EXCAVATION (ROADWAY AND CHANNEL)
|
CY
|
42.000
|
$50.000
|
$45.000
|
$28.500
|
$73.000
|
$100.000
|
$134.970
|
|
|
BACKFILL (TY A)
|
STA
|
41.000
|
$200.000
|
$175.000
|
$210.000
|
$200.000
|
$100.000
|
$486.180
|
|
|
BACKFILL (TY B)
|
STA
|
4.000
|
$300.000
|
$100.000
|
$500.000
|
$700.000
|
$100.000
|
$316.140
|
|
|
FURNISHING AND PLACING TOPSOIL (6")
|
SY
|
6,188.000
|
$10.000
|
$5.000
|
$1.300
|
$4.150
|
$3.000
|
$7.530
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
6,188.000
|
$3.200
|
$0.250
|
$0.500
|
$0.250
|
$0.250
|
$0.250
|
|
|
VEGETATIVE WATERING
|
MG
|
0.200
|
$500.000
|
$3,000.000
|
$900.000
|
$13,000.000
|
$50.000
|
$1,108.890
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
6,188.000
|
$1.400
|
$1.250
|
$1.400
|
$1.200
|
$1.200
|
$1.200
|
|
|
D-GR HMA TY-D SAC-B PG70-22
|
TON
|
239.000
|
$103.500
|
$90.000
|
$103.000
|
$98.000
|
$160.000
|
$89.130
|
|
|
TOM (ASPHALT) PG 76-22
|
TON
|
301.000
|
$87.500
|
$87.000
|
$90.250
|
$98.000
|
$82.000
|
$120.630
|
|
|
TOM - C (AGGREGATE) SAC - B
|
TON
|
4,561.000
|
$87.500
|
$87.000
|
$90.250
|
$98.000
|
$82.000
|
$120.630
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
|
SY
|
7,889.000
|
$42.500
|
$36.000
|
$37.000
|
$39.000
|
$36.000
|
$44.300
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 1")
|
SY
|
86,064.000
|
$1.000
|
$0.350
|
$0.500
|
$1.000
|
$0.960
|
$2.560
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
4,461.000
|
$3.000
|
$1.250
|
$0.500
|
$2.750
|
$6.850
|
$2.560
|
|
|
CUT & RESTORING PAV
|
SY
|
153.000
|
$100.000
|
$85.000
|
$109.000
|
$85.000
|
$150.000
|
$142.510
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
28.000
|
$475.000
|
$450.000
|
$507.000
|
$675.000
|
$439.000
|
$460.890
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
82.000
|
$474.000
|
$425.000
|
$470.000
|
$447.000
|
$447.000
|
$439.890
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
398.000
|
$56.000
|
$125.000
|
$89.000
|
$83.000
|
$75.000
|
$125.880
|
|
|
RC PIPE (CL III)(21 IN)
|
LF
|
40.000
|
$80.000
|
$70.000
|
$92.000
|
$120.000
|
$80.000
|
$72.440
|
|
|
SET (REPLACE PIPE RUNNER ASSEMBLY)
|
EA
|
4.000
|
$2,971.230
|
$1,500.000
|
$1,650.000
|
$1,400.000
|
$2,000.000
|
$1,564.290
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
14.000
|
$950.000
|
$750.000
|
$1,325.000
|
$2,100.000
|
$1,400.000
|
$775.850
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$1,380.730
|
$1,100.000
|
$1,875.000
|
$2,400.000
|
$1,500.000
|
$1,144.350
|
|
|
SET (REMOV & REINSTALL)
|
EA
|
2.000
|
$1,000.000
|
$1,000.000
|
$1,875.000
|
$580.000
|
$1,500.000
|
$1,039.360
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$91,400.000
|
$45,000.000
|
$100,000.000
|
$100,000.000
|
$141,000.000
|
$190,595.490
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
3.000
|
$3,500.000
|
$1,700.000
|
$8,500.000
|
$5,000.000
|
$28,000.000
|
$2,392.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
260.000
|
$25.000
|
$25.000
|
$22.000
|
$24.080
|
$24.080
|
$24.080
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
260.000
|
$10.000
|
$6.000
|
$9.000
|
$6.000
|
$6.000
|
$6.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
200.000
|
$25.000
|
$25.000
|
$12.000
|
$23.370
|
$23.370
|
$23.370
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
200.000
|
$10.000
|
$6.000
|
$9.000
|
$6.000
|
$6.000
|
$6.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
3,500.000
|
$2.750
|
$2.000
|
$2.000
|
$2.250
|
$2.250
|
$2.250
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
3,500.000
|
$0.790
|
$0.500
|
$0.500
|
$0.500
|
$0.500
|
$0.500
|
|
|
CURB RAMPS (TY 5)
|
EA
|
2.000
|
$1,960.000
|
$2,000.000
|
$4,200.000
|
$2,200.000
|
