REMOVING CONC (RIPRAP)
|
SY
|
10.000
|
$20.000
|
$55.000
|
$10.000
|
$63.000
|
$70.000
|
$50.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
451.910
|
$175.000
|
$100.000
|
$330.000
|
$154.000
|
$500.000
|
$350.000
|
|
|
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
|
CY
|
11,916.000
|
$20.000
|
$8.000
|
$11.000
|
$12.500
|
$7.000
|
$10.000
|
|
|
BLADING
|
STA
|
451.910
|
$50.000
|
$100.000
|
$51.000
|
$110.000
|
$250.000
|
$110.000
|
|
|
SPEC EXCAV WORK (HYD EXCAVATOR)
|
HR
|
86.000
|
$75.000
|
$70.000
|
$50.000
|
$190.000
|
$100.000
|
$175.000
|
|
|
BLOCK SODDING
|
SY
|
1,384.000
|
$5.000
|
$4.000
|
$6.000
|
$5.000
|
$5.000
|
$6.000
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
100,425.000
|
$0.150
|
$0.040
|
$0.120
|
$0.150
|
$0.100
|
$0.100
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
100,425.000
|
$0.150
|
$0.040
|
$0.120
|
$0.150
|
$0.100
|
$0.100
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
200,850.000
|
$0.250
|
$0.150
|
$0.300
|
$0.300
|
$0.300
|
$0.350
|
|
|
VEGETATIVE WATERING
|
MG
|
4,031.300
|
$15.000
|
$4.000
|
$0.010
|
$5.000
|
$1.000
|
$15.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
82.000
|
$2.000
|
$11.000
|
$5.000
|
$5.000
|
$5.000
|
$1.500
|
|
|
SPRINKLING (DUST CONTROL)
|
MG
|
1,205.000
|
$2.000
|
$1.000
|
$0.010
|
$5.000
|
$15.000
|
$0.010
|
|
|
FL BS (RDWY DEL) (TY A GR 1-2)
|
TON
|
42,640.000
|
$38.000
|
$34.680
|
$38.500
|
$35.700
|
$40.000
|
$37.000
|
|
|
CEMENT
|
TON
|
2,177.000
|
$135.000
|
$143.000
|
$140.000
|
$150.000
|
$150.000
|
$160.000
|
|
|
CEMENT TREAT(MX EXST MTL & NW BS)(12")
|
SY
|
120,511.000
|
$2.750
|
$3.800
|
$2.150
|
$3.500
|
$3.000
|
$3.500
|
|
|
ASPH (RC-250)
|
GAL
|
30,128.000
|
$3.500
|
$3.000
|
$3.500
|
$3.150
|
$3.500
|
$4.200
|
|
|
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
|
GAL
|
106,051.000
|
$2.800
|
$3.000
|
$2.590
|
$2.350
|
$2.750
|
$3.000
|
|
|
AGGR (TY-PE, E, L OR PL GR 3)
|
CY
|
1,339.000
|
$95.000
|
$120.000
|
$111.810
|
$110.000
|
$125.000
|
$120.000
|
|
|
AGGR (TY E OR L GR 5)
|
CY
|
927.000
|
$100.000
|
$140.000
|
$122.900
|
$110.000
|
$125.000
|
$160.000
|
|
|
AGGR(TY PE,TY-PL,TY-E,TY-L GR-4)(SAC-B)
|
CY
|
1,096.000
|
$120.000
|
$110.000
|
$126.000
|
$110.000
|
$125.000
|
$150.000
|
|
|
D-GR HMA(SQ) TY-D PG64-22 NON-MOW STRIP
|
SY
|
480.000
|
$35.000
|
$40.000
|
$65.420
|
$61.000
|
$75.000
|
$90.000
|
|
|
CEM STABIL BKFL
|
CY
|
180.000
|
$185.000
|
$175.000
|
$210.000
|
$170.000
|
$165.000
|
$190.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
117.000
|
$90.000
|
$99.000
|
$100.000
|
$69.000
|
$150.000
|
$90.000
|
|
|
CUT AND RESTORE PAV (FLEX BASE)
|
SY
|
4.000
|
$50.000
|
$42.000
|
$55.000
|
$100.000
|
$200.000
|
$70.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
37.000
|
$20.000
|
$7.000
|
$15.000
|
$28.000
|
$35.000
|
$40.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
96.000
|
$15.000
|
$32.000
|
$55.000
|
$43.000
|
$100.000
|
$60.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
4.000
|
$750.000
|
$300.000
|
$770.000
|
$950.000
|
$1,250.000
|
