PREP ROW (TREE)(24"-30"DIA)
|
EA
|
1.000
|
$1,500.000
|
$2,500.000
|
$3,000.000
|
$3,000.000
|
$15,000.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
82.000
|
$45.000
|
$20.000
|
$40.000
|
$10.000
|
$90.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
534.000
|
$16.000
|
$10.000
|
$6.000
|
$10.000
|
$10.000
|
|
|
REMOVING STAB BASE & ASPH PAV (7"-12")
|
SY
|
3,333.000
|
$25.000
|
$11.000
|
$8.000
|
$20.000
|
$13.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
708.000
|
$30.000
|
$15.000
|
$22.000
|
$30.000
|
$28.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
2,556.000
|
$50.000
|
$20.000
|
$32.000
|
$30.000
|
$30.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
5,464.000
|
$4.500
|
$3.000
|
$4.000
|
$4.000
|
$4.000
|
|
|
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
|
SY
|
5,464.000
|
$1.250
|
$0.720
|
$0.800
|
$1.500
|
$0.710
|
|
|
BONDED FBR MTRX SEED (TEMP)(WARM)
|
SY
|
2,732.000
|
$1.250
|
$0.690
|
$0.750
|
$1.000
|
$0.720
|
|
|
BONDED FBR MTRX SEED (TEMP)(COOL)
|
SY
|
2,732.000
|
$1.250
|
$0.690
|
$0.750
|
$1.000
|
$0.700
|
|
|
VEGETATIVE WATERING
|
MG
|
175.000
|
$160.000
|
$5.000
|
$44.000
|
$1.000
|
$12.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
950.000
|
$3.000
|
$0.800
|
$1.900
|
$3.000
|
$1.000
|
|
|
FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS)
|
CY
|
976.000
|
$125.000
|
$135.000
|
$135.000
|
$80.000
|
$145.000
|
|
|
CEMENT
|
TON
|
127.000
|
$325.000
|
$305.000
|
$300.000
|
$320.000
|
$320.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
4,391.000
|
$8.250
|
$5.000
|
$3.650
|
$12.000
|
$5.000
|
|
|
CEMENT TREAT (NEW BASE)(DC)(8")
|
SY
|
4,383.000
|
$8.250
|
$5.000
|
$3.650
|
$12.000
|
$5.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
1,097.000
|
$12.000
|
$6.500
|
$12.500
|
$8.000
|
$7.000
|
|
|
CEM STABIL BKFL
|
CY
|
141.000
|
$290.000
|
$275.000
|
$325.000
|
$250.000
|
$305.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
40.000
|
$650.000
|
$300.000
|
$280.000
|
$250.000
|
$350.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
450.000
|
$275.000
|
$175.000
|
$220.000
|
$125.000
|
$230.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
440.000
|
$350.000
|
$250.000
|
$380.000
|
$200.000
|
$325.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
29.000
|
$1,700.000
|
$1,275.000
|
$1,850.000
|
$1,800.000
|
$1,450.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
34.200
|
$1,850.000
|
$1,300.000
|
$1,925.000
|
$1,800.000
|
$1,350.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
12.700
|
$2,100.000
|
$1,300.000
|
$2,450.000
|
$1,800.000
|
$1,750.000
|
|
|
REINF CONC SLAB (SLAB BEAM)(HPC)
|
SF
|
7,849.000
|
$30.000
|
$30.000
|
$25.000
|
$24.000
|
$32.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
84.400
|
$850.000
|
$1,000.000
|
$770.000
|
$1,000.000
|
$1,100.000
|
|
|
PRESTR CONC SLAB BEAM (4SB15)
|
LF
|
672.010
|
$300.000
|
$235.000
|
$300.000
|
$250.000
|
$250.000
|
|
|
PRESTR CONC SLAB BEAM (5SB15)
|
LF
|
1,008.010
|
$310.000
|
$235.000
|
$300.000
|
$250.000
|
$250.000
|
|
|
RIPRAP (CONC)(CL B)
|
CY
|
2.600
|
$1,050.000
|
$1,000.000
|
$1,685.000
|
$1,000.000
|
$2,000.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
909.000
|
$225.000
|
$195.000
|
$160.000
|
$200.000
|
$210.000
|
|
|
BEDDING MATERIAL (6 IN)
|
CY
|
208.000
|
$220.000
|
$195.000
|
$185.000
|
$200.000
|
$225.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
40.000
|
$750.000
|
$725.000
|
$700.000
|
$650.000
|
$740.000
|
|
|
RAIL (TY SSTR) (W/DRAIN SLOT) (HPC)
|
LF
|
364.000
|
$165.000
|
$175.000
|
$135.000
|
$110.000
|
$155.000
|
|
|
ARMOR JOINT
|
LF
|
89.000
|
$175.000
|
$125.000
|
$110.000
|
$170.000
|
$130.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
128.000
|
$160.000
|
$150.000
|
$110.000
|
$170.000
|
$140.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$100,000.000
|
$40,000.000
|
$60,000.000
|
$175,000.000
|
$50,000.000
