REMOVING CONC (RIPRAP)
|
SY
|
122.000
|
$45.000
|
$7.000
|
$10.000
|
$18.000
|
$30.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
650.000
|
$15.000
|
$5.000
|
$4.000
|
$6.000
|
$15.000
|
|
|
REMOV STAB BASE AND ASPH PAV (2"-15")
|
SY
|
2,184.000
|
$15.000
|
$12.000
|
$7.000
|
$15.000
|
$13.500
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
508.000
|
$30.000
|
$20.000
|
$24.000
|
$15.000
|
$25.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
1,953.000
|
$50.000
|
$20.000
|
$24.000
|
$30.000
|
$30.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
2,832.000
|
$5.500
|
$4.500
|
$4.500
|
$3.000
|
$4.000
|
|
|
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
|
SY
|
2,832.000
|
$1.500
|
$2.680
|
$0.700
|
$2.000
|
$1.100
|
|
|
BONDED FBR MTRX SEED (TEMP)(WARM)
|
SY
|
1,416.000
|
$1.250
|
$0.010
|
$0.700
|
$1.000
|
$0.900
|
|
|
BONDED FBR MTRX SEED (TEMP)(COOL)
|
SY
|
1,416.000
|
$1.250
|
$0.010
|
$0.700
|
$1.000
|
$0.900
|
|
|
VEGETATIVE WATERING
|
MG
|
91.000
|
$160.000
|
$10.000
|
$30.000
|
$1.000
|
$10.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
160.000
|
$4.500
|
$2.000
|
$2.400
|
$4.000
|
$2.000
|
|
|
FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS)
|
CY
|
727.000
|
$110.000
|
$175.000
|
$140.000
|
$100.000
|
$85.000
|
|
|
CEMENT
|
TON
|
95.000
|
$325.000
|
$250.000
|
$350.000
|
$300.000
|
$375.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
3,319.000
|
$6.750
|
$5.750
|
$6.000
|
$7.000
|
$5.000
|
|
|
CEMENT TREAT (NEW BASE)(DC)(8")
|
SY
|
3,267.000
|
$5.250
|
$5.750
|
$6.000
|
$7.000
|
$5.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
818.000
|
$12.000
|
$8.360
|
$10.000
|
$15.000
|
$10.000
|
|
|
CEM STABIL BKFL
|
CY
|
137.000
|
$300.000
|
$300.000
|
$310.000
|
$300.000
|
$300.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
275.000
|
$275.000
|
$206.220
|
$275.000
|
$195.000
|
$230.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
240.000
|
$375.000
|
$272.070
|
$425.000
|
$275.000
|
$315.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
27.800
|
$1,700.000
|
$1,100.000
|
$1,385.000
|
$1,600.000
|
$1,400.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
22.800
|
$1,700.000
|
$1,100.000
|
$1,320.000
|
$1,600.000
|
$1,500.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
8.500
|
$2,000.000
|
$1,500.000
|
$1,575.000
|
$1,800.000
|
$1,500.000
|
|
|
REINF CONC SLAB (SLAB BEAM)(HPC)
|
SF
|
4,848.000
|
$25.000
|
$19.500
|
$31.000
|
$22.000
|
$25.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
84.400
|
$895.000
|
$630.000
|
$700.000
|
$1,000.000
|
$1,000.000
|
|
|
PRESTR CONC SLAB BEAM (4SB12)
|
LF
|
414.000
|
$250.000
|
$235.000
|
$280.000
|
$250.000
|
$230.000
|
|
|
PRESTR CONC SLAB BEAM (5SB12)
|
LF
|
621.000
|
$260.000
|
$235.000
|
$280.000
|
$250.000
|
$230.000
|
|
|
RIPRAP (CONC)(CL B)
|
CY
|
2.400
|
$875.000
|
$950.000
|
$1,000.000
|
$950.000
|
$2,000.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
566.000
|
$225.000
|
$160.000
|
$175.000
|
$200.000
|
$200.000
|
|
|
BEDDING MATERIAL (6 IN)
|
CY
|
108.000
|
$215.000
|
$140.000
|
$180.000
|
$180.000
|
$200.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
30.000
|
$740.000
|
$750.000
|
$600.000
|
$600.000
|
$800.000
|
|
|
RAIL (TY SSTR) (W/DRAIN SLOT) (HPC)
|
LF
|
234.000
|
$165.000
|
$160.000
|
$135.000
|
$150.000
|
$150.000
|
|
|
ARMOR JOINT
|
LF
|
88.000
|
$195.000
|
$150.000
|
$90.000
|
$200.000
|
$100.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
85.000
|
$200.000
|
$150.000
|
$110.000
|
$220.000
|
$150.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
28.000
|
$105.000
|
$100.000
|
$90.000
|
$120.000
|
$80.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,700.000
|
$1,000.000
|
$1,500.000
|
$2,500.000
|
$1,200.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
1.000
|
$40,000.000
|
$25,000.000
|
$31,000.000
|
$50,000.000
|
$25,000.000
|
|
|
REMOV STR (PIPE)
|
EA
|
1.000
|
$2,000.000
|
$500.000
|
$525.000
|
$1,000.000
|
$500.000
|
|
|
REMOV STR (SMALL FENCE)
|
LF
|
858.000
|
$15.000
|
$5.000
|
$4.500
|
$5.000
|
