Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
0196-02-126 DENTON IH 35E 01/08/2025 SEMA CONSTRUCTION, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.02% $43,701.13 29.00% $218,505,647.74
0271-07-326 HARRIS IH 10 08/01/2024 WEBBER, LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.24% $987,105.17 47.00% $411,293,819.00
0195-03-087 DENTON IH 35 04/04/2024 SEMA CONSTRUCTION, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.06% $355,084.06 41.00% $591,806,762.52
0196-02-128 DENTON IH 35E 01/06/2023 SEMA CONSTRUCTION, INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.06% $65,506.36 74.00% $109,177,265.39
0500-04-105 GALVESTON IH 45 08/07/2019 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.24% $410,972.44 88.00% $171,238,516.80
0271-17-161 HARRIS IH 610 08/08/2017 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.50% $1,368,230.69 101.00% $273,646,137.78
0271-04-071 WALLER IH 10 06/07/2017 WILLIAMS BROTHERS CONSTRUCTION CO., INC. 07/26 | 06/26 | 05/26 | 04/26 | 03/26 0.22% $344,915.24 97.00% $156,779,654.01