VICTORIA FM 236 (0842-03-037)

Items: 148

County: VICTORIA
Length: 5.4730 MILES
Highway: FM 236
District: YOAKUM
Control Number: 0842-03-037
DBE Goal: 0.0%
Project: F 2026(994)
Guaranty: $100,000.00
Time: 435 WORKING DAYS
Engineer's Estimate: $33,725,491.10
Date: 08/06/2026 1:00 PM CDT (6 weeks ago) Changed
Contract Number: 8263004
Type: WIDEN ROAD - ADD LANES AND SHOULDERS
Project ID: A00124182
Contract Type: FEDERAL
Project Description: ADD 3 LANES TO CONVERT TO A 4-LANE FACILITY WITH A CONTINUOUS LEFT TURN LANE INCLUDING WIDEN PAVEMENT, REALIGN OF ROADWAY, CONSTRUCT UNDIVIDED LANES, PLACEMENT OF ACP, UPGRADE TO STANDARD, AND PROPOSED DRAINAGE MODIFICATIONS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$33,725,491.10
$24,999,762.05
Over/Under Est: -25.87% -$8,725,729.05
$26,432,444.07
Over/Under Est: -21.62% -$7,293,047.03
Amt Left: 5.73% $1,432,682.02
Over/Under Est: 1.96% $662,159.90
Amt Left: 37.55% $9,387,888.95
Delta: -30.10% -$7,955,206.93

Bid Items & Bid Tabulations

148 Total 0 of 148
VICTORIA  |  FM 236  |  YOAKUM  |  0842-03-037  |  08/06/2026 1:00 PM CDT  |  $33,725,491.10  |  F 2026(994)  |  WIDEN ROAD - ADD LANES AND SHOULDERS  |  435 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CK NEWBERRY, LLC
HUNTER INDUSTRIES, LTD.
JOE BLAND CONSTRUCTION LLC
PREPARING ROW
STA 289.000 $2,500.000 $500.000 $930.600 $1,000.000
REMOV CONC (MOWSTRIP)
SY 340.000 $13.000 $10.000 $9.900 $25.000
REMOV CONC (DRIVEWAYS)
SY 928.000 $22.000 $20.000 $16.500 $25.000
RMV (10"-14") TRT/UNTRT BASE & ASPH PAV
SY 50,932.000 $11.000 $4.000 $6.530 $5.000
EXCAV (ROADWAY)
CY 48,832.000 $25.000 $15.000 $18.700 $24.000
EMBANK (FNL)(DC)(TY C)
CY 32,075.000 $30.000 $12.000 $18.700 $50.000
BLADING
HR 40.000 $150.000 $150.000 $99.000 $225.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 5,000.000 $2.000 $0.150 $0.250 $0.200
DRILL SEED (PERM_RURAL_CLAY)
SY 692,953.000 $0.200 $0.100 $0.130 $0.200
DRILL SEED (TEMP_WARM)
SY 173,241.000 $0.250 $0.050 $0.050 $0.200
DRILL SEED (TEMP_COOL)
SY 173,241.000 $0.250 $0.050 $0.050 $0.200
VEGETATIVE WATERING
TGL 5,884.200 $35.000 $15.000 $23.100 $20.000
FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS)
CY 54,553.000 $100.000 $95.000 $85.050 $75.000
REWORK BS MTL (TY C)(12")(ORD COMP)
SY 4,000.000 $8.000 $2.500 $4.400 $4.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 3,152.000 $255.000 $315.000 $363.000 $380.000
LIME TRT (SUBGRADE) (8")
SY 197,418.000 $12.000 $2.450 $3.300 $14.000
ASPH (RC-250)
GAL 38,374.000 $7.000 $5.000 $5.170 $5.500
AGGR (TY-E, GR-5)(SAC-B)
CY 1,382.000 $215.000 $120.000 $96.220 $138.000
AGGR (TY-PE, GR-4)(SAC-B)
CY 1,491.000 $195.000 $130.000 $142.940 $150.000
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 65,224.000 $4.500 $3.500 $4.350 $4.500
D-GR HMA TY-B PG64-22
TON 31,545.000 $98.000 $85.000 $96.800 $121.000
D-GR HMA TY-D SAC-B PG70-22
TON 44,677.000 $130.000 $90.000 $107.800 $144.000
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 10,807.000 $130.000 $100.000 $107.800 $150.000
TACK COAT
GAL 45,598.000 $3.000 $4.000 $3.300 $4.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 500.000 $95.000 $100.000 $105.270 $172.000
PLANE ASPH CONC PAV(0" TO 2")
SY 2,428.000 $2.000 $4.000 $3.300 $7.000
CUT & RESTORING PAV
SY 452.000 $90.000 $50.000 $230.000 $65.000
CEM STABIL BKFL
CY 1,153.000 $200.000 $123.000 $200.000 $165.000
TEMPORARY SPL SHORING