$8.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$175,000.000
|
$175,000.000
|
$60,000.000
|
$150,000.000
|
$200,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
6.000
|
$10,000.000
|
$1,500.000
|
$1,600.000
|
$4,500.000
|
$6,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
100.000
|
$50.000
|
$47.700
|
$54.000
|
$1.000
|
$42.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
15.000
|
$75.000
|
$53.000
|
$96.000
|
$1.000
|
$55.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
115.000
|
$18.000
|
$10.600
|
$18.000
|
$1.000
|
$16.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
160.000
|
$37.500
|
$37.100
|
$42.000
|
$1.000
|
$40.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
160.000
|
$13.000
|
$7.420
|
$12.000
|
$1.000
|
$16.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,608.000
|
$5.000
|
$4.770
|
$4.500
|
$1.000
|
$4.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,608.000
|
$1.750
|
$1.060
|
$0.300
|
$1.000
|
$1.500
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
355.000
|
$12.000
|
$12.460
|
$6.000
|
$5.000
|
$11.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
355.000
|
$2.750
|
$1.590
|
$1.200
|
$1.000
|
$5.500
|
|
|
DRIVEWAYS (ACP)
|
SY
|
119.000
|
$115.000
|
$25.160
|
$100.000
|
$120.000
|
$75.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
287.500
|
$30.000
|
$25.000
|
$27.000
|
$24.000
|
$25.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,500.000
|
$1,749.000
|
$2,000.000
|
$1,700.000
|
$1,850.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
400.000
|
$6.750
|
$2.120
|
$2.400
|
$2.000
|
$2.500
|
|
|
RM MTL BM GD FEN TRANS (T101)
|
EA
|
4.000
|
$300.000
|
$159.000
|
$180.000
|
$150.000
|
$200.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,450.000
|
$3,047.500
|
$3,450.000
|
$2,900.000
|
$3,200.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$410.000
|
$212.000
|
$240.000
|
$500.000
|
$250.000
|
|
|
WIRE FENCE (TY C)
|
LF
|
760.000
|
$35.000
|
$20.000
|
$21.000
|
$20.000
|
$32.000
|
|
|
GATE (TY 1)
|
EA
|
1.000
|
$3,450.000
|
$500.000
|
$900.000
|
$2,000.000
|
$1,200.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
1.000
|
$950.000
|
$1,500.000
|
$1,200.000
|
$1,500.000
|
$1,700.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
2.000
|
$900.000
|
$1,500.000
|
$1,200.000
|
$1,500.000
|
$1,400.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
1.000
|
$155.000
|
$500.000
|
$180.000
|
$500.000
|
$100.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
4.000
|
$45.000
|
$21.200
|
$24.000
|
$20.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
|
EA
|
7.000
|
$35.000
|
$21.200
|
$24.000
|
$20.000
|
$30.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
100.000
|
$2.500
|
$0.100
|
$2.400
|
$5.000
|
$3.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
100.000
|
$3.000
|
$0.100
|
$2.400
|
$5.000
|
$3.000
|
|
|
PAVEMENT SEALER 6"
|
LF
|
608.000
|
$1.000
|
$2.120
|
$2.400
|
$2.000
|
$2.200
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
22.000
|
$8.000
|
$10.600
|
$12.000
|
$10.000
|
$11.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
608.000
|
$0.750
|
$2.120
|
$2.400
|
$2.000
|
$2.200
|
|
|
PAV SURF PREP FOR MRK (RPM)
|
EA
|
4.000
|
$1.500
|
$26.500
|
$30.000
|
$25.000
|
$27.500
|
|
|
NO. OF WORKING DAYS
|
$/D
|
3,210.000
|
$102.000
|
$83.000
|
$102.000
|
$102.000
|
$102.000
|
|
|
SP MIXES SP-C PG76-22
|
TON
|
352.000
|
$180.000
|
$207.790
|
$234.000
|
$300.000
|
$245.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$15,950.000
|
$10,000.000
|
$18,000.000
|
$10,000.000
|
$15,000.000
|
|
|
REFL PAV MRK AWT (W) 6" (SLD) (100MIL)
|
LF
|
1,720.000
|
$1.400
|
$3.180
|
$3.600
|
$3.000
|
$3.300
|
|
|
REFL PAV MRK AWT (Y) 6" (SLD) (100MIL)
|
LF
|
1,720.000
|
$1.500
|
$3.180
|
$3.600
|
$3.000
|
$3.300
|
|
|
TMA (STATIONARY)
|
DAY
|
5.000
|
$400.000
|
$400.000
|
$240.000
|
$150.000
|
$300.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
60.000
|
$92.000
|
$35.000
|
$60.000
|
$20.000
|
$30.000
|
|
Totals: |
$2,229,422.250
|
$1,790,148.090
|
$1,939,811.600
|
$1,994,460.000
|
$2,039,492.200
|