PREPARING ROW
|
STA
|
112.000
|
$6,550.000
|
$3,200.000
|
$5,500.000
|
$1,050.000
|
$2,750.000
|
$17,500.000
|
$35,533.830
|
|
|
PREP ROW (TREE REMOVE) (12"-24" DIA)
|
EA
|
17.000
|
$2,000.000
|
$2,300.000
|
$2,000.000
|
$1,015.000
|
$750.000
|
$2,763.050
|
$8,377.610
|
|
|
TREE PROTECTION (INSTALL)
|
LF
|
148.000
|
$80.000
|
$5.600
|
$5.000
|
$6.000
|
$5.000
|
$6.930
|
$55.000
|
|
|
TREE PROTECTION (REMOVE)
|
LF
|
148.000
|
$10.000
|
$1.700
|
$3.000
|
$2.000
|
$2.000
|
$2.190
|
$5.000
|
|
|
REMOV CONC (PAV)
|
SY
|
20.000
|
$40.000
|
$10.000
|
$1.000
|
$90.000
|
$50.000
|
$242.420
|
$95.300
|
|
|
REMOV CONC (MOWSTRIP)
|
LF
|
112.000
|
$20.000
|
$18.000
|
$1.000
|
$12.000
|
$45.000
|
$21.490
|
$117.480
|
|
|
REMOV CONC (MEDIANS)
|
SY
|
58.000
|
$30.000
|
$12.000
|
$1.000
|
$40.000
|
$45.000
|
$79.750
|
$97.890
|
|
|
REMOV CONC (DRIVEWAYS)
|
SY
|
65.000
|
$35.000
|
$53.000
|
$1.000
|
$45.000
|
$40.000
|
$76.990
|
$89.590
|
|
|
REMOV CONC (SIDEWALK, RAMP OR SUP)
|
SY
|
627.000
|
$55.000
|
$9.500
|
$1.000
|
$25.000
|
$35.000
|
$22.690
|
$68.110
|
|
|
REMOV CONC (CURB RAMP)
|
SY
|
21.000
|
$150.000
|
$35.000
|
$1.000
|
$45.000
|
$45.000
|
$118.760
|
$401.210
|
|
|
REMOV CONC (CURB OR CURB & GUTTER)
|
LF
|
311.000
|
$30.000
|
$11.000
|
$1.000
|
$30.000
|
$15.000
|
$22.170
|
$76.290
|
|
|
REMOV CONC (FOUNDATIONS)
|
SY
|
19.000
|
$42.000
|
$40.000
|
$1.000
|
$75.000
|
$85.000
|
$260.550
|
$395.710
|
|
|
REMOV CONC (MISC)
|
SY
|
13.000
|
$70.000
|
$23.000
|
$1.000
|
$45.000
|
$75.000
|
$197.580
|
$403.960
|
|
|
FURN & PLACE TOPSOIL (4")
|
SY
|
23,692.000
|
$1.800
|
$1.000
|
$6.000
|
$6.000
|
$3.000
|
$2.920
|
$20.960
|
|
|
BROADCAST SEED (PERM_URBAN_CLAY)
|
SY
|
23,692.000
|
$2.000
|
$0.250
|
$1.000
|
$0.250
|
$0.500
|
$0.290
|
$0.200
|
|
|
FERTILIZER
|
AC
|
4.880
|
$750.000
|
$1,100.000
|
$665.000
|
$1,250.000
|
$1,150.000
|
$1,394.280
|
$955.000
|
|
|
VEGETATIVE WATERING
|
TGL
|
399.000
|
$60.000
|
$30.000
|
$50.000
|
$60.000
|
$65.000
|
$73.000
|
$120.050
|
|
|
D-GR HMA TY-B PG64-22 (EXEMPT)
|
TON
|
393.000
|
$135.000
|
$150.000
|
$270.000
|
$210.000
|
$120.000
|
$204.390
|
$224.150
|
|
|
D-GR HMA TY-C PG76-22 (EXEMPT)
|
TON
|
314.000
|
$125.000
|
$150.000
|
$290.000
|
$240.000
|
$350.000
|
$262.790
|
$264.590
|
|
|
D-GR HMA TY-D PG70-22 (EXEMPT)
|
TON
|
1,100.000
|
$110.000
|
$260.000
|
$208.000
|
$230.000
|
$360.000
|
$303.670
|
$214.240
|
|
|
TOM-C PG76-22 SAC-B
|
TON
|
1,130.000
|
$125.000
|
$240.000
|
$189.000
|
$210.000
|
$150.000
|
$280.310
|
$197.760
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
|
SY
|
6,547.000
|
$30.000
|
$38.000
|
$35.000
|
$70.000
|
$60.000
|
$87.600
|
$86.670
|
|
|
PLANE & TEXT ASPH CONC PAV(2")
|
SY
|
20,000.000
|
$1.350
|
$1.250
|
$1.000
|
$1.250
|
$4.000
|
$1.460
|
$5.730
|
|
|
FULL - DEPTH REPAIR CRCP (10")
|
CY
|
6.000
|
$1,750.000
|
$3,200.000
|
$900.000
|
$1,525.000
|
