PREPARING ROW
|
STA
|
61.000
|
$3,500.000
|
$1,000.000
|
$950.700
|
$2,700.000
|
$3,600.000
|
$24,030.930
|
$28,000.000
|
$1,000.000
|
$1,250.000
|
$434.360
|
$33,750.000
|
|
|
TREE PROTECTION (INSTALL)
|
EA
|
15.000
|
$250.000
|
$300.000
|
$1,080.000
|
$700.000
|
$550.000
|
$500.000
|
$685.330
|
$500.000
|
$200.000
|
$78.180
|
$300.000
|
|
|
TREE PROTECTION (REMOVE)
|
EA
|
15.000
|
$50.000
|
$100.000
|
$540.000
|
$500.000
|
$100.000
|
$100.000
|
$68.530
|
$250.000
|
$10.000
|
$12.410
|
$250.000
|
|
|
REMOV CONC (RIPRAP)
|
SY
|
700.000
|
$22.000
|
$20.000
|
$17.500
|
$16.000
|
$18.000
|
$17.370
|
$19.910
|
$30.000
|
$14.000
|
$12.200
|
$25.000
|
|
|
REMOV CONC (MISC)
|
CY
|
13.000
|
$130.000
|
$20.000
|
$463.500
|
$200.000
|
$17.500
|
$200.000
|
$422.870
|
$330.000
|
$100.000
|
$12.250
|
$150.000
|
|
|
RMV (8"-12") TRT/UNTRT BASE & ASPH PAV
|
SY
|
18,680.000
|
$12.000
|
$6.000
|
$6.440
|
$7.000
|
$9.500
|
$5.450
|
$8.000
|
$6.500
|
$12.500
|
$6.800
|
$6.500
|
|
|
EXCAV (ROADWAY)
|
CY
|
24,332.000
|
$16.000
|
$12.000
|
$12.000
|
$10.000
|
$10.750
|
$7.170
|
$13.000
|
$25.000
|
$20.000
|
$9.200
|
$8.000
|
|
|
EMBANK (FNL)(DC)(TY C)
|
CY
|
53,856.000
|
$16.000
|
$26.500
|
$16.920
|
$18.000
|
$12.000
|
$16.000
|
$20.000
|
$25.000
|
$30.000
|
$47.730
|
$23.000
|
|
|
FURN & PLACE TOPSOIL (6")
|
SY
|
50,414.000
|
$1.000
|
$2.500
|
$2.720
|
$0.500
|
$1.750
|
$1.130
|
$2.000
|
$4.750
|
$5.000
|
$9.930
|
$2.470
|
|
|
DRILL SEED (PERM_RURAL_CLAY)
|
SY
|
50,414.000
|
$0.250
|
$0.320
|
$0.300
|
$0.320
|
$0.500
|
$0.300
|
$0.750
|
$0.300
|
$0.550
|
$0.170
|
$0.390
|
|
|
DRILL SEED (TEMP_WARM_COOL)
|
SY
|
39,470.000
|
$0.250
|
$0.300
|
$0.280
|
$0.300
|
$0.300
|
$0.280
|
$0.570
|
$0.300
|
$0.500
|
$0.100
|
$0.300
|
|
|
SOIL RET BLKT(SL_STEEP_CLAY_SHORT)
|
SY
|
4,407.000
|
$1.000
|
$2.150
|
$2.000
|
$2.100
|
$2.000
|
$2.000
|
$4.000
|
$2.000
|
$5.000
|
$3.040
|
$4.580
|
|
|
PROOF ROLLING
|
HR
|
270.000
|
$150.000
|
$90.000
|
$77.000
|
$120.000
|
$105.000
|
$120.870
|
$150.000
|
$80.000
|
$50.000
|
$140.110
|
$75.000
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
4,503.000
|
$80.000
|
$68.000
|
$50.600
|
$78.000
|
$130.000
|
$33.140
|
$68.000
|
$100.000
|
$85.000
|
$91.180
|
$55.000
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
5,296.000
|
$5.400
|
$5.250
|
$5.090
|
$6.000
|
$5.000
|
$5.060
|
$6.850
|
$6.000
|
$5.000
|
$6.560
|
$6.000
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
13,483.000
|
$2.000
|
$4.000
|
$3.680
|
$6.000
|
$5.000
|
$5.000
|
$8.220
|
$4.500
|
$15.000
|
$5.320
|
$6.000
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
11,416.000
|
$125.000
|
$110.250
|
$78.120
|
$106.000
|
$110.000
|
$106.170
|
$125.000
|
$115.000
|
$150.000
|
$125.740
|
$185.000
|
|
|
D-GR HMA TY-C SAC-A PG76-22
|
TON
|
2,746.000
|
$135.000
|
$150.150
|
$97.560
|
$138.000
|
$150.000
|
$144.590
|
$146.000
|
$160.000
|
$150.000
|
$163.310
|
$210.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
20.000
|
$150.000
|
$200.000
|
$200.000
|
$100.000
|
$275.000