SF 3,796.000 $50.000 $25.000 $15.000 $30.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 180.000 $360.000 $250.000 $235.000 $350.000
DRILL SHAFT (TRF SIG POLE) (24 IN)
LF 18.000 $500.000 $225.000 $220.000 $400.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 108.000 $360.000 $300.000 $280.000 $585.000
RIPRAP (CONC)(5 IN)
CY 38.000 $600.000 $700.000 $630.000 $605.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 430.000 $250.000 $200.000 $200.000 $285.000
RAIL (TY T631)
LF 260.000 $80.000 $115.000 $100.000 $115.000
CONC BOX CULV (5 FT X 2 FT)
LF 924.000 $460.000 $550.000 $365.000 $1,000.000
CONC BOX CULV (5 FT X 3 FT)
LF 318.000 $470.000 $475.000 $420.000 $1,025.000
CONC BOX CULV (7 FT X 3 FT)
LF 569.000 $780.000 $850.000 $600.000 $1,600.000
RC PIPE (CL III)(18 IN)
LF 4,672.000 $100.000 $75.000 $65.000 $200.000
RC PIPE (CL III)(24 IN)
LF 1,778.000 $120.000 $95.000 $90.000 $240.000
WINGWALL (PW - 1) (HW=3 FT)
EA 1.000 $40,000.000 $10,000.000 $5,200.000 $7,500.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $40,000.000 $38,000.000 $24,000.000 $27,500.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $55,000.000 $40,000.000 $27,000.000 $30,250.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1)(C)
EA 21.000 $10,500.000 $5,500.000 $5,400.000 $1,500.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(6:1)(C)
EA 6.000 $10,300.000 $8,000.000 $8,500.000 $5,000.000
SET (TY I)(S= 7 FT)(HW= 4 FT)(6:1)(C)
EA 4.000 $13,000.000 $10,000.000 $11,000.000 $6,250.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 244.000 $2,000.000 $1,800.000 $2,400.000 $3,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 6.000 $2,800.000 $2,800.000 $3,800.000 $3,750.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 82.000 $2,300.000 $2,000.000 $3,900.000 $3,750.000
REMOV STR (BOX CULVERT)
EA 2.000 $17,000.000 $5,000.000 $17,500.000 $4,500.000
REMOV STR (SMALL)
EA 97.000 $1,600.000 $500.000 $500.000 $1,000.000
MOBILIZATION
LS 1.000 $3,000,000.000 $2,450,000.000 $2,223,897.210 $1,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 29.000 $3,500.000 $5,000.000 $7,696.470 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $15,000.000 $5,000.000 $20,500.000
TMA (STATIONARY)
DAY 435.000 $250.000 $250.000 $250.000 $215.000
TMA (MOBILE OPERATION)
DAY 60.000 $250.000 $25.000 $350.000 $675.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 1,540.000 $45.000 $30.000 $44.530 $80.000
ROCK FILTER DAMS (REMOVE)
LF 1,540.000 $13.000 $10.000 $40.900 $20.000
SANDBAGS FOR EROSION CONTROL
EA 100.000 $15.000 $10.000 $22.040 $35.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 8,590.000 $3.000 $3.500 $3.320 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 8,590.000 $1.500 $1.000 $0.850 $2.000
CONSTRUCTING DETOURS
SY 2,245.000 $125.000 $7.000 $13.200 $15.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 360.000 $75.000 $75.000 $45.000 $120.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 150.000 $50.000 $75.000 $64.000 $10.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 360.000 $30.000 $50.000 $25.000 $30.000
COLORED TEXTURED CONC (6")
SY 548.000 $225.000 $130.000 $90.000 $105.000
CONC CURB (TY II)
LF 730.000 $25.000 $25.000 $30.000 $25.000
DRIVEWAYS (CONC)
SY 1,033.000 $100.000 $95.000 $96.000 $120.000
DRIVEWAYS (ACP)
SY 346.000 $200.000 $75.000 $35.200 $90.000
DRIVEWAYS (SURF TREAT)
