WALLER BU 290H (0050-05-071)
Items: 17
County: WALLER
Length: 0.0000 MILES (26.2776 MILES)
Highway: BU 290H
District: HOUSTON
Control Number: 0050-05-071
DBE Goal: 0.0%
Project: STP 2026(935)HES
Guaranty: $89,000.00
Time: 305 WORKING DAYS
Engineer's Estimate: $4,454,020.25
Date: 08/05/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263023
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206808
Contract Type: FEDERAL
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
EUGENE AMPOMAH
KIALEE GBOSI
WALLER BU 290H (0050-05-071)
Project Name: N/A
Project: STP 2026(935)HES
Engineer's Estimate: $1,971,805.50
Length: 0.0000 MILES (9.8031 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: SH 159 (10ST STREET)
Limits To: HARRIS COUNTY LINE
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
HARRIS BU 90U (0028-01-109)
Project Name: BU 90U, FROM SHELDON TO CHAMPION PAPER
Project: STP 2026(935)HES
Engineer's Estimate: $171,349.50
Length: N/A (1.1096 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: SHELDON ROAD
Limits To: CHAMPION PAPER DRIVE
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
HARRIS BU 290H (0050-06-106)
Project Name: BU 290H, FROM SH 159 TO WARREN RANCH _ B
Project: STP 2026(935)HES
Engineer's Estimate: $666,700.50
Length: N/A (4.9477 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: WALLER COUNTY LINE
Limits To: WARREN RANCH DRIVE
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
MONTGOMERY FM 149 (0720-02-105)
Project Name: FM 149, FROM FM 1097 TO SH 105
Project: STP 2026(935)HES
Engineer's Estimate: $176,288.25
Length: N/A (1.0829 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: FM 1097
Limits To: SH 105
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
HARRIS FM 1942 (1812-01-024)
Project Name: FM 1942, FROM CROSBY LYNCHBURG TO N MAIN
Project: STP 2026(935)HES
Engineer's Estimate: $871,111.50
Length: N/A (5.9001 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: CROSBY LYNCHBURG ROAD
Limits To: NORTH MAIN STREET
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
MONTGOMERY FM 3083 (3158-01-047)
Project Name: HOU_FM 3083, FM 2090-FM 1485
Project: STP 2026(935)HES
Engineer's Estimate: $338,688.50
Length: N/A (1.9669 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: FM 2090
Limits To: FM 1485
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
MONTGOMERY SH 242 (3538-01-063)
Project Name: SH 242, FROM IH 45 TO GREAT OAKS
Project: STP 2026(935)HES
Engineer's Estimate: $178,462.50
Length: N/A (0.9713 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: IH 45
Limits To: GREAT OAKS DRIVE
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
MONTGOMERY SH 242 (3538-01-064)
Project Name: SH 242, FROM LEXINGTON TO HARPER'S TRACE
Project: STP 2026(935)HES
Engineer's Estimate: $79,614.00
Length: N/A (0.4960 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: LEXINGTON DRIVE
Limits To: HARPER'S TRACE
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
Bidders (7)
E
Engineer's Estimate
$4,454,020.25
1
Awarded
$3,894,237.41
Over/Under Est:
-12.57%
-$559,782.84
$4,026,662.28
Over/Under Est:
-9.59%
-$427,357.97
Amt Left:
3.4%
$132,424.87
$4,145,629.92
Over/Under Est:
-6.92%
-$308,390.33
Amt Left:
6.46%
$251,392.51
Delta:
-2.95%
-$118,967.64
$4,618,853.89
Over/Under Est:
3.7%
$164,833.64
Amt Left:
18.61%
$724,616.48
Delta:
-11.42%
-$473,223.97
$4,784,551.50
Over/Under Est:
7.42%
$330,531.25
Amt Left:
22.86%
$890,314.09
Delta:
-3.59%
-$165,697.61
$5,078,350.00
Over/Under Est:
14.02%
$624,329.75
Amt Left:
30.41%
$1,184,112.59
Delta:
-6.14%
-$293,798.50
$5,173,666.82
Over/Under Est:
16.16%
$719,646.57
Amt Left:
32.85%
$1,279,429.41
Delta:
-1.88%
-$95,316.82
Bid Items & Bid Tabulations
17
Total
0 of 17
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $12,000.00 |