|
$320.000
|
$500.000
|
$105.000
|
$150.000
|
$95.320
|
$350.000
|
|
|
CEM STABIL BKFL
|
CY
|
442.000
|
$100.000
|
$155.000
|
$275.000
|
$140.000
|
$290.000
|
$201.640
|
$290.000
|
$140.000
|
$185.000
|
$153.890
|
$95.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
43.000
|
$8.000
|
$20.000
|
$15.000
|
$22.000
|
$2.000
|
$1.040
|
$170.000
|
$22.000
|
$15.000
|
$10.600
|
$1.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
2,489.000
|
$25.000
|
$25.000
|
$15.000
|
$24.000
|
$24.000
|
$82.440
|
$0.010
|
$25.000
|
$25.000
|
$16.880
|
$20.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
180.000
|
$300.000
|
$350.000
|
$184.290
|
$180.000
|
$170.000
|
$188.110
|
$200.000
|
$185.000
|
$200.000
|
$186.150
|
$175.000
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
500.000
|
$400.000
|
$550.000
|
$432.390
|
$390.000
|
$412.000
|
$443.320
|
$440.000
|
$400.000
|
$550.000
|
$434.360
|
$430.000
|
|
|
DRILL SHAFT (48 IN)
|
LF
|
760.000
|
$550.000
|
$625.000
|
$509.680
|
$490.000
|
$485.000
|
$508.400
|
$600.000
|
$500.000
|
$600.000
|
$434.360
|
$500.000
|
|
|
DRILL SHAFT (66 IN)
|
LF
|
420.000
|
$1,000.000
|
$900.000
|
$644.780
|
$640.000
|
$625.000
|
$642.930
|
$700.000
|
$655.000
|
$800.000
|
$682.570
|
$675.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
32.000
|
$275.000
|
$360.000
|
$330.000
|
$350.000
|
$250.000
|
$356.180
|
$380.000
|
$360.000
|
$275.000
|
$409.540
|
$356.180
|
|
|
CL C CONC (ABUT)
|
CY
|
116.800
|
$1,300.000
|
$1,061.200
|
$1,500.000
|
$1,400.000
|
$1,250.000
|
$1,114.000
|
$1,000.000
|
$1,500.000
|
$1,350.000
|
$1,820.170
|
$1,500.000
|
|
|
CL C CONC (CAP)
|
CY
|
175.800
|
$1,600.000
|
$964.600
|
$1,400.000
|
$1,400.000
|
$1,600.000
|
$1,323.020
|
$1,400.000
|
$1,400.000
|
$1,350.000
|
$1,679.380
|
$1,550.000
|
|
|
CL C CONC (CAP)(MASS)
|
CY
|
248.000
|
$1,500.000
|
$880.600
|
$1,200.000
|
$1,400.000
|
$1,625.000
|
$1,006.330
|
$1,500.000
|
$1,200.000
|
$1,350.000
|
$1,276.130
|
$1,750.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
242.000
|
$1,500.000
|
$718.200
|
$1,200.000
|
$1,100.000
|
$1,350.000
|
$1,155.930
|
$1,300.000
|
$1,100.000
|
$1,350.000
|
$758.140
|
$1,500.000
|
|
|
CL C CONC (COLUMN)(MASS)
|
CY
|
520.000
|
$1,500.000
|
$667.800
|
$1,200.000
|
$960.000
|
$1,500.000
|
$896.820
|
$1,350.000
|
$975.000
|
$1,200.000
|
$811.660
|
$2,000.000
|
|
|
REINF CONC SLAB
|
SF
|
74,001.000
|
$25.000
|
$20.000
|
$24.800
|
$25.000
|
$23.500
|
$30.300
|
$24.500
|
$25.000
|
$29.000
|
$18.180
|
$25.000
|
|
|
APPROACH SLAB
|
CY
|
77.000
|
$159.000
|
$1,178.800
|
$650.000
|
$905.000
|
$650.000
|
$849.790
|
$1,000.000
|
$900.000
|
$1,000.000
|
$963.240
|
$1,750.000
|
|
|
PRESTR CONC GIRDER (TX70)
|
LF
|
8,850.420
|
$300.000
|
$245.000
|
$221.750
|
$315.000
|
$300.000
|
$232.590
|
$225.000
|
$320.000
|
$250.000
|
$439.450
|
$350.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
2.300
|
$600.000
|
$900.000
|
$1,000.000
|
$880.000
|
$800.000
|
$1,079.980
|
$1,400.000
|
$750.000
|
$650.000
|
$617.560
|
$3,000.000
