REWORK BS MTL (TY C)(12")(ORD COMP)
|
STA
|
4.000
|
$3,500.000
|
$15,500.000
|
$5,400.000
|
$10,000.000
|
|
|
D-GR HMA(SQ) TY-D PG76-22
|
TON
|
1,147.000
|
$75.000
|
$194.000
|
$147.000
|
$150.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 6")
|
SY
|
4,920.000
|
$5.000
|
$6.000
|
$5.000
|
$12.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
43.800
|
$150.000
|
$500.000
|
$230.000
|
$300.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
4.000
|
$1,000.000
|
$8,000.000
|
$3,200.000
|
$8,000.000
|
|
|
CL C CONC (CAP)(HPC)(EXTEND)
|
CY
|
7.600
|
$1,000.000
|
$4,300.000
|
$3,017.000
|
$8,000.000
|
|
|
CL C CONC (VEH DEFL WALL)(HPC)
|
CY
|
65.000
|
$1,000.000
|
$2,700.000
|
$1,100.000
|
$1,200.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
10,556.000
|
$30.000
|
$38.000
|
$26.000
|
$40.000
|
|
|
APPROACH SLAB (MOD)
|
CY
|
90.000
|
$1,100.000
|
$650.000
|
$751.000
|
$800.000
|
|
|
PENETRATING CONCRETE SURFACE TREATMENT
|
SY
|
391.000
|
$15.000
|
$18.000
|
$30.000
|
$15.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
1,762.000
|
$300.000
|
$115.000
|
$137.000
|
$250.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
149.000
|
$510.000
|
$600.000
|
$430.000
|
$650.000
|
|
|
MULTI-LAYER POLYMER OVERLAY
|
SY
|
1,540.000
|
$75.000
|
$49.000
|
$75.000
|
$80.000
|
|
|
STR STEEL (DIAPHRAGM & STIFFENER)
|
LB
|
3,468.000
|
$14.000
|
$10.000
|
$8.000
|
$15.000
|
|
|
STR STEEL (SHEAR CONNECTOR)
|
LB
|
1,160.000
|
$7.000
|
$30.000
|
$6.000
|
$15.000
|
|
|
SPOT CLEAN & PAINT EXT STR(SPL PRT SYS)
|
LS
|
1.000
|
$100,000.000
|
$290,000.000
|
$254,500.000
|
$350,000.000
|
|
|
RAIL (TY SSTR)(HPC)
|
LF
|
920.000
|
$50.000
|
$90.000
|
$82.000
|
$150.000
|
|
|
RETROFIT RAIL (TY SSTR)
|
LF
|
629.000
|
$130.000
|
$200.000
|
$170.000
|
$350.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
|
LF
|
104.000
|
$85.000
|
$50.000
|
$150.000
|
$150.000
|
|
|
HEADER TYPE EXPANSION JOINT
|
LF
|
148.000
|
$100.000
|
$25.000
|
$125.000
|
$200.000
|
|
|
RAISING EXIST STRUCT
|
LS
|
1.000
|
$23,200.000
|
$275,000.000
|
$197,600.000
|
$600,000.000
|
|
|
REMOV STR (BRIDGE SLAB)
|
EA
|
2.000
|
$200,000.000
|
$85,000.000
|
$215,915.000
|
$300,000.000
|
|
|
REMOVE STR (CONC)
|
EA
|
4.000
|
$2,000.000
|
$3,000.000
|
$5,500.000
|
$30,000.000
|
|
|
REMOV STR (BACKWALL)
|
EA
|
2.000
|
$10,000.000
|
$10,000.000
|
$11,000.000
|
$10,000.000
|
|
|
REMOV STR (WINGWALL PARAPET)
|
EA
|
8.000
|
$1,100.000
|
$400.000
|
$1,500.000
|
$7,000.000
|
|
|
REMOVE STR (RAIL)
|
LF
|
760.000
|
$45.000
|
$5.000
|
$40.000
|
$50.000
|
|
|
REMOVE STR (BENT CAP)
|
EA
|
4.000
|
$3,000.000
|
$3,100.000
|
$11,000.000
|
$30,000.000
|
|
|
ADJUST STL SHOES
|
EA
|
32.000
|
$1,000.000
|
$250.000
|
$600.000
|
$4,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$249,933.340
|
$150,000.000
|
$330,000.000
|
$550,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$6,000.000
|
$8,000.000
|
$18,500.000
|
$7,000.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
680.000
|
$26.500
|
$90.000
|
$75.000
|
$70.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
2,040.000
|
$9.000
|
$10.000
|
$6.000
|
$10.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
680.000
|
$9.000
|
$40.000
|
$7.000
|
$15.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
2,325.000
|
$20.000
|
$18.000
|
$20.000
|
$25.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
16.000
|
$2,000.000
|
$1,500.000
|
$1,275.000
|
$1,500.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
2,745.000
|
$4.000
|
$2.100
|
$3.000
|
$5.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
6.000
|
$280.000
|
$250.000
|
$200.000
|
$350.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$300.000
|
$200.000
|
$150.000
|
$350.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
16.000
|
$2,450.000
|
$2,250.000
|
$2,250.000
|
$2,800.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
14.000
|
$300.000
|
$200.000
|
$200.000
|
$350.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
4.000
|
$16,500.000
|
$6,000.000
|
$6,725.000
|
$10,000.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
3.000
|
$1,700.000
|
$500.000
|
$2,500.000
|
$4,000.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
1.000
|
$1,000.000
|
$500.000
|
$1,000.000
|
$2,500.000
|
|
|
CRASH CUSHION ATTEN (INSTALL) (TRACC)
|
EA
|
1.000
|
$16,500.000
|
$20,000.000
|
$18,125.000
|
$10,000.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
2.000
|
$1,500.000
|
$1,600.000
|
$1,863.000
|
$1,000.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
16.000
|
$40.000
|
$26.000
|
$18.000
|
$5.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
16.000
|
$40.000
|
$27.000
|
$18.000
|
$5.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
24.000
|
$50.000
|
$30.000
|
$25.000
|
$25.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
29.000
|
$50.000
|
$33.000
|
$23.000
|
$25.000
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY W
|
EA
|
486.000
|
$1.500
|
$40.000
|
$35.000
|
$6.000
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
|
EA
|
162.000
|
$0.200
|
$40.000
|
$35.000
|
$6.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
280.000
|
$0.500
|
$2.000
|
$2.000
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
6,380.000
|
$0.500
|
$2.000
|
$2.000
|
$1.000
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
6,380.000
|
$0.500
|
$2.000
|
$2.000
|
$1.000
|
|
REFL PAV MRKR TY I-A
|
EA
|
54.000
|
$3.000
|
$6.000
|
$6.000
|
$5.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
176.000
|
$3.000
|
$6.000
|
$6.000
|
$5.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
20.000
|
$3.000
|
$6.000
|
$6.000
|
$5.000
|
|
|
REP STL BRIDGE MEMBERS
|
LS
|
1.000
|
$6,000.000
|
$30,000.000
|
$20,000.000
|
$100,000.000
|
|
|
BRIDGE JOINT REPAIR (ARMOR)
|
LF
|
158.000
|
$100.000
|
$350.000
|
$310.000
|
$800.000
|
|
Totals: |
$2,821,266.740
|
$3,149,693.500
|
$3,305,625.200
|
$5,294,268.000
|