|
$10.000
|
$8.500
|
$16.000
|
$21.000
|
|
|
EXCAV (ROADWAY & CHANNEL)
|
CY
|
9,029.000
|
$45.000
|
$22.000
|
$40.000
|
$42.000
|
$42.000
|
|
|
EMBANK (FNL)(DC)(TY C2)
|
CY
|
1,493.000
|
$50.000
|
$18.000
|
$15.000
|
$63.000
|
$70.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
8,690.000
|
$15.000
|
$9.000
|
$6.850
|
$7.300
|
$10.000
|
|
|
BLOCK SODDING
|
SY
|
6,032.000
|
$25.000
|
$4.550
|
$7.250
|
$5.640
|
$5.000
|
|
|
ROLL SODDING
|
SY
|
2,658.000
|
$10.000
|
$4.550
|
$7.500
|
$5.860
|
$5.000
|
|
|
BROADCAST SEED (TEMP_WARM)
|
SY
|
4,345.000
|
$1.000
|
$0.250
|
$0.500
|
$0.530
|
$0.300
|
|
|
BROADCAST SEED (TEMP_COOL)
|
SY
|
4,345.000
|
$1.000
|
$0.260
|
$0.500
|
$0.530
|
$0.300
|
|
|
VEGETATIVE WATERING
|
TGL
|
305.000
|
$180.000
|
$65.000
|
$40.000
|
$53.250
|
$38.000
|
|
|
RDSIDE AMENITY (GATE)
|
EA
|
1.000
|
$5,000.000
|
$11,500.000
|
$3,500.000
|
$5,325.000
|
$2,700.000
|
|
|
PROOF ROLLING
|
HR
|
16.000
|
$150.000
|
$400.000
|
$125.000
|
$315.000
|
$60.000
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
2,815.000
|
$100.000
|
$80.000
|
$110.000
|
$88.000
|
$80.000
|
|
|
LIME (COM OR QK)(SLURRY)
|
TON
|
222.000
|
$400.000
|
$325.000
|
$315.000
|
$315.000
|
$330.000
|
|
|
LIME TRT (EXIST MATL)(8")
|
SY
|
13,246.000
|
$10.000
|
$6.000
|
$3.900
|
$3.150
|
$6.000
|
|
|
CEMENT TRT (NEW BASE)(8")
|
SY
|
5,000.000
|
$10.000
|
$6.000
|
$2.900
|
$5.250
|
$3.000
|
|
|
SALV, HAUL & STKPL RCL APH PV (2"-6")
|
SY
|
1,920.000
|
$15.000
|
$5.240
|
$5.500
|
$7.190
|
$7.000
|
|
|
SALV, HAUL & STKPL RCL APH PV (5 TO 9")
|
SY
|
5,940.000
|
$15.000
|
$8.000
|
$5.500
|
$8.790
|
$9.000
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
4,834.000
|
$12.000
|
$0.100
|
$5.500
|
$8.380
|
$4.250
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
2,020.000
|
$150.000
|
$125.000
|
$150.000
|
$127.320
|
$110.000
|
|
|
TACK COAT
|
GAL
|
2,303.000
|
$10.000
|
$0.100
|
$5.500
|
$5.330
|
$3.000
|
|
|
SP MIXES SP-C SAC-B PG70-28
|
TON
|
1,257.000
|
$225.000
|
$155.000
|
$175.000
|
$172.640
|
$130.000
|
|
|
CONC PVMT (CRCP) (9")
|
SY
|
492.000
|
$150.000
|
$132.360
|
$95.000
|
$161.000
|
$160.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
1,878.000
|
$30.000
|
$40.000
|
$2.000
|
$25.000
|
$12.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
8,474.000
|
$50.000
|
$35.000
|
$0.100
|
$50.000
|
$36.000
|
|
|
RETAINING WALL (SPREAD FOOTING)
|
SF
|
6,209.000
|
$125.000
|
$77.100
|
$90.000
|
$90.000
|
$135.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
12.000
|
$2,000.000
|
$522.420
|
$650.000
|
$1,155.000
|
$500.000
|
|
|
RIPRAP (STONE COMMON)(GROUT)(24 IN)
|
CY
|
447.000
|
$200.000
|
$232.950
|
$175.000
|
$630.000
|
$400.000
|
|
|
RAIL (TY C223)
|
LF
|
422.000
|
$200.000
|
$89.600
|
$125.000
|
$205.000
|
$220.000
|
|
|
CONC BOX CULV (7 FT X 6 FT)
|
LF
|
400.000
|
$1,300.000
|
$515.700
|
$1,200.000
|
$915.000
|
$1,100.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
1,577.000
|
$175.000
|
$165.000
|
$92.000
|
$150.000
|
$180.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
418.000
|
$200.000
|
$210.000
|
$125.000
|
$175.000
|
$290.000
|
|
|
INLET (COMPL)(CO)(10 FT)(FTW)
|
EA
|
5.000
|
$12,000.000
|
$4,909.400
|
$11,350.000
|
$11,000.000
|
$12,000.000
|
|
|
INLET (COMPL)(CO)(15 FT)(FTW)
|
EA
|
4.000
|
$15,000.000
|
$6,272.100
|
$14,750.000
|
$13,000.000
|
$16,000.000
|
|
|
INLET (COMPL)( CO)(20 FT)(FTW)
|
EA
|
4.000
|
$18,000.000
|
$7,637.600
|
$18,075.000
|
$15,000.000
|
$16,000.000
|
|
|
INLET (COMPL)(COB)(20 FT)(FTW)
|
EA
|
1.000
|
$30,000.000
|
$10,293.900
|
$21,050.000
|
$20,000.000
|
$29,000.000
|
|
|
ADJUSTING MANHOLES
|
EA
|
4.000
|
$1,450.000
|