|
|
|
RIPRAP (CONC)(CL B)
|
CY
|
1.600
|
$650.000
|
$900.000
|
$1,000.000
|
$840.000
|
$800.000
|
$1,427.080
|
$2,500.000
|
$720.000
|
$650.000
|
$618.240
|
$4,000.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
55.000
|
$640.000
|
$465.000
|
$750.000
|
$730.000
|
$525.000
|
$604.520
|
$400.000
|
$650.000
|
$650.000
|
$653.870
|
$850.000
|
|
|
RIPRAP (CONC)(CL B)(RR8&RR9)
|
CY
|
635.000
|
$650.000
|
$435.000
|
$650.000
|
$690.000
|
$500.000
|
$364.070
|
$640.000
|
$650.000
|
$650.000
|
$832.760
|
$650.000
|
|
|
RAIL (TY SSTR)
|
LF
|
3,040.000
|
$75.000
|
$80.400
|
$100.000
|
$78.000
|
$98.000
|
$66.670
|
$75.000
|
$80.000
|
$120.000
|
$83.150
|
$75.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
295.000
|
$220.000
|
$253.400
|
$250.000
|
$270.000
|
$250.000
|
$190.930
|
$280.000
|
$275.000
|
$225.000
|
$283.050
|
$215.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)
|
LF
|
61.000
|
$450.000
|
$483.000
|
$475.000
|
$630.000
|
$475.000
|
$382.180
|
$700.000
|
$645.000
|
$450.000
|
$751.240
|
$600.000
|
|
|
SET (TY I)(S= 3 FT)(HW= 3 FT)(3:1)(C)
|
EA
|
2.000
|
$6,300.000
|
$7,850.000
|
$7,250.000
|
$5,060.000
|
$10,200.000
|
$7,216.190
|
$16,000.000
|
$5,000.000
|
$5,000.000
|
$9,744.270
|
$25,000.000
|
|
|
REMOV STR (BOX CULVERT)
|
EA
|
1.000
|
$7,000.000
|
$3,500.000
|
$2,500.000
|
$2,130.000
|
$17,600.000
|
$1,580.340
|
$7,000.000
|
$2,000.000
|
$2,500.000
|
$97.030
|
$4,000.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
2.000
|
$2,000.000
|
$900.000
|
$900.000
|
$750.000
|
$1,100.000
|
$1,466.260
|
$2,500.000
|
$725.000
|
$1,000.000
|
$2,603.500
|
$3,000.000
|
|
|
REMOV STR (BRIDGE 1000 FT OR GREATER)
|
EA
|
1.000
|
$2,000,000.000
|
$450,000.000
|
$1,240,000.000
|
$1,050,000.000
|
$504,000.000
|
$1,000,000.000
|
$350,000.000
|
$1,150,000.000
|
$1,350,000.000
|
$1,217,807.350
|
$1,000,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,633,200.000
|
$900,000.000
|
$1,449,741.040
|
$1,700,000.000
|
$1,600,000.000
|
$1,600,000.000
|
$1,374,000.000
|
$1,750,000.000
|
$1,400,000.000
|
$1,374,214.210
|
$2,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
15.000
|
$5,000.000
|
$3,500.000
|
$2,000.000
|
$2,630.000
|
$2,100.000
|
$3,480.320
|
$30,000.000
|
$15,000.000
|
$3,000.000
|
$1,530.600
|
$3,800.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$15,000.000
|
$5,000.000
|
$18,000.000
|
$13,850.000
|
$10,866.700
|
$50,000.000
|
$20,000.000
|
$15,000.000
|
$7,500.000
|
$5,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
30.000
|
$200.000
|
$300.000
|
$150.000
|
$316.000
|
$235.000
|
$232.000
|
$500.000
|
$375.000
|
$200.000
|
$165.000
|
$200.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
160.000
|
$100.000
|
$80.000
|
$100.000
|
$76.000
|
$400.000
|
$63.560
|
$150.000
|
$80.000
|
$200.000
|
$215.000
|
$250.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
100.000
|
$38.000
|
$43.000
|
$65.000
|
$42.000
|
$40.000
|
$40.000
|
$100.000
|
$40.000
|
$50.000
|
$55.100
|
$44.400
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
