REMOVING STAB BASE & ASPH PAV (0-6")
|
SY
|
5,656.000
|
$9.300
|
$6.000
|
$10.500
|
$3.250
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,041.000
|
$7.100
|
$7.000
|
$31.000
|
$6.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
4,163.000
|
$2.910
|
$27.000
|
$32.500
|
$25.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
60,554.000
|
$0.350
|
$0.140
|
$0.110
|
$0.130
|
|
|
BROADCAST SEED (TEMP)(WARM OR COOL)
|
SY
|
60,554.000
|
$0.550
|
$0.140
|
$0.070
|
$0.130
|
|
|
VEGETATIVE WATERING
|
MG
|
511.000
|
$31.040
|
$25.000
|
$27.500
|
$28.000
|
|
|
SUPERPAVE MIXTURES SP-D PG64-22
|
TON
|
276.000
|
$74.000
|
$95.000
|
$230.000
|
$280.000
|
|
|
TBPFC (MEMBRANE)
|
GAL
|
189,030.000
|
$1.700
|
$3.470
|
$3.700
|
$3.340
|
|
|
TBPFC (ASPHALT)(PG 76-22)
|
TON
|
2,448.000
|
$101.000
|
$790.000
|
$685.000
|
$748.000
|
|
|
TBPFC (AGGREGATE) (SAC-A)
|
TON
|
38,357.000
|
$101.000
|
$61.000
|
$94.000
|
$81.500
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
426,228.000
|
$1.190
|
$1.450
|
$1.300
|
$1.640
|
|
|
FULL - DEPTH REPAIR CRCP (8")
|
SY
|
375.000
|
$275.000
|
$242.000
|
$370.000
|
$162.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
859.000
|
$490.000
|
$700.000
|
$640.000
|
$500.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
1,560.000
|
$490.000
|
$439.000
|
$400.000
|
$500.000
|
|
|
ADJUSTING MANHOLES
|
EA
|
2.000
|
$599.000
|
$250.000
|
$2,100.000
|
$3,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$784,975.250
|
$200,000.000
|
$430,000.000
|
$1,017,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$10,000.000
|
$5,700.000
|
$20,000.000
|
$32,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
420.000
|
$5.000
|
$11.700
|
$3.450
|
$11.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
420.000
|
$2.500
|
$2.340
|
$1.050
|
$2.200
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
213,081.000
|
$0.110
|
$0.140
|
$0.090
|
$0.110
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
14,850.000
|
$17.850
|
$23.400
|
$21.500
|
$22.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
34.000
|
$1,750.000
|
$2,223.000
|
$2,000.000
|
$2,100.000
|
|
|
MTL W-BEAM GD FEN ADJUSTMENT
|
LF
|
9,037.000
|
$15.000
|
$8.190
|
$7.450
|
$7.800
|
|
|
MTL THRIE-BEAM GD FEN ADJUSTMENT
|
LF
|
338.000
|
$30.000
|
$23.400
|
$21.500
|
$22.000
|
|
|
TRANSITION ADJUSTMENT
|
EA
|
8.000
|
$1,100.000
|
$585.000
|
$530.000
|
$550.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
15.000
|
$1,007.000
|
$1,140.750
|
$1,000.000
|
$1,075.000
|
|
|
MTL BM GD FEN TRANS (NON - SYM)
|
EA
|
15.000
|
$794.000
|
$848.250
|
$770.000
|
$790.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL ADJUSTMENT
|
EA
|
6.000
|
$300.000
|
$468.000
|
$425.000
|
$440.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
15,225.000
|
$3.400
|
$2.340
|
$2.150
|
$2.200
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
15.000
|
$274.000
|
$292.500
|
$265.000
|
$275.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
6.000
|
$200.000
|
$292.500
|
$265.000
|
$275.000
|
|
|
CABLE BARRIER SYSTEM (TL-4)
|
LF
|
44,598.000
|
$17.000
|
$10.000
|
$9.150
|
$9.500
|
|
|
CABLE BARRIER TERMINAL SECTION (TL-4)
|
EA
|
16.000
|
$3,000.000
|
$2,925.000
|
$2,700.000
|
$2,750.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
35.000
|
$2,300.000
|
$3,100.000
|
$2,800.000
|
$2,900.000
|
|
|
GUARDRAIL END TREATMENT (MOVE & RESET)
|
EA
|
16.000
|
$870.000
|
$1,755.000
|
$1,600.000
|
$1,650.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
35.000
|
$235.000
|
$292.500
|
$265.000
|
$275.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
|
EA
|
670.000
|
$19.000
|
$11.700
|
$10.500
|
$11.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
32,228.000
|
$0.210
|
$0.360
|
$0.330
|
$0.340
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
9,720.000
|
$1.090
|
$1.000
|
$1.050
|
$1.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
28,416.000
|
$0.780
|
$0.940
|
$0.850
|
$0.880
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
32,228.000
|
$0.380
|
$0.470
|
$0.430
|
$0.440
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
123,999.000
|
$0.210
|
$0.340
|
$0.310
|
$0.320
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
129,034.000
|
$0.250
|
$0.340
|
$0.310
|
$0.320
|
|
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
|
LF
|
1,060.000
|
$2.720
|
$2.340
|
$2.150
|
$2.200
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
44.000
|
$13.490
|
$14.630
|
$13.500
|
$13.750
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
4.000
|
$200.000
|
$245.000
|
$225.000
|
$230.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
1,632.000
|
$2.540
|
$4.080
|
$3.700
|
$3.850
|
|
|
JT / CRCK ROUT / SEAL(RUBBER - ASPHALT)
|
LF
|
3,171.000
|
$2.000
|
$2.500
|
$21.500
|
$5.500
|
|
|
TMA (STATIONARY)
|
DAY
|
111.000
|
$175.000
|
$117.000
|
$105.000
|
$320.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
48.000
|
$53.020
|
$40.000
|
$100.000
|
$50.000
|
|
Totals: |
$8,924,359.340
|
$8,831,585.370
|
$10,146,535.520
|
$10,445,062.350
|