PREPARING ROW
|
STA
|
7.000
|
$1,650.000
|
$4,000.000
|
$3,000.000
|
$1,750.000
|
$10,000.000
|
$21,500.000
|
$2,000.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (10")
|
SY
|
2,147.000
|
$7.500
|
$9.000
|
$20.000
|
$15.000
|
$20.000
|
$20.000
|
$16.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
133.000
|
$10.000
|
$24.000
|
$20.000
|
$40.000
|
$25.000
|
$20.000
|
$75.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
2,124.000
|
$15.000
|
$18.000
|
$20.000
|
$18.000
|
$25.000
|
$30.000
|
$22.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
1,425.000
|
$15.000
|
$18.000
|
$35.000
|
$35.000
|
$25.000
|
$35.000
|
$22.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
6,100.000
|
$5.000
|
$2.500
|
$3.000
|
$1.000
|
$4.000
|
$6.000
|
$8.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
6,100.000
|
$0.250
|
$0.410
|
$0.500
|
$0.160
|
$0.400
|
$2.000
|
$2.000
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
SY
|
3,050.000
|
$0.250
|
$0.480
|
$0.400
|
$0.120
|
$0.400
|
$2.000
|
$1.000
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
SY
|
3,050.000
|
$0.250
|
$0.430
|
$0.400
|
$0.130
|
$0.400
|
$2.000
|
$1.000
|
|
|
VEGETATIVE WATERING
|
MG
|
51.200
|
$40.000
|
$50.000
|
$1.000
|
$30.000
|
$100.000
|
$50.000
|
$25.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
4,417.000
|
$2.000
|
$1.110
|
$1.200
|
$1.850
|
$3.000
|
$6.500
|
$3.500
|
|
|
SOIL RETENTION BLANKETS (CL 2) (TY H)
|
SY
|
1,683.000
|
$6.000
|
$4.300
|
$5.000
|
$5.500
|
$8.000
|
$8.000
|
$2.000
|
|
|
CEMENT
|
TON
|
23.000
|
$200.000
|
$300.000
|
$250.000
|
$300.000
|
$220.000
|
$250.000
|
$150.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
2,118.000
|
$5.000
|
$12.000
|
$25.000
|
$14.000
|
$16.000
|
$6.000
|
$35.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
530.000
|
$5.000
|
$15.000
|
$10.000
|
$14.000
|
$20.000
|
$12.000
|
$12.000
|
|
|
D-GR HMA(SQ) TY-B PG64-22
|
TON
|
699.000
|
$90.000
|
$152.000
|
$160.000
|
$141.000
|
$165.000
|
$145.000
|
$200.000
|
|
|
D-GR HMA(SQ) TY-D SAC-B PG64-22
|
TON
|
233.000
|
$140.000
|
$198.000
|
$160.000
|
$160.000
|
$190.000
|
$165.000
|
$200.000
|
|
|
TACK COAT
|
GAL
|
550.000
|
$3.500
|
$4.000
|
$10.000
|
$4.000
|
$10.000
|
$10.000
|
$35.000
|
|
|
CEM STABIL BKFL
|
CY
|
88.000
|
$200.000
|
$200.000
|
$200.000
|
$280.000
|
$250.000
|
$350.000
|
$125.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
50.000
|
$150.000
|
$200.000
|
$200.000
|
$287.000
|
$250.000
|
$350.000
|
$125.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
870.000
|
$25.000
|
$75.000
|
$60.000
|
$111.000
|
$40.000
|
$60.000
|
$35.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
280.000
|
$275.000
|
$252.000
|
$240.000
|
$260.000
|
$260.000
|
$285.000
|
$295.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
47.800
|
$2,000.000
|
$1,400.000
|
$1,500.000
|
$1,500.000
|
$2,000.000
|
$1,250.000
|
$1,800.000
|
|
|
CL F CONC (MISC)
|
CY
|
23.800
|
$1,800.000
|
$750.000
|
$550.000
|
$545.000
|
$2,000.000
|
$2,000.000
|
$1,800.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
3,060.000
|
$40.000
|
$34.000
|
$35.000
|
$40.000
|
$28.000
|
$20.000
|
$45.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
73.700
|
$1,000.000
|
$800.000
|
$850.000
|
$720.000
|
$950.000
|
$1,250.000
|
$1,900.000
|
|
|
PRESTR CONC GIRDER (TX34)
|
LF
|
536.520
|
$180.000
|
$230.000
|
$260.000
|
$243.000
|
$210.000
|
$180.000
|
$275.000
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
642.000
|
$180.000
|
$110.000
|
$150.000
|
$170.000
|
$160.000
|
$200.000
|
$200.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
28.000
|
$700.000
|
$500.000
|
$500.000
|
$962.000
|
$700.000
|
$650.000
|
$900.000
|
|
|
RAIL (TY T223)(HPC)
|
LF
|
224.000
|
$175.000
|
$150.000
|
$120.000
|
$152.000
|
$125.000
|
$185.000
|
$150.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
78.000
|
$90.000
|
$110.000
|
$75.000
|
$105.000
|
$100.000
|
$100.000
|
$150.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
180.000
|
$30.000
|
$150.000
|
$340.000
|
$250.000
|
$500.000
|
$300.000
|
$125.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$130,000.000
|
$157,000.000
|
$145,000.000
|
$155,000.000
|
$190,000.000
|
$200,000.000
|
$190,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
10.000
|
$10,000.000
|
$5,500.000
|
$4,000.000
|
$9,000.000
|
$8,000.000
|
$9,500.000
|
$25,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
75.000
|
$50.000
|
$65.000
|
$5.000