$1,500.000
|
$1,532.980
|
$750.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
9,493.000
|
$12.500
|
$4.500
|
$0.010
|
$30.000
|
$15.000
|
$9.850
|
$48.470
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
113.000
|
$675.000
|
$540.000
|
$780.000
|
$700.000
|
$775.000
|
$912.480
|
$958.460
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
7.000
|
$730.000
|
$280.000
|
$700.000
|
$930.000
|
$725.000
|
$948.980
|
$1,445.010
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,250,000.000
|
$700,000.000
|
$1,500,000.000
|
$1,400,000.000
|
$425,000.000
|
$2,000,000.000
|
$4,250,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$45,000.000
|
$7,300.000
|
$6,000.000
|
$32,750.000
|
$4,500.000
|
$25,000.000
|
$250,000.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$12,500.000
|
$13,000.000
|
$22,800.000
|
$18,925.000
|
$20,000.000
|
$27,657.560
|
$20,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
90.000
|
$275.000
|
$280.000
|
$277.000
|
$350.000
|
$340.000
|
$276.660
|
$350.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
45.000
|
$350.000
|
$80.000
|
$750.000
|
$1,600.000
|
$340.000
|
$1,053.260
|
$600.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
30.000
|
$75.000
|
$45.000
|
$43.000
|
$230.000
|
$60.000
|
$62.050
|
$50.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
30.000
|
$20.000
|
$35.000
|
$38.000
|
$40.000
|
$35.000
|
$54.750
|
$29.750
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
333.000
|
$35.000
|
$42.000
|
$22.000
|
$45.000
|
$50.000
|
$31.390
|
$35.750
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
333.000
|
$14.000
|
$11.000
|
$16.000
|
$10.000
|
$10.000
|
$22.990
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
3,623.000
|
$5.500
|
$3.000
|
$4.000
|
$3.000
|
$5.000
|
$5.470
|
$7.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
3,623.000
|
$2.000
|
$1.000
|
$0.500
|
$1.000
|
$2.000
|
$0.730
|
$0.950
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
564.000
|
$8.000
|
$4.500
|
$8.000
|
$5.000
|
$8.000
|
$10.950
|
$4.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
564.000
|
$2.000
|
$1.500
|
$1.000
|
$1.500
|
$2.000
|
$1.460
|
$1.250
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
1,740.000
|
$60.000
|
$17.000
|
$105.000
|
$100.000
|
$115.000
|
$57.360
|
$86.910
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
140.000
|
$75.000
|
$13.000
|
$35.000
|
$100.000
|
$110.000
|
$136.850
|
$81.340
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
2,060.000
|
$12.000
|
$10.000
|
$19.000
|
$25.000
|
$25.000
|
$24.220
|
$34.380
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
260.000
|
$20.000
|
$18.000
|
$19.000
|
$25.000
|
$25.000
|
$42.090
|
$35.810
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
1,740.000
|
$20.000
|
$6.500
|
$24.000
|
$20.000
|
$15.000
|
$28.970
|
$42.450