SY 7,115.000 $40.000 $45.000 $35.200 $25.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 58,220.000 $0.500 $0.200 $0.180 $0.200
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 52,768.000 $0.500 $0.200 $0.180 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 340.000 $30.000 $30.000 $28.990 $32.000
REMOVE METAL BEAM GUARD FENCE
LF 400.000 $5.000 $3.250 $3.100 $2.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $4,000.000 $3,679.000 $4,375.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $375.000 $375.000 $175.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 16.000 $2,000.000 $900.000 $1,450.000 $1,750.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $800.000 $900.000 $1,300.000 $1,125.000
CCA (INSTL)(N)(TL3)(WORK ZONE)
EA 4.000 $8,500.000 $10,000.000 $8,800.000 $8,800.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 13.000 $450.000 $500.000 $500.000 $550.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 45.000 $250.000 $175.000 $175.000 $275.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 7.000 $300.000 $185.000 $185.000 $300.000
IN RD IL (TY SA) 50T-8 (400W EQ) LED
EA 18.000 $3,500.000 $5,200.000 $5,112.000 $7,000.000
CONDT (PVC) (SCH 40) (2")
LF 4,585.000 $22.000 $10.250 $10.260 $25.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 1,715.000 $15.000 $14.500 $14.260 $30.000
CONDT (PVC) (SCH 40) (3")
LF 140.000 $13.500 $16.500 $16.400 $30.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 530.000 $35.000 $15.000 $14.980 $30.000
ELEC CONDR (NO.8) BARE
LF 3,450.000 $2.000 $2.250 $2.160 $4.000
ELEC CONDR (NO.8) INSULATED
LF 1,950.000 $2.400 $2.500 $2.380 $4.000
ELEC CONDR (NO.6) BARE
LF 3,555.000 $2.400 $2.750 $2.740 $4.000
ELEC CONDR (NO.6) INSULATED
LF 7,510.000 $2.600 $3.250 $3.070 $4.000
TRAY CABLE (4 CONDR) (12 AWG)
LF 4,071.000 $4.000 $3.250 $3.250 $4.000
GROUND BOX TY A (122311)W/APRON
EA 18.000 $1,350.000 $1,000.000 $985.000 $1,525.000
GROUND BOX TY D (162922)W/APRON
EA 16.000 $1,250.000 $1,150.000 $1,125.000 $2,150.000
REMOVE GROUND BOX
EA 3.000 $550.000 $50.000 $50.000 $350.000
REMOVE ELECTRICAL SERVICES
EA 2.000 $1,000.000 $100.000 $100.000 $600.000
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 2.000 $10,000.000 $8,500.000 $8,350.000 $11,250.000
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 1.000 $8,600.000 $8,000.000 $7,975.000 $11,250.000
ELC SRV TY T 120/240 000(NS)GS(N)SP(O)
EA 3.000 $8,600.000 $6,500.000 $6,490.000 $7,500.000
ALUMINUM SIGNS (TY A)
SF 57.000 $30.000 $34.000 $27.500 $35.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 4.000 $650.000 $750.000 $750.000 $925.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 13.000 $800.000 $725.000 $725.000 $935.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $950.000 $1,000.000 $1,000.000 $1,025.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 1.000 $1,000.000 $1,200.000 $1,200.000 $1,450.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 25.000 $450.000 $475.000 $465.000 $500.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 9.000 $500.000 $525.000 $520.000 $575.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 3.000 $750.000 $450.000 $400.000 $550.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 2.000 $200.000 $300.000 $300.000 $550.000
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
EA 4.000 $270.000 $100.000 $100.000 $120.000
REMOVE SM RD SN SUP&AM