|
|
|
REMOV STR (SMALL FENCE)
|
LF
|
447.000
|
$20.000
|
$4.000
|
$6.000
|
$10.000
|
$10.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$281,000.000
|
$225,000.000
|
$200,000.000
|
$225,000.000
|
$260,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
11.000
|
$10,600.000
|
$5,000.000
|
$5,500.000
|
$12,000.000
|
$6,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
60.000
|
$45.000
|
$38.000
|
$50.000
|
$1.000
|
$45.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
100.000
|
$75.000
|
$54.000
|
$88.000
|
$1.000
|
$55.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
160.000
|
$20.000
|
$11.000
|
$18.000
|
$1.000
|
$11.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
160.000
|
$35.000
|
$32.000
|
$37.500
|
$1.000
|
$39.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
160.000
|
$12.000
|
$10.500
|
$15.000
|
$1.000
|
$11.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,551.000
|
$5.000
|
$4.250
|
$5.000
|
$1.000
|
$4.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,551.000
|
$1.750
|
$0.700
|
$0.800
|
$1.000
|
$2.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
391.000
|
$12.000
|
$8.500
|
$7.500
|
$1.000
|
$7.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
391.000
|
$3.000
|
$2.150
|
$1.250
|
$1.000
|
$2.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
562.500
|
$35.000
|
$25.000
|
$29.000
|
$26.000
|
$26.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,500.000
|
$2,000.000
|
$2,000.000
|
$1,500.000
|
$1,820.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
275.000
|
$7.000
|
$2.150
|
$2.500
|
$2.000
|
$2.200
|
|
|
RM MTL BM GD FEN TRANS (T101)
|
EA
|
4.000
|
$275.000
|
$165.000
|
$187.500
|
$1,200.000
|
$165.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,500.000
|
$3,100.000
|
$3,600.000
|
$2,800.000
|
$3,200.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$350.000
|
$215.000
|
$250.000
|
$500.000
|
$220.000
|
|
|
WIRE FENCE (TY C)
|
LF
|
448.000
|
$40.000
|
$27.000
|
$18.750
|
$20.000
|
$11.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
2.000
|
$825.000
|
$1,200.000
|
$1,250.000
|
$1,600.000
|
$1,200.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
6.000
|
$43.500
|
$50.000
|
$56.250
|
$50.000
|
$50.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
|
EA
|
18.000
|
$35.000
|
$30.000
|
$31.250
|
$40.000
|
$28.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
2.000
|
$110.000
|
$250.000
|
$125.000
|
$200.000
|
$300.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
150.000
|
$3.000
|
$2.000
|
$3.750
|
$5.000
|
$2.200
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
150.000
|
$3.000
|
$2.000
|
$3.750
|
$5.000
|
$2.200
|
|
|
PAVEMENT SEALER 6"
|
LF
|
868.000
|
$1.100
|
$2.150
|
$2.500
|
$1.000
|
$2.200
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
34.000
|
$10.000
|
$21.500
|
$25.000
|
$20.000
|
$22.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
868.000
|
$1.250
|
$1.100
|
$1.250
|
$1.000
|
$1.100
|
|
|
PAV SURF PREP FOR MRK (RPM)
|
EA
|
6.000
|
$10.000
|
$11.000
|
$12.500
|
$1.000
|
$13.000
|
|
|
NO. OF WORKING DAYS
|
$/D
|
5,997.000
|
$204.000
|
$171.000
|
$171.000
|
$171.000
|
$204.000
|
|
|
SP MIXES SP-D PG70-22
|
TON
|
354.000
|
$380.000
|
$245.000
|
$225.000
|
$250.000
|
$200.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
3.000
|
$16,500.000
|
$18,000.000
|
$20,000.000
|
$28,000.000
|
$22,000.000
|
|
|
REFL PAV MRK AWT (W) 6" (SLD) (100MIL)
|
LF
|
2,680.000
|
$3.000
|
$2.150
|
$2.500
|
$4.000
|
$2.200
|
|
|
REFL PAV MRK AWT (Y) 6" (SLD) (100MIL)
|
LF
|
2,680.000
|
$3.000
|
$2.150
|
$2.500
|
$4.000
|
$2.200
|
|
|
TMA (STATIONARY)
|
DAY
|
5.000
|
$310.000
|
$350.000
|
$180.000
|
$300.000
|
$250.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
60.000
|
$95.000
|
$35.000
|
$20.000
|
$50.000
|
$70.000
|
|
Totals: |
$4,301,743.150
|
$3,343,732.790
|
$3,520,919.850
|
$3,616,494.000
|
$3,816,182.780
|