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
140.000
|
$22.000
|
$5.500
|
$15.000
|
$20.000
|
$15.000
|
$49.300
|
$29.690
|
|
|
COLORED TEXTURED CONC (4")
|
SY
|
73.000
|
$165.000
|
$120.000
|
$125.000
|
$235.000
|
$140.000
|
$20.000
|
$642.730
|
|
|
COLORED TEXTURED CONC (6")
|
SY
|
280.000
|
$145.000
|
$95.000
|
$127.000
|
$245.000
|
$155.000
|
$33.790
|
$647.870
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
263.000
|
$46.000
|
$31.000
|
$32.000
|
$80.000
|
$35.000
|
$43.800
|
$221.170
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
63.000
|
$300.000
|
$32.000
|
$180.000
|
$225.000
|
$245.000
|
$29.310
|
$237.020
|
|
|
CONC SIDEWALKS (5")
|
SY
|
274.000
|
$102.000
|
$68.000
|
$110.000
|
$210.000
|
$95.000
|
$19.240
|
$234.520
|
|
|
CURB RAMPS (TY 1)
|
EA
|
2.000
|
$3,000.000
|
$3,400.000
|
$3,000.000
|
$3,700.000
|
$1,750.000
|
$4,306.940
|
$4,050.830
|
|
|
CURB RAMPS (TY 7)
|
EA
|
3.000
|
$3,000.000
|
$3,700.000
|
$3,200.000
|
$4,700.000
|
$1,750.000
|
$5,328.930
|
$4,146.440
|
|
|
CONC MEDIAN
|
SY
|
56.000
|
$112.000
|
$100.000
|
$120.000
|
$225.000
|
$115.000
|
$200.740
|
$630.650
|
|
|
CONCRETE MEDIAN (NOSE)
|
SY
|
11.000
|
$850.000
|
$260.000
|
$850.000
|
$250.000
|
$250.000
|
$138.700
|
$461.880
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
75.000
|
$33.000
|
$27.000
|
$35.000
|
$34.000
|
$25.000
|
$51.100
|
$50.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
1.000
|
$3,000.000
|
$2,000.000
|
$4,500.000
|
$2,600.000
|
$2,000.000
|
$4,744.950
|
$2,500.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
77.000
|
$5.000
|
$1.500
|
$15.000
|
$2.000
|
$2.000
|
$7.300
|
$5.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
3.000
|
$310.000
|
$175.000
|
$1,500.000
|
$220.000
|
$150.000
|
$364.990
|
$150.000
|
|
|
GUARDRAIL END TREATMENT (MOVE & RESET)
|
EA
|
3.000
|
$5,000.000
|
$1,300.000
|
$4,500.000
|
$1,600.000
|
$1,250.000
|
$1,094.980
|
$1,100.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
4.000
|
$850.000
|
$1,250.000
|
$650.000
|
$700.000
|
$750.000
|
$1,569.480
|
$1,075.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
5.000
|
$250.000
|
$84.000
|
$100.000
|
$160.000
|
$115.000
|
$105.120
|
$125.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
2,090.000
|
$1.000
|
$0.300
|
$2.000
|
$2.000
|
$2.500
|
$0.480
|
$0.330
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
1,834.000
|
$1.000
|
$0.250
|
$2.000
|
$2.000
|
$2.500
|
$0.320
|
$0.220
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
4,550.000
|
$1.000
|
$0.250
|
$2.000
|
$2.000
|
$2.500
|
$0.320
|
$0.220
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
1,715.000
|
$1.000
|
$0.300
|
$3.000
|
$3.000
|
$3.500
|
$0.420
|
$0.290
|
|
|
WK ZN PAV MRK REMOV (W)(ARROW)
|
EA
|
1.000
|
$500.000
|
$91.000
|
$200.000
|
$200.000
|
$240.000
|
$116.800
|
$380.000
|
|
|
WK ZN PAV MRK REMOV (W)(WORD)
|
EA
|
1.000
|
