TOM GREEN SH0208 (6501-05-001)

Items: 37

County: TOM GREEN
Length: 0.0100 MILES
Highway: SH0208
District: SAN ANGELO
Control Number: 6501-05-001
DBE Goal: 0.0%
Project: BPM - A00221262
Guaranty: $26,000.00
Time: 90 WORKING DAYS
Engineer's Estimate: $1,329,347.00
Date: 09/03/2026 1:00 PM CDT (16 days ago) Changed
Contract Number: 9264202
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00221262
Project Description: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 3 files available
Bidders (11)
E
Engineer's Estimate
$1,329,347.00
Over/Under Est: 4.06% $54,036.00
Over/Under Est: 4.18% $55,571.50
Amt Left: 0.11% $1,535.50
$1,461,026.30
Over/Under Est: 9.91% $131,679.30
Amt Left: 5.61% $77,643.30
Delta: -5.50% -$76,107.80
$1,478,786.00
Over/Under Est: 11.24% $149,439.00
Amt Left: 6.9% $95,403.00
Delta: -1.22% -$17,759.70
Over/Under Est: 15.16% $201,516.90
Amt Left: 10.66% $147,480.90
Delta: -3.52% -$52,077.90
Over/Under Est: 17.4% $231,257.00
Amt Left: 12.81% $177,221.00
Delta: -1.94% -$29,740.10
Over/Under Est: 17.64% $234,526.00
Amt Left: 13.05% $180,490.00
Delta: -0.21% -$3,269.00
Over/Under Est: 24.7% $328,386.00
Amt Left: 19.83% $274,350.00
Delta: -6.00% -$93,860.00
Over/Under Est: 29.39% $390,680.50
Amt Left: 24.33% $336,644.50
Delta: -3.76% -$62,294.50
Over/Under Est: 33.97% $451,608.00
Amt Left: 28.74% $397,572.00
Delta: -3.54% -$60,927.50
$1,790,802.60
Over/Under Est: 34.71% $461,455.60
Amt Left: 29.45% $407,419.60
Delta: -0.55% -$9,847.60