100.000
|
$15.000
|
$16.120
|
$15.000
|
$16.000
|
$15.000
|
$15.000
|
$50.000
|
$15.000
|
$10.000
|
$14.640
|
$11.800
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
444.000
|
$30.000
|
$43.000
|
$40.000
|
$43.000
|
$40.000
|
$40.000
|
$75.000
|
$40.000
|
$35.000
|
$34.030
|
$35.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
444.000
|
$15.000
|
$12.900
|
$12.000
|
$13.000
|
$12.000
|
$12.000
|
$40.000
|
$12.000
|
$5.000
|
$12.160
|
$20.000
|
|
|
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
|
CY
|
150.000
|
$30.000
|
$50.000
|
$32.800
|
$46.000
|
$12.500
|
$26.280
|
$35.000
|
$130.000
|
$50.000
|
$12.850
|
$25.000
|
|
|
BACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
120.000
|
$100.000
|
$80.000
|
$77.000
|
$190.000
|
$65.000
|
$85.100
|
$200.000
|
$120.000
|
$40.000
|
$19.270
|
$100.000
|
|
|
FRNT END LOADER WORK (ERSN & SEDM CONT)
|
HR
|
120.000
|
$200.000
|
$80.000
|
$77.000
|
$134.000
|
$90.000
|
$99.270
|
$210.000
|
$150.000
|
$40.000
|
$25.570
|
$135.000
|
|
|
BLADING WORK (EROSION & SEDMT CONT)
|
HR
|
120.000
|
$145.000
|
$100.000
|
$77.000
|
$165.000
|
$165.000
|
$166.970
|
$250.000
|
$190.000
|
$40.000
|
$24.890
|
$200.000
|
|
|
BULLDOZER WORK (EROSION & SEDMT CONT)
|
HR
|
120.000
|
$100.000
|
$100.000
|
$77.000
|
$112.000
|
$150.000
|
$111.790
|
$300.000
|
$340.000
|
$40.000
|
$19.330
|
$300.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
10,255.000
|
$5.000
|
$4.830
|
$4.500
|
$5.000
|
$5.000
|
$4.500
|
$5.000
|
$4.500
|
$6.000
|
$6.210
|
$6.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
10,255.000
|
$1.500
|
$0.800
|
$0.750
|
$0.800
|
$1.000
|
$0.750
|
$2.000
|
$1.000
|
$1.000
|
$0.620
|
$1.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
4,761.000
|
$90.000
|
$80.000
|
$42.480
|
$91.000
|
$80.000
|
$66.190
|
$100.000
|
$95.000
|
$60.000
|
$121.900
|
$100.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
6,600.000
|
$50.000
|
$25.000
|
$30.000
|
$30.000
|
$50.000
|
$29.610
|
$15.000
|
$80.000
|
$65.000
|
$79.170
|
$55.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
4,650.000
|
$9.500
|
$8.000
|
$15.000
|
$1.600
|
$4.500
|
$1.480
|
$2.000
|
$6.500
|
$10.000
|
$13.660
|
$5.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
6,600.000
|
$12.000
|
$25.000
|
$15.000
|
$14.500
|
$36.750
|
$6.140
|
$2.000
|
$33.000
|
$20.000
|
$20.750
|
$15.000
|
|
|
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
|
LF
|
8,600.000
|
$0.500
|
$0.570
|
$0.750
|
$0.500
|
$0.400
|
$0.530
|
$0.720
|
$0.500
|
$0.750
|
$0.180
|
$0.530
|
|
|
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
|
LF
|
8,600.000
|
$0.500
|
$0.570
|
$0.750
|
$0.500
|
$0.400
|
$0.530
|
$0.720
|
$0.500
|
$0.750
|
$0.470
|
$0.530
|
|
|
FILL MILLED ASPH RUMBLE STRIPS (SHLDR)
|
LF
|
5,780.000
|
$2.250
|
$2.000
|
$2.950
|
$8.500
|
$2.500
|
$3.000
|
$4.110
|
$2.250
|
$5.000
|
$4.340
|
$15.000
|
|
|
FILL MILLED ASPH RMBL STRIP(CENTERLINE)
|
LF
|
5,130.000
|
$4.000
|
$2.000
|
$2.950
|
$9.000
|
$2.500
|
$3.000
|
$4.110
