PREPARING ROW
|
STA
|
52.550
|
$750.000
|
$496.170
|
$7,000.000
|
$520.000
|
$8,500.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (6")
|
SY
|
8,822.000
|
$3.000
|
$3.490
|
$1.500
|
$2.400
|
$1.500
|
|
|
REMOVING STAB BASE & ASPH PAV (12")
|
SY
|
6,580.000
|
$5.000
|
$7.000
|
$3.000
|
$5.000
|
$5.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
7,317.000
|
$9.000
|
$12.180
|
$9.000
|
$8.000
|
$5.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY A)
|
CY
|
19,133.000
|
$15.000
|
$14.280
|
$18.000
|
$16.000
|
$18.500
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
22,928.000
|
$0.990
|
$1.090
|
$4.000
|
$1.000
|
$1.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
30,868.000
|
$0.120
|
$0.190
|
$0.209
|
$0.200
|
$0.350
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
SY
|
30,868.000
|
$0.100
|
$0.150
|
$0.170
|
$0.150
|
$0.260
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
5,208.000
|
$50.000
|
$50.930
|
$52.000
|
$52.000
|
$50.000
|
|
|
LIME (HYD, COM, OR QK(SLURRY))
|
TON
|
251.000
|
$194.070
|
$173.250
|
$175.000
|
$188.000
|
$155.000
|
|
|
LIME TRT (SUBGRADE)(6")
|
SY
|
16,838.000
|
$2.500
|
$1.940
|
$3.000
|
$5.000
|
$4.500
|
|
|
PRIME COAT (MC-30)
|
GAL
|
3,054.000
|
$5.000
|
$4.470
|
$3.760
|
$4.000
|
$5.000
|
|
|
CEM STABIL BKFL
|
CY
|
332.200
|
$100.000
|
$240.910
|
$200.000
|
$150.000
|
$165.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
1,754.000
|
$200.000
|
$202.650
|
$170.000
|
$210.000
|
$200.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
3,312.000
|
$225.000
|
$254.320
|
$250.000
|
$250.000
|
$300.000
|
|
|
CL C CONC (ABUT)
|
CY
|
125.400
|
$950.000
|
$1,000.000
|
$1,148.000
|
$1,200.000
|
$1,200.000
|
|
|
CL C CONC (CAP)
|
CY
|
399.200
|
$900.000
|
$1,000.000
|
$1,129.620
|
$1,300.000
|
$1,200.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
139.800
|
$950.000
|
$1,000.000
|
$1,211.520
|
$1,600.000
|
$1,200.000
|
|
|
REINF CONC SLAB
|
SF
|
59,850.000
|
$25.000
|
$22.000
|
$22.000
|
$22.000
|
$20.000
|
|
|
REINF CONC SLAB (SLAB BEAM)
|
SF
|
14,700.000
|
$20.000
|
$22.000
|
$13.650
|
$17.000
|
$17.500
|
|
|
APPROACH SLAB
|
CY
|
192.600
|
$550.000
|
$600.000
|
$821.800
|
$780.000
|
$600.000
|
|
|
RETAINING WALL (CONC BLOCK)
|
SF
|
11,912.000
|
$42.000
|
$30.000
|
$29.000
|
$39.300
|
$50.000
|
|
|
PRESTR CONC SLAB BEAM (4SB12)
|
LF
|
1,382.000
|
$160.000
|
$135.000
|
$115.000
|
$140.000
|
$130.000
|
|
|
PRESTR CONC SLAB BEAM (5SB12)
|
LF
|
1,727.500
|
$160.000
|
$135.000
|
$115.000
|
$135.000
|
$130.000
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
8,493.120
|
$150.000
|
$135.000
|
$115.000
|
$140.000
|
$125.000
|
|
|
PENETRATING CONCRETE SURFACE TREATMENT
|
SY
|
2,154.000
|
$14.000
|
$4.930
|
$5.000
|
$5.000
|
$12.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
565.000
|
$160.000
|
$235.000
|
$105.000
|
$130.000
|
$285.000
|
|
|
RIPRAP (CONC)(FLUME)
|
CY
|
164.000
|
$492.830
|
$500.000
|
$425.000
|
$490.000
|
$600.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
189.000
|
$436.000
|
$600.000
|
$450.000
|
$490.000
|
$525.000
|
|
|
RAIL (TY T223)
|
LF
|
3,670.000
|
$120.000
|
$100.000
|
$72.000
|
$103.000
|
$115.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
228.000
|
$95.000
|
$100.000
|
$65.000
|
$115.000
|
$100.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
373.000
|
$130.000
|
$125.000
|
$90.000
|
$107.000
|
$120.000
|
|
|
INLET (COMPL) (DROP) (SPL)
|
EA
|
2.000
|
$5,758.000
|
$2,000.000
|
$6,500.000
|
$4,060.000
|
$7,500.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
28.000
|
$1,600.000
|
$25.000
|
$900.000
|
$485.000
|
$100.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
483.000
|
$60.000
|
$115.000
|
$60.000
|
$80.000
|
$75.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$60,000.000
|
$45,000.000
|
$45,000.000
|
$37,300.000
|
$25,000.000
|
|
|
REMOVE STR (RAIL)
|
LF
|
216.000
|
$38.130
|