EA 61.000 $100.000 $100.000 $100.000 $120.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 12.000 $30.000 $25.000 $25.000 $30.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 22.000 $60.000 $80.000 $76.000 $120.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 117,350.000 $1.000 $0.300 $0.300 $1.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 120.000 $12.000 $25.000 $25.000 $12.000
WK ZN PAV MRK REMOV (Y)6"(BRK)
LF 8,700.000 $1.600 $1.000 $0.880 $1.500
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 160,780.000 $1.000 $0.300 $0.300 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,890.000 $2.000 $1.000 $1.530 $1.250
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,890.000 $2.000 $1.000 $1.530 $1.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,880.000 $2.000 $1.200 $1.200 $1.000
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 13,926.000 $1.200 $0.900 $0.880 $1.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 58,220.000 $1.100 $0.750 $0.720 $1.000
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 12,792.000 $1.200 $0.900 $0.880 $1.000
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 59,818.000 $1.100 $0.750 $0.720 $1.000
PREFAB PM TY C (W)(24")(SLD)
LF 32.000 $15.000 $50.000 $50.000 $16.000
PREFAB PM TY C (W)(ARROW)
EA 68.000 $250.000 $125.000 $125.000 $295.000
PREFAB PM TY C (W)(WORD)
EA 8.000 $400.000 $275.000 $275.000 $350.000
REFL PAV MRKR TY I-C
EA 794.000 $11.000 $7.500 $7.500 $5.000
REFL PAV MRKR TY II-A-A
EA 1,672.000 $11.000 $7.500 $7.500 $5.000
ELIM EXT PM & MRKS (4")
LF 63,584.000 $0.500 $3.000 $0.370 $0.500
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $20,000.000 $17,000.000 $16,548.000 $18,750.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $8,000.000 $5,000.000 $5,000.000 $11,250.000
VEH SIG SEC (12")LED(GRN)
EA 16.000 $300.000 $350.000 $340.000 $450.000
VEH SIG SEC (12")LED(GRN ARW)
EA 6.000 $300.000 $350.000 $340.000 $450.000
VEH SIG SEC (12")LED(YEL)
EA 16.000 $300.000 $350.000 $340.000 $450.000
VEH SIG SEC (12")LED(YEL ARW)
EA 6.000 $300.000 $340.000 $340.000 $450.000
VEH SIG SEC (12")LED(RED)
EA 16.000 $300.000 $340.000 $340.000 $450.000
VEH SIG SEC (12")LED(RED ARW)
EA 6.000 $300.000 $340.000 $340.000 $450.000
BACKPLATE W/REFL BRDR(3 SEC)ALUM
EA 22.000 $180.000 $180.000 $180.000 $200.000
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 5,214.000 $3.400 $4.750 $4.640 $6.000
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 3.000 $5,300.000 $6,500.000 $6,355.000 $10,000.000
REMOVE RDSD FLASH BEACON ASSEMBLY
EA 1.000 $1,000.000 $150.000 $150.000 $1,000.000
INS TRF SIG PL AM(S)1 ARM(32')LUM
EA 3.000 $13,000.000 $14,125.000 $14,125.000 $21,150.000
INS TRF SIG PL AM(S)1 ARM(36')LUM
EA 3.000 $13,500.000 $15,500.000 $15,106.000 $21,150.000
INS TRF SIG PL AM(S)1 ARM(40')LUM
EA 1.000 $15,000.000 $15,500.000 $15,440.000 $21,150.000
INS TRF SIG PL AM(S)1 ARM(44')LUM
EA 1.000 $15,000.000 $16,000.000 $15,832.000 $21,150.000
INSTALL RADAR VEHICLE DETECTION SYSTEM
EA 14.000 $3,500.000 $10,000.000 $9,132.180 $11,750.000
FULL - WIDTH MOWING
AC 143.200 $40.000 $80.000 $70.000 $900.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $12,000.000 $5,000.000 $7,500.000 $17,500.000
Totals: $33,725,491.100 $24,999,762.050 $26,432,444.070 $34,387,651.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $500.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $40,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $41,500.00