$500.000
|
$105.000
|
$200.000
|
$200.000
|
$240.000
|
$138.700
|
$495.000
|
|
REFL PAV MRK TY I (W)4"(LNDP)(100MIL)
|
LF
|
10.000
|
$2.500
|
$1.500
|
$1.000
|
$1.000
|
$1.200
|
$2.120
|
$2.450
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
95.000
|
$3.750
|
$5.000
|
$3.500
|
$3.500
|
$4.000
|
$6.500
|
$6.450
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
940.000
|
$8.500
|
$8.000
|
$7.000
|
$7.000
|
$8.000
|
$10.950
|
$10.500
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
7.000
|
$250.000
|
$5.000
|
$200.000
|
$200.000
|
$220.000
|
$211.690
|
$445.000
|
|
REFL PAV MRK TY I (W)(BIKE ARW)(100MIL)
|
EA
|
2.000
|
$200.000
|
$165.000
|
$150.000
|
$150.000
|
$175.000
|
$211.690
|
$645.000
|
|
REFL PAV MRK TY I(W)(BIKE SYML)(100MIL)
|
EA
|
2.000
|
$300.000
|
$245.000
|
$200.000
|
$200.000
|
$220.000
|
$313.890
|
$600.000
|
|
REFL PAV MRK TY I (Y)4"(DOT)(100MIL)
|
LF
|
8.000
|
$6.250
|
$1.800
|
$1.000
|
$1.000
|
$1.500
|
$2.340
|
$3.600
|
|
RE PM TY II (W) 4" (LNDP)
|
LF
|
10.000
|
$1.500
|
$1.000
|
$2.000
|
$2.000
|
$2.000
|
$1.460
|
$2.000
|
|
RE PM TY II (W) 6" (BRK)
|
LF
|
1,460.000
|
$0.350
|
$0.300
|
$0.650
|
$0.650
|
$1.000
|
$0.390
|
$0.270
|
|
RE PM TY II (W) 6" (SLD)
|
LF
|
6,703.000
|
$0.350
|
$0.300
|
$0.650
|
$0.650
|
$1.000
|
$0.390
|
$0.270
|
|
RE PM TY II (W) 8" (SLD)
|
LF
|
136.000
|
$1.500
|
$0.400
|
$0.650
|
$0.650
|
$1.000
|
$0.530
|
$0.860
|
|
RE PM TY II (W) 12" (SLD)
|
LF
|
95.000
|
$2.750
|
$1.400
|
$2.500
|
$2.500
|
$3.000
|
$1.900
|
$1.300
|
|
RE PM TY II (W) 24" (SLD)
|
LF
|
940.000
|
$4.750
|
$5.400
|
$5.000
|
$5.000
|
$6.000
|
$6.930
|
$4.750
|
|
RE PM TY II (W) (ARROW)
|
EA
|
7.000
|
$125.000
|
$9.000
|
$100.000
|
$100.000
|
$115.000
|
$124.100
|
$85.000
|
|
RE PM TY II (W) (BIKE ARROW)
|
EA
|
2.000
|
$125.000
|
$40.000
|
$100.000
|
$100.000
|
$115.000
|
$51.100
|
$35.000
|
|
RE PM TY II (W) (BIKE SYMBOL)
|
EA
|
2.000
|
$175.000
|
$45.000
|
$100.000
|
$100.000
|
$115.000
|
$58.400
|
$40.000
|
|
RE PM TY II (Y) 4" (DOT)
|
LF
|
8.000
|
$10.000
|
$1.300
|
$0.650
|
$0.650
|
$1.000
|
$1.750
|
$1.200
|
|
RE PM TY II (Y) 4" (SLD)
|
LF
|
1,648.000
|
$0.300
|
$0.300
|
$0.650
|
$0.650
|
$1.000
|
$0.360
|
$0.250
|
|
RE PM TY II (Y) 6" (SLD)
|
LF
|
5,820.000
|
$0.350
|
$0.350
|
$0.650
|
$0.650
|
$1.000
|
$0.440
|
$0.300
|
|
|
PAVEMENT SLER 4"
|
LF
|
1,666.000
|
$0.650
|
$0.300
|
$0.300
|
$0.300
|
$1.000
|
$0.360
|
$0.250
|
|
|
PAVEMENT SLER 6"
|
LF
|
13,983.000
|
$0.300
|
$0.350
|
$0.400
|
$0.400
|
$1.000
|
$0.440
|
$0.300
|
|
|
PAVEMENT SLER 12"
|
LF
|
95.000
|
$1.500
|
$1.400
|
$1.500
|
$1.500
|
$2.000
|
$1.900
|
$1.300
|
|
|
PAVEMENT SLER 24"
|
LF
|
940.000
|
$3.000
|
$5.000
|
$3.000
|
$3.000
|
$4.000
|
$6.930
|
$4.750
|
|
|
PAVEMENT SLER (ARROW)
|
EA
|
7.000
|
$50.000
|
$97.000
|
$50.000
|
$50.000
|
$60.000
|
$124.100
|
$85.000
|
|
|
PAVEMENT SLER (BIKE ARROW)
|
EA
|
2.000