|
$2.500
|
$5.000
|
$4.340
|
$15.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
650.000
|
$26.000
|
$33.000
|
$30.700
|
$32.000
|
$30.750
|
$25.550
|
$42.080
|
$55.000
|
$30.000
|
$38.100
|
$30.700
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$3,000.000
|
$2,480.020
|
$2,807.000
|
$3,500.000
|
$237.000
|
$1,772.830
|
$3,162.110
|
$2,700.000
|
$1,500.000
|
$2,863.060
|
$2,307.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
4,300.000
|
$2.500
|
$2.680
|
$2.500
|
$2.600
|
$2.500
|
$2.610
|
$3.430
|
$10.000
|
$3.000
|
$3.100
|
$2.500
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$300.000
|
$349.370
|
$325.000
|
$345.000
|
$325.000
|
$156.430
|
$445.470
|
$1,050.000
|
$250.000
|
$403.340
|
$325.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,400.000
|
$4,085.000
|
$3,800.000
|
$4,040.000
|
$3,800.000
|
$3,519.580
|
$5,208.510
|
$2,700.000
|
$3,300.000
|
$4,715.920
|
$3,800.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$260.000
|
$376.250
|
$350.000
|
$370.000
|
$350.000
|
$208.570
|
$479.730
|
$1,050.000
|
$250.000
|
$434.360
|
$350.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,300.000
|
$700.000
|
$1,500.000
|
$260.000
|
$827.000
|
$2,607.100
|
$2,055.990
|
$250.000
|
$2,000.000
|
$2,911.380
|
$1,500.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
4.000
|
$1,000.000
|
$215.000
|
$1,200.000
|
$200.000
|
$827.000
|
$1,042.840
|
$1,644.790
|
$200.000
|
$1,000.000
|
$1,164.040
|
$1,200.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
4.000
|
$10,000.000
|
$8,500.000
|
$8,400.000
|
$6,000.000
|
$6,500.000
|
$9,385.540
|
$11,513.540
|
$6,000.000
|
$7,500.000
|
$9,088.020
|
$8,400.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
5.000
|
$800.000
|
$1,021.250
|
$950.000
|
$1,000.000
|
$950.000
|
$950.000
|
$1,441.010
|
$1,000.000
|
$1,000.000
|
$1,178.980
|
$950.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
1.000
|
$850.000
|
$1,612.500
|
$1,500.000
|
$1,600.000
|
$1,500.000
|
$1,500.000
|
$2,275.280
|
$1,500.000
|
$1,700.000
|
$1,861.550
|
$1,500.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GF2(BI)
|
EA
|
20.000
|
$35.000
|
$102.120
|
$95.000
|
$100.000
|
$95.000
|
$95.000
|
$144.100
|
$100.000
|
$100.000
|
$124.000
|
$95.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
|
EA
|
18.000
|
$31.000
|
$134.370
|
$125.000
|
$133.000
|
$125.000
|
$125.000
|
$189.610
|
$130.000
|
$125.000
|
$95.000
|
$125.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
|
EA
|
58.000
|
$30.000
|
$102.120
|
$95.000
|
$100.000
|
$18.000
|
$95.000
|
$87.980
|
$100.000
|
$100.000
|
$110.000
|
$95.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
2.000
|
$100.000
|
$161.250
|
$150.000
|
$160.000
|
$150.000
|
$150.000
|
$227.540
|
$150.000
|
$150.000
|
$88.000
|
$150.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
24,010.000
|
$2.000
|
$0.450
|
$0.420
|
$0.500
|
$0.400
|
$0.420
|
$0.580
|
$0.500
|
$0.550
|
$0.520
|
$0.420
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
24,010.000
|
$3.000
