PREPARING ROW
|
AC
|
0.250
|
$55,000.000
|
$50,000.000
|
$20,000.000
|
$200,000.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
224.000
|
$35.000
|
$25.000
|
$30.000
|
$90.000
|
|
|
REMOVING CONC (SIDEWALKS)
|
SY
|
120.000
|
$20.000
|
$25.000
|
$30.000
|
$90.000
|
|
|
REMOVING STAB BASE & ASPH PAV (7"-12")
|
SY
|
1,162.000
|
$15.000
|
$13.500
|
$20.000
|
$15.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
307.200
|
$15.000
|
$35.000
|
$40.000
|
$40.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
114.800
|
$25.000
|
$35.000
|
$50.000
|
$60.000
|
|
|
BROADCAST SEED (PERM) (URBAN) (CLAY)
|
SY
|
1,184.000
|
$1.250
|
$2.000
|
$5.000
|
$4.000
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
238.000
|
$80.000
|
$100.000
|
$130.000
|
$100.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
132.000
|
$20.000
|
$15.000
|
$30.000
|
$40.000
|
|
|
CURB (TYPE II)
|
LF
|
10.000
|
$40.000
|
$40.000
|
$50.000
|
$500.000
|
|
|
CEM STABIL BKFL
|
CY
|
42.000
|
$320.000
|
$250.000
|
$250.000
|
$350.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
660.000
|
$35.000
|
$120.000
|
$45.000
|
$5.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
380.000
|
$250.000
|
$210.000
|
$300.000
|
$250.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
23.800
|
$2,000.000
|
$1,650.000
|
$2,000.000
|
$2,000.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
18.800
|
$2,000.000
|
$1,900.000
|
$2,000.000
|
$2,200.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
4.500
|
$2,300.000
|
$1,800.000
|
$2,000.000
|
$3,000.000
|
|
|
REINF CONC SLAB (SLAB BEAM)(HPC)
|
SF
|
3,600.000
|
$30.000
|
$30.500
|
$50.000
|
$60.000
|
|
|
BRIDGE SIDEWALK (HPC)
|
SF
|
1,100.000
|
$25.000
|
$28.000
|
$35.000
|
$50.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
76.300
|
$1,030.000
|
$1,050.000
|
$1,500.000
|
$1,200.000
|
|
|
PRESTR CONC SLAB BEAM (5SB12)
|
LF
|
689.390
|
$275.000
|
$264.750
|
$310.000
|
$385.000
|
|
|
SILICONE RESIN PAINT FINISH
|
SF
|
410.000
|
$12.000
|
$18.000
|
$30.000
|
$10.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
3.000
|
$250.000
|
$500.000
|
$250.000
|
$500.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
578.200
|
$175.000
|
$125.000
|
$300.000
|
$220.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
6.000
|
$700.000
|
$750.000
|
$625.000
|
$800.000
|
|
|
STR STEEL (MISC NON - BRIDGE)
|
LB
|
283.000
|
$20.000
|
$112.000
|
$35.000
|
$45.000
|
|
|
RAIL (TY T223)(HPC)
|
LF
|
112.000
|
$205.000
|
$185.000
|
$200.000
|
$200.000
|
|
|
RAIL (TY C223)(HPC)
|
LF
|
112.000
|
$225.000
|
$185.000
|
$200.000
|
$200.000
|
|
|
TYPE A JOINT
|
LF
|
74.000
|
$100.000
|
$32.000
|
$150.000
|
$75.000
|
|
|
RC PIPE (CL IV)(18 IN)
|
LF
|
50.000
|
$125.000
|
$250.000
|
$110.000
|
$150.000
|
|
|
SET (TY II) (18 IN) (RCP) (3: 1) (P)
|
EA
|
2.000
|
$1,500.000
|
$3,000.000
|
$1,300.000
|
$5,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
150.000
|
$30.000
|
$35.000
|
$20.000
|
$30.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
1.000
|
$50,000.000
|
$135,000.000
|
$40,000.000
|
$60,000.000
|
|
|
REMOV STR (PIPE GATE)
|
LF
|
26.000
|
$100.000
|
$35.000
|
$50.000
|
$40.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$105,000.000
|
$100,000.000
|
$170,000.000
|
$130,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$10,000.000
|
$6,000.000
|
$4,000.000
|
$14,000.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
120.000
|
$30.000
|
$80.000
|
$40.000
|
$1.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
120.000
|
$10.000
|
$25.000
|
$20.000
|
$1.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
110.000
|
$5.000
|
$10.000
|
$7.000
|
$1.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
110.000
|
$2.000
|
$2.000
|
$2.000
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
372.000
|
$12.000
|
$10.000
|
$10.000
|
$5.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
372.000
|
$2.000
|
$2.000
|
$2.000
|
$1.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
110.000
|
$85.000
|
$98.000
|
$100.000
|
$150.000
|
|
|
CURB RAMPS (SPECIAL)
|
SY
|
8.000
|
$560.000
|
$325.000
|
$400.000
|
$750.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
25.000
|
$35.000
|
$44.000
|
$45.000
|
$40.000
|
|
|
MTL BEAM GD FEN TRANS (TL2)
|
EA
|
1.000
|
$1,500.000
|
$1,650.000
|
$1,750.000
|
$3,000.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
1.000
|
$4,000.000
|
$6,050.000
|
$4,000.000
|
$4,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
1.000
|
$30,000.000
|
$33,000.000
|
$30,000.000
|
$30,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$1,025.000
|
$962.000
|
$1,050.000
|
$1,500.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
2.000
|
$600.000
|
$500.000
|
$600.000
|
$1,500.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
4.000
|
$600.000
|
$640.000
|
$650.000
|
$2,000.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
2.000
|
$750.000
|
$770.000
|
$800.000
|
$1,000.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
2.000
|
$130.000
|
$100.000
|
$200.000
|
$200.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
|
EA
|
9.000
|
$77.000
|
$46.000
|
$50.000
|
$50.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI)
|
EA
|
2.000
|
$51.000
|
$47.000
|
$65.000
|
$50.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
9.000
|
$45.000
|
$50.000
|
$60.000
|
$50.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
1.000
|
$86.000
|
$53.000
|
$60.000
|
$50.000
|
|
|
INSTL OM ASSM (OM-3L)(TWT)GND
|
EA
|
1.000
|
$350.000
|
$620.000
|
$700.000
|
$500.000
|
|
|
INSTL OM ASSM (OM-3R)(TWT)GND
|
EA
|
1.000
|
$350.000
|
$620.000
|
$700.000
|
$500.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
682.000
|
$1.000
|
$1.000
|
$4.000
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
718.000
|
$1.000
|
$4.700
|
$9.000
|
$3.000
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
804.000
|
$1.000
|
$4.700
|
$9.000
|
$3.000
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
60.000
|
$25.000
|
$22.000
|
$22.000
|
$20.000
|
|
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
|
EA
|
10.000
|
$75.000
|
$44.000
|
$170.000
|
$40.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
9.000
|
$5.000
|
$17.000
|
$45.000
|
$20.000
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
72.000
|
$200.000
|
$250.000
|
$250.000
|
$400.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
1.000
|
$400.000
|
$1,000.000
|
$2,000.000
|
$200.000
|
|
Totals: |
$1,216,522.250
|
$1,316,532.402
|
$1,517,493.900
|
$1,643,216.150
|