WALLER BU 290H (0050-05-071)

Items: 17

County: WALLER
Length: 0.0000 MILES (26.2776 MILES)
Highway: BU 290H
District: HOUSTON
Control Number: 0050-05-071
DBE Goal: 0.0%
Project: STP 2026(935)HES
Guaranty: $89,000.00
Time: 305 WORKING DAYS
Engineer's Estimate: $4,454,020.25
Date: 08/05/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263023
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206808
Contract Type: FEDERAL
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 2 files available
Bidders (7)
E
Engineer's Estimate
$4,454,020.25
$3,894,237.41
Over/Under Est: -12.57% -$559,782.84
$4,026,662.28
Over/Under Est: -9.59% -$427,357.97
Amt Left: 3.4% $132,424.87
Over/Under Est: -6.92% -$308,390.33
Amt Left: 6.46% $251,392.51
Delta: -2.95% -$118,967.64
Over/Under Est: 3.7% $164,833.64
Amt Left: 18.61% $724,616.48
Delta: -11.42% -$473,223.97
Over/Under Est: 7.42% $330,531.25
Amt Left: 22.86% $890,314.09
Delta: -3.59% -$165,697.61
Over/Under Est: 14.02% $624,329.75
Amt Left: 30.41% $1,184,112.59
Delta: -6.14% -$293,798.50
$5,173,666.82
Over/Under Est: 16.16% $719,646.57
Amt Left: 32.85% $1,279,429.41
Delta: -1.88% -$95,316.82

Bid Items & Bid Tabulations

17 Total 0 of 17
WALLER  |  BU 290H  |  HOUSTON  |  0050-05-071  |  08/05/2026 1:00 PM CDT  |  $4,454,020.25  |  STP 2026(935)HES  |  HAZARD ELIM & SAFETY  |  305 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALBATROSS CONSTRUCTION LLC
SICE, INC.
THIRD COAST SERVICES LLC
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
ALLSTATE SIGNAL & CONSTRUCTION, LLC
FLORIDA TRAFFIC CONTROL DEVICES, INC.
CREACOM, INC.
MOBILIZATION
LS 1.000 $412,000.000 $174,594.880 $385,648.517 $414,562.990 $456,133.590 $75,000.000 $500,000.000 $338,412.720
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $4,500.000 $5,228.170 $2,769.810 $2,425.370 $3,599.760 $3,450.000 $4,500.000 $5,429.110
TMA (STATIONARY)
DAY 272.000 $300.000 $210.190 $176.854 $0.130 $242.210 $300.000 $83.000 $386.230
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,070.000 $3.000 $2.000 $1.737 $7.560 $3.540 $0.750 $3.100 $2.010
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,070.000 $0.750 $0.780 $0.684 $0.470 $1.180 $0.250 $1.100 $1.190
CONDT (PVC) (SCH 80) (2") (BORE)
LF 21,305.000 $17.500 $10.320 $7.985 $14.360 $12.270 $13.300 $12.750 $12.960
CONDT (PVC) (SCH 80) (2") (CONC ENCSE)
LF 129,140.000 $16.500 $16.210 $16.353 $15.520 $16.180 $21.130 $15.100 $20.870
CONDT (PVC) (SCH 80) (4") (BORE)
LF 145.000 $35.000 $36.640 $14.494 $24.540 $164.490 $101.260 $450.000 $294.610
CONDT (RM) (2")
LF 570.000 $32.000 $37.490 $33.094 $29.130 $90.030 $58.320 $180.000 $111.240
ELEC CONDR (NO.14) INSULATED
LF 150,300.000 $0.450 $0.910 $0.711 $0.850 $1.170 $0.550 $1.550 $0.760
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 209.000 $3,750.000 $3,135.250 $3,369.899 $3,368.420 $3,793.700 $4,701.000 $4,890.000 $4,804.430
FIBER OPTIC CBL (SINGLE-MODE)(12 FIBER)
LF 3,745.000 $1.750 $1.080 $1.341 $3.660 $2.010 $4.430 $3.250 $5.830
FIBER OPTIC CBL (SINGLE-MODE)(36 FIBER)
LF 155,135.000 $1.900 $2.050 $1.851 $1.820 $2.270 $1.740 $3.800 $1.880
FIBER OPTIC FUSION SPLICE
EA 270.000 $75.000 $29.120 $30.273 $20.040 $47.200 $138.760 $93.000 $26.130
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 28.000 $1,350.000 $915.690 $1,557.394 $1,273.380 $2,249.280 $882.720 $1,800.000 $987.180
FO SPLICE ENCLOSURE (TYPE 1)
EA 27.000 $1,550.000 $921.380 $746.700 $3,266.240 $3,110.680 $899.670 $1,744.000 $1,120.880
SUBSURFACE UTIL LOCATE (OUTSIDE RDBED)
EA 54.000 $900.000 $227.500 $595.577 $218.900 $1,102.180 $875.000 $930.000 $180.990
Totals: $4,454,020.250 $3,894,237.410 $4,026,662.261 $4,145,629.920 $4,618,853.890 $4,784,551.500 $5,078,350.000 $5,173,666.820
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $12,000.00