Bid Cobra

TxDOT Subcontracts for FNH CONSTRUCTION, LLC

Control Number County Highway Bid Date Low Bidder Pay Estimates % of Contract Amount % Complete Contract Amount
0718-02-076 TARRANT FM 156 05/02/2025 GREY SKY CONSTRUCTION LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 6.00% $385,923.44 44.00% $6,432,057.40
0718-02-076 TARRANT FM 156 05/02/2025 GREY SKY CONSTRUCTION LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 15.40% $990,536.84 44.00% $6,432,057.40
0092-04-077 ELLIS IH 45 03/04/2025 GREY SKY CONSTRUCTION LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 6.00% $495,833.94 58.00% $8,263,898.95
0495-07-087 GREGG IH 20 02/07/2025 GREY SKY CONSTRUCTION LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 1.30% $38,907.52 115.00% $2,992,886.20
0495-07-087 GREGG IH 20 02/07/2025 GREY SKY CONSTRUCTION LLC 07/26 | 06/26 | 05/26 | 04/26 | 03/26 7.25% $216,984.25 115.00% $2,992,886.20