$800.000
|
$1,280.000
|
$4,500.000
|
$3,600.000
|
|
|
REMOV STR (INLET)
|
EA
|
1.000
|
$1,200.000
|
$1,500.000
|
$600.000
|
$2,000.000
|
$4,800.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
2.000
|
$1,400.000
|
$1,800.000
|
$1,400.000
|
$5,000.000
|
$7,000.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
63.000
|
$100.000
|
$87.000
|
$70.000
|
$300.000
|
$600.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$700,000.000
|
$305,000.000
|
$540,000.000
|
$595,000.000
|
$684,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$15,000.000
|
$100,000.000
|
$35,825.000
|
$21,000.000
|
$36,000.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$8,500.000
|
$5,000.000
|
$12,000.000
|
$20,000.000
|
$15,750.000
|
|
|
TMA (STATIONARY)
|
DAY
|
94.000
|
$225.000
|
$1.000
|
$400.000
|
$210.000
|
$260.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
122.000
|
$60.000
|
$40.000
|
$44.000
|
$61.130
|
$46.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
122.000
|
$25.000
|
$14.000
|
$18.000
|
$26.630
|
$19.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
342.000
|
$40.000
|
$33.500
|
$44.000
|
$54.210
|
$4.250
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
342.000
|
$15.000
|
$9.000
|
$13.000
|
$23.430
|
$14.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
3,762.000
|
$5.000
|
$0.100
|
$5.000
|
$3.040
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
3,762.000
|
$2.000
|
$0.100
|
$1.000
|
$1.380
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
285.000
|
$10.000
|
$4.500
|
$6.000
|
$4.260
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
285.000
|
$3.000
|
$1.100
|
$1.000
|
$2.080
|
$1.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
642.000
|
$100.000
|
$85.000
|
$120.000
|
$111.000
|
$100.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
180.000
|
$50.000
|
$70.000
|
$150.000
|
$40.000
|
$70.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$50.000
|
$70.000
|
$150.000
|
$120.000
|
$70.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
180.000
|
$10.000
|
$50.000
|
$12.000
|
$30.000
|
$50.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$10.000
|
$50.000
|
$20.000
|
$90.000
|
$60.000
|
|
|
CONC CURB (MONO) (TY II)
|
LF
|
286.000
|
$15.000
|
$15.930
|
$13.000
|
$10.500
|
$2.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
3,829.000
|
$70.000
|
$26.250
|
$27.000
|
$42.000
|
$26.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
929.000
|
$135.000
|
$93.240
|
$96.000
|
$147.000
|
$120.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
3,001.000
|
$100.000
|
$50.840
|
$55.000
|
$77.000
|
$70.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
2.000
|
$4,600.000
|
$2,500.000
|
$1,750.000
|
$2,500.000
|
$3,700.000
|
|
|
CURB RAMPS (TY 3)
|
EA
|
3.000
|
$4,000.000
|
$2,500.000
|
$1,350.000
|
$2,500.000
|
$3,700.000
|
|
|
CURB RAMPS (TY 22)
|
EA
|
1.000
|
$7,000.000
|
$3,500.000
|
$3,710.000
|
$4,000.000
|
$5,000.000
|
|
|
CONC SIDEWALKS (SPECIAL) (TYPE A)
|
SY
|
57.000
|
$300.000
|
$129.630
|
$135.000
|
$275.000
|
$320.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
238.000
|
$5.000
|
$5.000
|
$5.000
|
$29.350
|
$6.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
2.000
|
$200.000
|
$300.000
|
$300.000
|
$1,467.310
|
$360.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
21.000
|
$1,000.000
|
$645.000
|
$650.000
|
$692.250
|
$700.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$1,000.000
|
$735.000
|
$725.000
|
$772.130
|
$700.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
1.000
|
$1,200.000
|
$1,225.000
|
$1,130.000
|
$1,203.450
|
$1,200.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$1,300.000