$1,890.000
|
$1,984.230
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,900.000
|
$18.680
|
$18.000
|
$18.000
|
$16.840
|
$16.840
|
$16.840
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
2.000
|
$1,443.850
|
$1,500.000
|
$1,700.000
|
$1,398.000
|
$1,498.000
|
$1,898.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,900.000
|
$1.500
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$2,499.660
|
$2,400.000
|
$5,700.000
|
$2,235.000
|
$2,235.000
|
$2,235.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$300.000
|
$100.000
|
$100.000
|
$100.000
|
$100.000
|
$100.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
1,437.000
|
$0.930
|
$0.550
|
$0.600
|
$0.550
|
$0.550
|
$0.550
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
647.000
|
$2.850
|
$2.500
|
$2.800
|
$2.680
|
$2.680
|
$2.680
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
192.000
|
$8.390
|
$5.500
|
$6.000
|
$5.450
|
$5.450
|
$5.450
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
17.000
|
$120.260
|
$75.000
|
$70.000
|
$72.000
|
$72.000
|
$72.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
12.000
|
$146.140
|
$140.000
|
$140.000
|
$134.000
|
$134.000
|
$134.000
|
|
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
|
LF
|
551.000
|
$6.000
|
$2.750
|
$3.000
|
$2.720
|
$2.720
|
$2.720
|
|
REFL PAV MRK TY II (W) 4" (BRK)
|
LF
|
139.000
|
$0.170
|
$0.150
|
$0.150
|
$0.160
|
$0.160
|
$0.160
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
36,861.000
|
$0.130
|
$0.150
|
$0.200
|
$0.160
|
$0.160
|
$0.160
|
|
REFL PAV MRK TY II (W) 8" (SLD)
|
LF
|
1,437.000
|
$0.330
|
$0.300
|
$0.300
|
$0.300
|
$0.300
|
$0.300
|
|
REFL PAV MRK TY II (W) 12" (SLD)
|
LF
|
647.000
|
$1.070
|
$1.250
|
$1.200
|
$1.180
|
$1.180
|
$1.180
|
|
REFL PAV MRK TY II (W) 24" (SLD)
|
LF
|
192.000
|
$2.970
|
$2.750
|
$2.800
|
$2.720
|
$2.720
|
$2.720
|
|
REFL PAV MRK TY II (W) (ARROW)
|
EA
|
17.000
|
$60.190
|
$35.000
|
$36.800
|
$35.000
|
$35.000
|
$35.000
|
|
REFL PAV MRK TY II (W) (WORD)
|
EA
|
12.000
|
$77.420
|
$50.000
|
$50.000
|
$50.000
|
$50.000
|
$50.000
|
|
REFL PAV MRK TY II (Y) 4" (BRK)
|
LF
|
710.000
|
$0.120
|
$0.150
|
$0.150
|
$0.160
|
$0.160
|
$0.160
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
33,737.000
|
$0.140
|
$0.150
|
$0.150
|
$0.160
|
$0.160
|
$0.160
|
|
REFL PAV MRK TY II (Y) 24" (SLD)
|
LF
|
551.000
|
$2.690
|
$2.750
|
$2.800
|
$2.720
|
$2.720
|
$2.720
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
139.000
|
$0.370
|
$0.300
|
$0.300
|
$0.280
|
$0.280
|
$0.280
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
36,861.000
|
$0.330
|
$0.300
|
$0.300
|
$0.280
|
$0.280
|
$0.280
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
710.000
|
$0.800
|
$0.300
|
$0.300
|
$0.280
|
$0.280
|
$0.280
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
33,737.000
|
$0.330
|
$0.300
|
$0.300
|
$0.280
|
$0.280
|
$0.280
|
|
REFL PAV MRKR TY I-C
|
EA
|
45.000
|
$3.070
|
$3.000
|
$3.000
|
$3.000
|
$3.000
|
$3.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
661.000
|
$2.790
|
$3.000
|
$3.000
|
$2.880
|
$2.880
|
$2.880
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
750.000
|
$0.430
|
$1.250
|
$1.300
|
$1.250
|
$1.250
|
$1.250
|
|
|
STORM SEWER CLEANING (PIPE)(12"-18"DIA)
|
LF
|
398.000
|
$20.000
|
$35.000
|
$26.000
|
$16.000
|
$25.000
|
$33.030
|
|
|
BONDING COURSESE
|
GAL
|
7,746.000
|
$2.750
|
$2.250
|
$3.200
|
$2.500
|
$4.150
|
$4.520
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
3.000
|
$7,000.000
|
$2,500.000
|
$4,300.000
|
$2,500.000
|
$5,200.000
|
$5,171.100
|
|
Totals: |
$1,396,812.250
|
$1,158,086.000
|
$1,281,266.300
|
$1,373,412.160
|
$1,409,982.400
|
$1,797,059.198
|