Bid Items & Bid Tabulations

37 Total 0 of 37
TOM GREEN  |  SH0208  |  SAN ANGELO  |  6501-05-001  |  09/03/2026 1:00 PM CDT  |  $1,329,347.00  |  BPM - A00221262  |  BRIDGE PREVENT MAINT  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE TRUESDELL CORPORATION
STRUCTURAL INTEGRITY GROUP LLC
MPB, INC.
RELMCO, INC.
GIBSON & ASSOCIATES, INC.
ROY JORGENSEN ASSOCIATES, INC.
BLACKSMITH VENTURES LLC
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
RAGLE CONSTRUCTION, INC.
CROSS PLUS CONSTRUCTION, LLC
TI-ZACK CONCRETE, LLC
EMBANK (FNL)(OC)(TY B)
CY 332.000 $50.000 $125.000 $70.000 $85.000 $40.000 $68.200 $25.000 $110.000 $75.000 $100.000 $55.000 $28.000
FLOWABLE BACKFILL
CY 10.000 $350.000 $555.000 $450.000 $310.000 $220.000 $600.000 $200.000 $700.000 $681.000 $750.000 $1,100.000 $870.240
PENETRATING CONCRETE SURFACE TREATMENT
SY 2,974.000 $15.000 $18.000 $10.000 $11.200 $10.500 $11.000 $18.000 $12.000 $36.000 $11.000 $11.000 $61.600
CONC STR REPAIR (EPOXY MORTAR)
SF 40.000 $150.000 $185.000 $500.000 $135.000 $225.000 $148.500 $200.000 $150.000 $167.000 $160.000 $330.000 $275.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 195.000 $130.000 $165.000 $210.000 $125.000 $195.000 $176.000 $180.000 $240.000 $182.000 $175.000 $330.000 $275.000
CONC STR REPAIR (STANDARD)
SF 45.000 $138.000 $155.000 $335.000 $125.000 $205.000 $141.900 $150.000 $200.000 $138.000 $180.000 $550.000 $246.400
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 203.000 $150.000 $201.000 $259.000 $275.000 $215.000 $275.000 $200.000 $280.000 $229.000 $202.000 $330.000 $140.000
RIPRAP (STONE COMMON)(DRY)(24 IN)
CY 96.000 $180.000 $215.000 $240.000 $335.000 $215.000 $286.000 $275.000 $320.000 $250.000 $200.000 $385.000 $408.800
CLEANING & SEALING EXISTING JOINT (SEJ)
LF 943.000 $45.000 $40.000 $63.000 $56.000 $38.000 $88.000 $70.000 $45.000 $59.000 $60.000 $165.000 $106.400
MULTI-LAYER POLYMER OVERLAY
SY 13,010.000 $40.000 $28.000 $30.500 $38.750 $41.000 $31.000 $45.000 $40.000 $42.000 $32.750 $44.000 $61.600
CLEAN & PAINT EXIST STR (SYSTEM II)
LS 1.000 $309,000.000 $355,000.000 $353,280.000 $371,000.000 $369,894.000 $369,600.000 $388,608.000 $345,000.000 $185,337.000 $353,280.000 $412,500.000 $106,400.000
PIPE (GALV) (4 IN X 5IN)
LF 32.000 $140.000 $100.000 $325.000 $380.000 $150.000 $550.000 $100.000 $450.000 $272.000 $250.000 $165.000 $582.400
SHOT BLASTING
SY 13,010.000 $5.000 $3.000 $3.000 $5.000 $3.000 $3.300 $4.000 $2.000 $18.000 $2.500 $5.500 $6.720
MOBILIZATION
LS 1.000 $60,000.000 $179,204.000 $110,500.000 $75,000.000 $125,000.000 $210,000.000 $80,000.000 $150,000.000 $165,000.000 $170,000.000 $55,000.000 $61,600.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $8,000.000 $6,000.000 $1.000 $3,000.000 $3,500.000 $7,250.000 $5,000.000 $7,000.000 $11,008.000 $52,000.000 $5,500.000 $8,400.000
TMA (STATIONARY)
DAY 50.000 $300.000 $300.000 $250.000 $100.000 $250.000 $350.000 $1.000 $200.000 $591.000 $1,750.000 $550.000 $246.400
TMA (MOBILE OPERATION)
DAY 2.000 $250.000 $2,100.000 $250.000 $100.000 $250.000 $500.000 $1.000 $2,000.000 $977.000 $630.000 $550.000 $5,600.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 500.000 $1.000 $3.200 $3.000 $3.150 $3.300 $3.300 $3.900 $5.000 $6.000 $3.000 $11.000 $3.360
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 380.000 $3.500 $5.300 $5.000 $5.250 $5.500 $5.500 $6.500 $8.000 $6.000 $5.000 $11.000 $5.600
RE PM TY II (W) 6" (BRK)
LF 840.000 $0.300 $2.150 $2.000 $2.100 $2.200 $2.200 $2.600 $3.000 $2.000 $2.000 $2.200 $2.240
RE PM TY II (W) 6" (SLD)
LF 1,500.000 $0.300 $2.150 $2.000 $2.100 $2.200 $2.200 $2.600 $3.000 $2.000 $2.000 $2.200 $2.240
RE PM TY II (W) 8" (SLD)
LF 500.000 $0.500 $2.150 $2.000 $2.100 $2.200 $2.200 $2.600 $4.000 $2.500 $2.000 $8.250 $2.240
RE PM TY II (W) 12" (SLD)
LF 380.000 $1.750 $3.200 $3.000 $3.150 $3.200 $3.300 $3.900 $8.000 $4.000 $3.000 $11.000 $3.360
RE PM TY II (Y) 6" (SLD)
LF 2,900.000 $0.300 $2.150 $2.000 $2.100 $2.200 $2.200 $2.600 $3.000 $2.000 $2.000 $2.200 $2.240
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 840.000 $0.500 $3.200 $3.000 $3.150 $3.300 $3.300 $3.900 $3.000 $2.000 $3.000 $2.200 $3.360
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 1,500.000 $0.500 $3.200 $3.000 $3.150 $3.300 $3.300 $3.900 $3.000 $2.000 $3.000 $2.200 $3.360
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 2,900.000 $0.500 $3.200 $3.000 $3.150 $3.300 $3.300 $3.900 $3.000 $2.000 $3.000 $2.200 $3.360
REFL PAV MRKR TY I-C
EA 20.000 $3.500 $16.000 $15.000 $15.750 $16.500 $16.500 $19.500 $20.000 $50.000 $15.000 $16.500 $16.800
REFL PAV MRKR TY II-A-A
EA 40.000 $3.500 $16.000 $15.000 $15.750 $16.500 $16.500 $19.500 $20.000 $35.000 $15.000 $33.000 $16.800
REFL PAV MRKR TY II-C-R
EA 20.000 $3.500 $16.000 $15.000 $15.750 $16.500 $16.500 $19.500 $20.000 $50.000 $15.000 $33.000 $16.800
ELIM EXT PM & MRKS (4")
LF 600.000 $0.500 $3.200 $3.000 $3.150 $3.300 $3.300 $3.900 $5.000 $3.000 $3.000 $5.500 $3.360
DRIFTWOOD REMOVAL
CY 27.000 $75.000 $110.000 $240.000 $60.000 $300.000 $530.000 $100.000 $180.000 $168.000 $150.000 $550.000 $560.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 0.250 $1,800.000 $16,500.000 $1,150.000 $2,000.000 $40,000.000 $10,000.000 $10,000.000 $25,000.000 $8,964.000 $15,000.000 $22,000.000 $22,400.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 140.000 $25.000 $45.000 $30.000 $30.000 $50.000 $42.900 $50.000 $40.000 $23.000 $20.000 $27.500 $140.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 214.000 $60.000 $55.000 $90.000 $65.000 $50.000 $66.000 $75.000 $80.000 $42.000 $30.000 $82.500 $84.000
STEEL BRIDGE ZONE PAINTING REF STR #1
EA 1.000 $75,000.000 $75,000.000 $72,000.000 $76,000.000 $75,600.000 $71,500.000 $85,000.000 $70,000.000 $50,505.000 $72,000.000 $88,000.000 $84,000.000
STONE MASONRY REPAIR
SF 470.000 $45.000 $21.000 $120.000 $85.000 $50.000 $25.000 $45.000 $80.000 $31.000 $40.000 $16.500 $50.400
Totals: $1,329,347.000 $1,383,383.000 $1,384,918.500 $1,461,026.300 $1,478,786.000 $1,530,863.900 $1,560,604.000 $1,563,873.000 $1,657,733.000 $1,720,027.500 $1,780,955.000 $1,790,802.600