|
$1,299.000
|
$1,130.000
|
$1,203.450
|
$1,300.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
4.000
|
$100.000
|
$75.000
|
$60.000
|
$63.900
|
$80.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
3,087.000
|
$2.000
|
$0.500
|
$0.450
|
$0.800
|
$0.400
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
3,358.000
|
$2.000
|
$0.500
|
$0.450
|
$0.800
|
$0.400
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
7,105.000
|
$6.000
|
$3.750
|
$3.550
|
$5.060
|
$6.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
4,076.000
|
$2.000
|
$0.880
|
$1.350
|
$1.540
|
$0.900
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
37.000
|
$15.000
|
$5.760
|
$7.000
|
$5.330
|
$6.000
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
3,765.000
|
$2.000
|
$0.880
|
$1.350
|
$1.540
|
$0.900
|
|
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
|
LF
|
57.000
|
$3.000
|
$2.000
|
$2.450
|
$1.070
|
$1.750
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
1,098.000
|
$2.000
|
$1.000
|
$1.450
|
$1.070
|
$0.900
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
403.000
|
$10.000
|
$6.890
|
$6.950
|
$7.190
|
$7.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
16.000
|
$160.000
|
$155.000
|
$181.000
|
$149.100
|
$140.000
|
|
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
|
EA
|
2.000
|
$250.000
|
$199.000
|
$362.000
|
$239.630
|
$190.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
7.000
|
$250.000
|
$170.000
|
$210.000
|
$159.750
|
$160.000
|
|
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
|
EA
|
29.000
|
$85.000
|
$38.000
|
$25.500
|
$58.580
|
$60.000
|
|
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
|
LF
|
383.000
|
$2.000
|
$1.000
|
$0.850
|
$0.850
|
$0.700
|
|
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
|
LF
|
4,183.000
|
$2.000
|
$0.870
|
$0.680
|
$0.800
|
$0.700
|
|
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
|
LF
|
277.000
|
$2.000
|
$1.000
|
$0.850
|
$0.850
|
$0.700
|
|
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
|
LF
|
5,183.000
|
$2.000
|
$0.870
|
$0.680
|
$0.800
|
$0.700
|
|
REFL PAV MRKR TY I-C
|
EA
|
66.000
|
$5.000
|
$5.000
|
$3.550
|
$15.980
|
$5.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
7.000
|
$5.000
|
$5.000
|
$5.000
|
$26.630
|
$5.000
|
|
|
ELIM EXT PM & MRKS (6")
|
LF
|
836.000
|
$2.000
|
$0.750
|
$0.650
|
$2.130
|
$0.500
|
|
|
ELIM EXT PM & MRKS (24")
|
LF
|
98.000
|
$2.000
|
$3.900
|
$3.550
|
$3.200
|
$2.750
|
|
|
ELIM EXT PM & MRKS (ARROW)
|
EA
|
2.000
|
$2.000
|
$55.000
|
$65.000
|
$53.250
|
$39.000
|
|
|
ELIM EXT PM & MRKS (DBL ARROW)
|
EA
|
1.000
|
$2.000
|
$75.000
|
$125.000
|
$63.900
|
$50.000
|
|
|
ELIM EXT PM & MRKS (WORD)
|
EA
|
1.000
|
$2.000
|
$55.000
|
$65.000
|
$58.580
|
$47.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
1,360.000
|
$2.000
|
$0.250
|
$0.060
|
$0.320
|
$0.020
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
355.000
|
$2.000
|
$0.330
|
$0.080
|
$0.640
|
$0.060
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
70.000
|
$5.000
|
$55.000
|
$0.240
|
$1.070
|
$0.500
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
2.000
|
$2.000
|
$15.000
|
$15.000
|
$21.300
|
$12.000
|
|
|
PAV SURF PREP FOR MRK (DBL ARROW)
|
EA
|
1.000
|
$50.000
|
$20.000
|
$30.000
|
$31.950
|
$17.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
1.000
|
$50.000
|
$15.000
|
$15.000
|
$26.630
|
$13.000
|
|
|
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
|
EA
|
2.000
|
$1,200.000
|
$225.000
|
$1,750.000
|
$1,597.500
|
$230.000
|
|
Totals: |
$6,914,803.000
|
$5,160,281.790
|
$5,474,780.530
|
$6,111,371.500
|
$6,166,871.050
|