$10.000
|
$50.000
|
$40.000
|
$10.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$912,359.940
|
$868,449.970
|
$825,000.000
|
$827,000.000
|
$795,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$7,500.000
|
$3,277.170
|
$7,500.000
|
$1,700.000
|
$5,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
1,911.000
|
$42.390
|
$56.650
|
$67.180
|
$61.000
|
$60.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,911.000
|
$19.630
|
$16.480
|
$24.180
|
$14.000
|
$15.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
222.000
|
$17.380
|
$17.510
|
$38.700
|
$37.000
|
$31.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
222.000
|
$5.310
|
$2.060
|
$19.350
|
$19.000
|
$10.500
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
810.000
|
$2.500
|
$3.600
|
$4.250
|
$3.000
|
$4.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
810.000
|
$0.820
|
$1.030
|
$2.090
|
$2.000
|
$0.750
|
|
|
DRIVEWAYS (ACP)
|
SY
|
131.000
|
$31.000
|
$48.180
|
$65.000
|
$50.000
|
$45.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
6,115.000
|
$0.170
|
$0.420
|
$0.380
|
$0.250
|
$0.250
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
1,900.000
|
$0.190
|
$0.470
|
$0.380
|
$0.300
|
$0.250
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
2,837.500
|
$22.000
|
$19.500
|
$20.970
|
$20.000
|
$20.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
12.000
|
$1,800.000
|
$1,450.000
|
$1,558.750
|
$2,000.000
|
$1,800.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,000.000
|
$1.700
|
$1.750
|
$1.880
|
$1.800
|
$1.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
8.000
|
$174.420
|
$175.000
|
$188.250
|
$180.000
|
$150.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$275.000
|
$115.000
|
$123.620
|
$118.000
|
$100.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
10.000
|
$3,000.000
|
$2,550.000
|
$2,741.250
|
$2,600.000
|
$2,600.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
211.000
|
$22.450
|
$16.000
|
$30.100
|
$29.000
|
$17.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
21.000
|
$425.770
|
$568.000
|
$483.750
|
$460.000
|
$575.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
8.000
|
$70.960
|
$85.000
|
$91.370
|
$87.000
|
$50.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
44.000
|
$22.490
|
$26.000
|
$17.200
|
$16.000
|
$25.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
12.000
|
$72.000
|
$68.000
|
$161.250
|
$154.000
|
$70.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
26.000
|
$33.280
|
$32.000
|
$34.400
|
$33.000
|
$30.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
6,710.000
|
$0.220
|
$0.480
|
$0.520
|
$0.500
|
$0.300
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
6,710.000
|
$0.220
|
$0.480
|
$0.520
|
$0.500
|
$0.300
|
|
|
PAVEMENT SEALER 4"
|
LF
|
1,560.000
|
$0.100
|
$0.350
|
$0.370
|
$0.400
|
$0.520
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
10,410.000
|
$0.310
|
$0.600
|
$0.650
|
$0.600
|
$0.520
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
138.000
|
$0.220
|
$0.650
|
$0.700
|
$0.700
|
$2.100
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
9,560.000
|
$0.380
|
$0.600
|
$0.650
|
$0.600
|
$0.520
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
139.000
|
$3.000
|
$6.000
|
$6.450
|
$6.000
|
$12.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
1,560.000
|
$0.050
|
$0.150
|
$0.160
|
$0.150
|
$0.520
|
|
|
SP MIXES SP-B SAC-B PG70-22
|
TON
|
2,536.000
|
$120.000
|
$74.160
|
$96.600
|
$80.000
|
$100.000
|
|
|
SP MIXES SP-C SAC-A PG76-22
|
TON
|
1,661.000
|
$130.000
|
$90.360
|
$120.750
|
$100.000
|
$115.000
|
|
|
BONDING COURSE
|
GAL
|
2,287.000
|
$3.000
|
$3.060
|
$5.250
|
$3.000
|
$3.250
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
9.000
|
$8,500.000
|
$7,500.000
|
$16,000.000
|
$9,300.000
|
$5,000.000
|
|
Totals: |
$9,587,228.700
|
$8,978,775.556
|
$9,136,779.467
|
$9,268,028.850
|
$9,758,987.580
|