$2,500.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(12 IN)
|
CY
|
20.000
|
$180.000
|
$185.000
|
$210.000
|
$160.000
|
$250.000
|
$150.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
63.000
|
$200.000
|
$185.000
|
$225.000
|
$160.000
|
$200.000
|
$190.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
892.000
|
$40.000
|
$60.000
|
$60.000
|
$42.000
|
$55.000
|
$36.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
208.000
|
$60.000
|
$75.000
|
$82.000
|
$59.000
|
$80.000
|
$50.000
|
|
|
HEADWALL (CH - FW - 0) (DIA= 30 IN)
|
EA
|
2.000
|
$4,000.000
|
$5,300.000
|
$6,600.000
|
$4,000.000
|
$4,500.000
|
$3,300.000
|
|
|
HEADWALL (CH - FW - 0) (DIA= 36 IN)
|
EA
|
4.000
|
$4,500.000
|
$6,200.000
|
$7,000.000
|
$5,500.000
|
$7,500.000
|
$4,400.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 72 IN)
|
EA
|
1.000
|
$13,500.000
|
$16,500.000
|
$18,700.000
|
$16,500.000
|
$15,000.000
|
$14,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
2.000
|
$500.000
|
$500.000
|
$575.000
|
$600.000
|
$700.000
|
$495.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
64.000
|
$600.000
|
$600.000
|
$600.000
|
$600.000
|
$750.000
|
$550.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
13.000
|
$750.000
|
$700.000
|
$825.000
|
$700.000
|
$1,000.000
|
$700.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$800.000
|
$900.000
|
$1,050.000
|
$900.000
|
$1,250.000
|
$900.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
2.000
|
$600.000
|
$200.000
|
$500.000
|
$750.000
|
$2,500.000
|
$1,000.000
|
|
|
REMOV STR (PIPE)
|
EA
|
35.000
|
$200.000
|
$200.000
|
$275.000
|
$270.000
|
$300.000
|
$400.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$400,000.000
|
$300,000.000
|
$232,000.000
|
$400,000.000
|
$490,000.000
|
$450,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$1,500.000
|
$7,000.000
|
$2,600.000
|
$3,000.000
|
$5,000.000
|
$3,200.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,470.000
|
$30.000
|
$33.000
|
$30.000
|
$31.000
|
$25.000
|
$32.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,470.000
|
$5.000
|
$4.000
|
$8.250
|
$8.000
|
$5.000
|
$8.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
492.000
|
$20.000
|
$10.000
|
$23.000
|
$22.000
|
$15.000
|
$21.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
492.000
|
$10.000
|
$3.000
|
$8.250
|
$7.350
|
$5.000
|
$7.000
|
|
|
CONSTRUCTION PERIMETER FENCE
|
LF
|
900.000
|
$1.500
|
$4.000
|
$3.750
|
$2.900
|
$3.000
|
$3.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
13,670.000
|
$2.500
|
$2.750
|
$5.000
|
$2.500
|
$3.000
|
$2.750
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
13,670.000
|
$1.000
|
$0.600
|
$2.000
|
$0.800
|
$0.500
|
$0.800
|
|
|
DRIVEWAYS (ACP)
|
SY
|
861.000
|
$40.000
|
$40.000
|
$24.960
|
$58.000
|
$30.000
|
$55.000
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
1,815.000
|
$25.000
|
$24.000
|
$27.380
|
$50.000
|
$30.000
|
$55.000
|
|
|
TURNOUTS (SURF TREAT)
|
SY
|
113.000
|
$25.000
|
$40.000
|
$29.420
|
$53.000
|
$50.000
|
$75.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
350.000
|
$20.000
|
$18.000
|
$19.800
|