|
$0.450
|
$0.420
|
$0.500
|
$0.400
|
$0.420
|
$0.580
|
$0.500
|
$0.550
|
$0.520
|
$0.420
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
1,201.000
|
$1.250
|
$6.000
|
$1.600
|
$1.800
|
$1.500
|
$2.000
|
$0.690
|
$0.900
|
$1.000
|
$0.620
|
$3.150
|
|
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
|
LF
|
15,498.000
|
$1.000
|
$1.010
|
$0.940
|
$1.000
|
$1.000
|
$0.940
|
$1.290
|
$0.950
|
$1.250
|
$1.170
|
$0.940
|
|
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
|
LF
|
14,484.000
|
$1.000
|
$1.010
|
$0.940
|
$1.000
|
$1.000
|
$0.940
|
$1.290
|
$0.950
|
$1.250
|
$1.170
|
$0.940
|
|
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
|
LF
|
260.000
|
$1.000
|
$3.760
|
$3.500
|
$3.700
|
$3.500
|
$3.500
|
$4.800
|
$3.500
|
$4.000
|
$4.340
|
$3.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
390.000
|
$4.000
|
$16.120
|
$15.000
|
$16.000
|
$15.000
|
$15.000
|
$20.560
|
$15.000
|
$27.000
|
$18.620
|
$15.000
|
|
|
TREE REMOVAL (12" - 18" DIA)
|
EA
|
12.000
|
$100.000
|
$967.500
|
$972.000
|
$960.000
|
$900.000
|
$170.520
|
$1,500.000
|
$850.000
|
$250.000
|
$1,116.930
|
$711.110
|
|
|
TREE REMOVAL (18" - 24" DIA)
|
EA
|
5.000
|
$145.000
|
$1,655.500
|
$1,663.200
|
$1,640.010
|
$1,500.000
|
$204.620
|
$2,000.000
|
$1,200.000
|
$300.000
|
$1,911.190
|
$853.340
|
|
|
TREE REMOVAL (30" - 36" DIA)
|
EA
|
9.000
|
$210.000
|
$1,827.500
|
$1,836.000
|
$1,810.000
|
$1,700.000
|
$216.490
|
$2,500.000
|
$1,100.000
|
$350.000
|
$2,109.750
|
$948.150
|
|
|
TREE REMOVAL (36" - 42" DIA)
|
EA
|
2.000
|
$225.000
|
$2,150.000
|
$2,160.000
|
$2,130.000
|
$2,000.000
|
$462.660
|
$3,000.000
|
$3,500.000
|
$450.000
|
$2,482.060
|
$2,133.350
|
|
|
TREE REMOVAL (42" - 48" DIA)
|
EA
|
1.000
|
$375.000
|
$3,010.000
|
$3,024.000
|
$2,930.000
|
$2,800.000
|
$925.310
|
$4,000.000
|
$3,500.000
|
$500.000
|
$3,474.890
|
$2,133.340
|
|
|
TREE REMOVAL (60" - 72" DIA)
|
EA
|
2.000
|
$500.000
|
$3,655.000
|
$3,672.000
|
$3,600.000
|
$3,400.000
|
$1,752.790
|
$6,000.000
|
$7,000.000
|
$600.000
|
$4,219.500
|
$4,266.670
|
|
|
BONDING COURSE
|
GAL
|
4,929.000
|
$5.000
|
$5.000
|
$3.190
|
$4.500
|
$4.500
|
$4.550
|
$6.170
|
$4.000
|
$5.000
|
$11.040
|
$4.990
|
|
|
TIP TESTING(DRILL SHAFT)
|
EA
|
4.000
|
$5,600.000
|
$6,600.000
|
$35,000.000
|
$9,000.000
|
$8,000.000
|
$9,459.860
|
$11,802.110
|
$9,000.000
|
$5,000.000
|
$8,687.210
|
$8,875.910
|
|
|
REMOVE LEAD-CONTAINING COATING (OTHER)
|
LS
|
1.000
|
$100,000.000
|
$50,000.000
|
$5,000.000
|
$42,500.000
|
$250,000.000
|
$313,766.000
|
$261,447.880
|
$45,000.000
|
$10,000.000
|
$193,600.690
|
$313,766.000
|
|
|
SOLAR-POWERED LED RDWY LUM ASSEMBLIES
|
EA
|
11.000
|
$12,000.000
|
$12,265.750
|
$10,500.000
|
$11,100.000
|
$13,860.000
|
$11,332.940
|
$15,533.600
|
$12,000.000
|
$20,000.000
|
$13,030.820
|
$11,332.940
|
|
Totals: |
$17,896,171.150
|
$13,786,606.520
|
$14,520,387.555
|
$16,071,101.830
|
$16,122,618.000
|
$16,236,815.856
|
$17,454,137.590
|
$18,011,532.900
|
$18,212,971.200
|
$19,455,980.231
|
$21,284,802.930
|