|
$72.500
|
$40.000
|
$25.000
|
$25.000
|
$30.000
|
$51.100
|
$35.000
|
|
|
PAVEMENT SLER (BIKE SYMBOL)
|
EA
|
2.000
|
$100.000
|
$45.000
|
$25.000
|
$25.000
|
$30.000
|
$58.400
|
$40.000
|
|
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
|
LF
|
1,460.000
|
$0.750
|
$0.800
|
$1.000
|
$1.000
|
$1.200
|
$1.090
|
$0.750
|
|
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
|
LF
|
6,703.000
|
$0.500
|
$0.800
|
$1.000
|
$1.000
|
$1.200
|
$0.990
|
$0.680
|
|
REFL PAV MRK TY I (Y)4"(SLD)(100MIL)
|
LF
|
1,648.000
|
$0.450
|
$0.500
|
$1.000
|
$1.000
|
$1.200
|
$0.730
|
$0.500
|
|
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
|
LF
|
5,820.000
|
$0.800
|
$0.700
|
$1.000
|
$1.000
|
$1.200
|
$0.990
|
$0.680
|
|
|
ELIM EXT PM & MRKS (4")
|
LF
|
7,875.000
|
$1.000
|
$0.500
|
$1.500
|
$1.500
|
$2.000
|
$0.730
|
$0.500
|
|
|
ELIM EXT PM & MRKS (8")
|
LF
|
173.000
|
$1.000
|
$1.100
|
$1.500
|
$1.500
|
$2.000
|
$1.460
|
$1.000
|
|
|
ELIM EXT PM & MRKS (ARROW)
|
EA
|
3.000
|
$200.000
|
$51.000
|
$200.000
|
$200.000
|
$220.000
|
$65.700
|
$255.000
|
|
|
ELIM EXT PM & MRKS (WORD)
|
EA
|
1.000
|
$500.000
|
$62.000
|
$200.000
|
$200.000
|
$220.000
|
$80.300
|
$255.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
1,666.000
|
$0.300
|
$0.400
|
$0.020
|
$0.020
|
$0.500
|
$0.510
|
$0.350
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
13,983.000
|
$0.200
|
$0.600
|
$0.040
|
$0.040
|
$0.500
|
$0.770
|
$0.530
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
95.000
|
$0.500
|
$0.800
|
$0.250
|
$0.250
|
$0.500
|
$1.020
|
$0.700
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
940.000
|
$2.000
|
$0.900
|
$0.500
|
$0.500
|
$0.500
|
$1.170
|
$0.800
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
7.000
|
$28.000
|
$45.000
|
$25.000
|
$25.000
|
$30.000
|
$58.400
|
$40.000
|
|
|
PAV SURF PREP FOR MRK (BIKE ARROW)
|
EA
|
2.000
|
$85.000
|
$51.000
|
$25.000
|
$25.000
|
$30.000
|
$65.700
|
$45.000
|
|
|
PAV SURF PREP FOR MRK (BIKE SYMBOL)
|
EA
|
2.000
|
$85.000
|
$51.000
|
$25.000
|
$25.000
|
$30.000
|
$65.700
|
$45.000
|
|
|
BONDING COURSE
|
GAL
|
3,600.000
|
$3.700
|
$4.000
|
$3.250
|
$3.250
|
$5.000
|
$4.740
|
$3.350
|
|
|
LED ROADSIDE SIGN
|
EA
|
1.000
|
$5,000.000
|
$2,600.000
|
$2,100.000
|
$2,800.000
|
$3,500.000
|
$14,599.830
|
$3,500.000
|
|
|
DUCT BANK (CONC ENCASE) (TRENCH)
|
LF
|
9,485.000
|
$500.000
|
$248.000
|
$678.000
|
$750.000
|
$1,270.000
|
$955.380
|
$542.490
|
|
|
DUCT BANK (STL ENCASE) (BORE)
|
LF
|
1,413.000
|
$2,200.000
|
$1,200.000
|
$2,350.000
|
$2,150.000
|
$1,950.000
|
$2,962.320
|
$1,735.490
|
|
|
MANHOLE (6’X12’) (ALL DEPTHS)
|
EA
|
35.000
|
$95,500.000
|
$30,000.000
|
$50,000.000
|
$35,600.000
|
$45,750.000
|
$60,870.060
|
$35,787.630
|
|
Totals: |
$16,306,478.850
|
$7,779,122.150
|
$15,620,588.270
|
$15,891,034.640
|
$19,561,040.700
|
$22,146,358.556
|
$23,827,063.280
|