|
$60.000
|
$45.000
|
$30.000
|
$45.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
75.000
|
$10.000
|
$10.000
|
$1.000
|
$15.000
|
$10.000
|
$15.000
|
$15.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,350.000
|
$3.000
|
$2.500
|
$1.000
|
$2.250
|
$5.000
|
$4.000
|
$6.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,350.000
|
$1.000
|
$1.150
|
$1.000
|
$1.000
|
$2.000
|
$2.000
|
$2.500
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
360.000
|
$11.000
|
$6.000
|
$8.000
|
$6.000
|
$15.000
|
$18.000
|
$12.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
360.000
|
$1.000
|
$1.250
|
$1.000
|
$1.000
|
$2.000
|
$9.000
|
$5.000
|
|
|
PTB (FRN&INSTL)(F SHAPE)(TY 1) OR (STL)
|
LF
|
750.000
|
$70.000
|
$83.000
|
$90.000
|
$53.000
|
$75.000
|
$70.000
|
$85.000
|
|
|
PTB (MOVE)(F SHAPE)(TY 1) OR (STL)
|
LF
|
750.000
|
$7.500
|
$11.000
|
$20.000
|
$10.000
|
$20.000
|
$30.000
|
$15.000
|
|
|
PTB (REMOVE)(F SHAPE)(TY 1) OR (STL)
|
LF
|
750.000
|
$8.000
|
$17.000
|
$50.000
|
$10.000
|
$25.000
|
$30.000
|
$35.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
300.000
|
$23.000
|
$22.000
|
$22.000
|
$20.000
|
$30.000
|
$25.000
|
$25.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,000.000
|
$1,600.000
|
$1,600.000
|
$1,500.000
|
$2,000.000
|
$1,850.000
|
$2,500.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
575.000
|
$3.000
|
$3.490
|
$5.000
|
$3.000
|
$5.000
|
$3.000
|
$15.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,700.000
|
$2,700.000
|
$2,800.000
|
$3,000.000
|
$3,000.000
|
$2,850.000
|
$2,500.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$300.000
|
$250.000
|
$500.000
|
$225.000
|
$350.000
|
$1,500.000
|
$800.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,650.000
|
$2,725.000
|
$3,500.000
|
$3,000.000
|
$3,500.000
|
$5,000.000
|
$8,000.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$1,050.000
|
$1,125.000
|
$1,000.000
|
$1,000.000
|
$3,000.000
|
$2,500.000
|
$2,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$10,000.000
|
$9,900.000
|
$10,000.000
|
$9,150.000
|
$10,000.000
|
$22,500.000
|
$30,000.000
|
|
|
WIRE FENCE (TY D)
|
LF
|
130.000
|
$25.000
|
$15.000
|
$20.000
|
$50.000
|
$16.000
|
$10.000
|
$25.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
4.000
|
$25.000
|
$39.000
|
$40.000
|
$20.000
|
$20.000
|
$100.000
|
$200.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
6.000
|
$25.000
|
$39.000
|
$40.000
|
$25.000
|
$75.000
|
$100.000
|
$200.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
180.000
|
$4.000
|
$5.800
|
$10.000
|
$5.000
|
$8.000
|
$15.000
|
$19.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
3,544.000
|
$1.000
|
$0.940
|
$1.000
|
$0.850
|
$1.200
|
$2.000
|
$5.000
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
20.000
|
$9.000
|
$17.600
|
$16.000
|
$13.000
|
$18.000
|
$20.000
|
$100.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
7,200.000
|
$1.000
|
$0.930
|
$1.000
|
$0.850
|
$1.200
|
$2.000
|
$3.500
|
|
|
PAVEMENT SEALER 4"
|
LF
|
360.000
|
$0.250
|
$2.350
|
$4.000
|
$2.000
|
$4.000
|
$2.000
|
$16.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
1,380.000
|
$0.400
|
$0.970
|
$1.000
|
$0.850
|
$1.200
|
$2.000
|
$6.000
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
4,610.000
|
$0.400
|
$0.930
|
$1.000
|
$0.850
|
$1.200
|
$2.000
|
$3.000
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
2,545.000
|
$0.400
|
$0.950
|
$1.000
|
$0.850
|
$1.200
|
$2.000
|
$5.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
90.000
|
$4.000
|
$22.400
|
$22.000
|
$20.000
|
$25.000
|
$15.000
|
$12.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
5,800.000
|
$0.600
|
$1.090
|
$2.000
|
$1.000
|
$1.500
|
$2.000
|
$5.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
360.000
|
$0.250
|
$2.360
|
$3.000
|
$2.000
|
$3.000
|
$2.000
|
$12.000
|
|
|
INTRLCK ART CONC BLKS W/ CABLE (6" MIN)
|
SF
|
6,735.000
|
$20.000
|
$20.000
|
$15.000
|
$23.000
|
$26.000
|
$36.000
|
$8.000
|
|
|
STEEL FENCE (REMOVE)
|
LF
|
91.000
|
$14.000
|
$28.990
|
$6.000
|
$15.000
|
$10.000
|
$30.000
|
$15.000
|
|
|
STEEL FENCE (INSTALL)
|
LF
|
130.000
|
$50.000
|
$125.000
|
$115.000
|
$40.000
|
$50.000
|
$100.000
|
$25.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
32.000
|
$85.000
|
$125.000
|
$150.000
|
$310.000
|
$75.000
|
$850.000
|
$500.000
|
|
Totals: |
$1,523,928.100
|
$1,584,998.820
|
$1,691,676.800
|
$1,738,793.460
|
$1,954,447.000
|
$2,224,394.100
|
$2,305,478.500
|