$19.000
|
$25.000
|
$23.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,800.000
|
$1,300.000
|
$1,742.500
|
$2,600.000
|
$1,500.000
|
$1,700.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
956.000
|
$5.000
|
$2.500
|
$2.750
|
$3.500
|
$5.000
|
$3.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$150.000
|
$300.000
|
$330.000
|
$220.000
|
$250.000
|
$350.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,200.000
|
$2,350.000
|
$2,585.000
|
$2,500.000
|
$2,600.000
|
$3,000.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$270.000
|
$300.000
|
$330.000
|
$220.000
|
$500.000
|
$350.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
5.000
|
$150.000
|
$175.000
|
$192.500
|
$185.000
|
$210.000
|
$200.000
|
|
|
MAILBOX INSTALL-D (WC-POST) TY 3
|
EA
|
2.000
|
$165.000
|
$175.000
|
$192.500
|
$185.000
|
$250.000
|
$200.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
9.000
|
$450.000
|
$475.000
|
$522.500
|
$500.000
|
$500.000
|
$600.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
1.000
|
$500.000
|
$550.000
|
$605.000
|
$575.000
|
$500.000
|
$700.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
26.000
|
$260.000
|
$275.000
|
$302.500
|
$290.000
|
$275.000
|
$350.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
10.000
|
$280.000
|
$300.000
|
$330.000
|
$315.000
|
$350.000
|
$375.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
44.000
|
$80.000
|
$75.000
|
$82.500
|
$80.000
|
$90.000
|
$80.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
4.000
|
$20.000
|
$20.000
|
$22.000
|
$21.000
|
$25.000
|
$25.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
8.000
|
$40.000
|
$27.500
|
$30.250
|
$29.000
|
$30.000
|
$30.000
|
|
|
INSTL DEL ASSN (OM-2Z)(FLX)(WAP)
|
EA
|
62.000
|
$50.000
|
$70.000
|
$77.000
|
$73.500
|
$200.000
|
$80.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
180,765.000
|
$0.100
|
$0.090
|
$0.110
|
$0.100
|
$0.100
|
$0.100
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
271,148.000
|
$0.100
|
$0.090
|
$0.110
|
$0.100
|
$0.100
|
$0.100
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
27,117.000
|
$1.000
|
$0.300
|
$1.000
|
$1.100
|
$0.250
|
$1.400
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
90,359.000
|
$0.250
|
$0.330
|
$0.390
|
$0.350
|
$0.330
|
$0.400
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
8,540.000
|
$0.250
|
$0.380
|
$0.400
|
$0.400
|
$0.400
|
$0.450
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
47,551.000
|
$0.250
|
$0.330
|
$0.340
|
$0.350
|
$0.330
|
$0.400
|
|
RE PM W/RET REQ TY II (Y) 4" (SLD)
|
LF
|
480.000
|
$0.250
|
$1.000
|
$1.100
|
$1.050
|
$1.000
|
$1.200
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
33.000
|
$15.000
|
$15.000
|
$16.500
|
$16.000
|
$15.000
|
$16.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,080.000
|
$3.000
|
$3.250
|
$3.500
|
$3.400
|
$4.000
|
$4.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
60.000
|
$2.500
|
$3.000
|
$2.200
|
$2.100
|
$3.000
|
$3.000
|
|
Totals: |
$4,505,850.100
|
$4,311,589.970
|
$4,391,116.803
|
$4,533,242.490
|
$4,983,703.900
|
$5,009,294.350
|